Soriano Manufacturing Company uses a standard cost accounting system to account for the manufacturing of exhaust fans. In July 2020, it accumulates the following data for 1,500 units started and finished:
Cost and Production Data |
Actual |
Standard |
---|---|---|
Raw materials |
||
Units purchased |
21,000 |
|
Units used |
21,000 |
22,000 |
Unit cost |
$3.40 |
$3.00 |
Direct labour |
||
Hours worked |
3,450 |
3,600 |
Hourly rate |
$11.80 |
$12.50 |
Manufacturing overhead |
||
Incurred |
$101,500 |
|
Applied |
$108,000 |
Manufacturing overhead was applied based on direct labour hours. Normal capacity for the month was 3,400 direct labour hours. At normal capacity, budgeted overhead costs were $20 per labour hour variable and $10.00 per labour hour fixed. Total budgeted fixed overhead costs were $34,000.
Jobs finished during the month were sold for $280,000. Selling and administrative expenses were $25,000.
Instructions
a.
Calculate all of the variances for direct materials and direct labour.
LQV = $1,875 F
b.
Calculate the total manufacturing overhead variance.
OHV = $6,500 F
c.
Calculate the overhead budget variance and the overhead volume variance.
d.
Prepare an income statement for management showing the variances. Ignore income taxes.
Please explain it well
Soriano Manufacturing Company uses a standard cost accounting system to account for the manufacturing of exhaust...
Franklin Glass Works uses a standard cost system in which manufacturing overhead is applied to units of product on the basis of direct labour-hours. Each unit requires two standard hours of labour for completion. The denominator activity for the year was based on budgeted production of 200,000 units. Total overhead was budgeted at £900,000 for the year, and the fixed overhead rate was £3.00 per unit. The actual data pertaining to the manufacturing overhead for the year are presented below:...
sol th Question 4 (10 marks) The following is the standard cost card for X Company's only product: Direct materials, 4 metres at $4.00 Direct labour, 1.5 hours at $10.00 Variable overhead, 1.5 hours at $3.00 Fixed overhead, 1.5 hours at $7.00 Standard cost per unit $16.00 $15.00 $4.50 $10.50 $46.00 The company manufactured and sold 18 000 units of product during the year. A total of 70,200 metres of material was purchased durine the vear at cost of $4.20...
Zeus Shoe Limited is a manufacturer of ladies shoes and uses a standard costing system. The standard manufacturing overhead cost per shoe are based on direct labour hours and are as follows: Variable Overhead (5 hours @ $24 per hour) $120 Fixed Overhead (5 hours @ $38 per hour) $180 TOTAL OVERHEAD $310 (Based on capacity of 300,000 direct labour hours per month) The following information is available for the month of October. 56,000 shoes were produced, although...
Rondell Company uses a standard cost system. Indirect costs were budgeted at $196,000 plus $15 per direct labour hour. The overhead rate is based on 9,800 hours. Actual results were: Standard direct labour hours allowed 8,780 Actual direct labour hours Fixed overhead Variable overhead 9,800 $189,200 $183,600 Calculate the fixed overhead production volume variance Fixed overhead production volume variance Calculate the variable overhead spending variance. Variable averhead spending variance Calculate the varlable overhead efficlency variance. Variable overhead efficiency variance Calculate...
The Schock Manufacturing Company uses a standard cost system. The standards are set January 1 each year and remain unchanged until December 31 The standard costs set for the next year are: Diret materials S10.00 per unit Direct labor Overhead 7.50 per unit 600 per unit The labor standard above includes a methods change from 2 hours to 1% bours per unit, effective February 28, and a change in labor rates from $4.00 to $5,00 per hour effective February 28....
Concita Ltd. uses a standard cost system and sets predetermined overhead rates on the basis of direct labour hours. The company's budget indicates the following data for the current year. Denominator activity Variable manufacturing overhead (10,000 direct labour hours @$3.42) Fixed manufacturing overhead cost Predetermined overhead rate ($104,200 10,000 direct labour hours) 5,000 units $34,200 $70,000 $10.42 The standard cost card for the company's only product is given below: Standard Quantity Standard price Standard cost or hours Per Unit or...
The Ramirez Company uses standard costing in its manufacturing plant for auto parts. The standard cost of a particular aut part, based on a denominator level of 4.100 output units per year, included 6 machine-hours of variable manufacturing overhead at $8 per hour and 6 machine-hours of fixed manufacturing overhead at $15 per hour. Actual output produced was 4,500 units. Variable manufacturing overhead incurred was $260,000. Fixed manufacturing overhead incurred was $385,000 Actual machine-hours were 28,500. Read the requirements Journal...
managerial accounting, please help Versailles Company produces a product that relies on a standard cost system for planning and control. The following are the standards for producing one unit of product. VERSAILLES COMPANY STANDARDS FOR PRODUCTION OF ONE UNIT OF PRODUCT Standard Standard Standard Quantity of Price Cost Input of Input Per Unit Direct Materials 3 units S 10.00 S 30.00 Direct Labor 1.0 hours 8.00 8.00 Variable Manufacturing Overhead 1.0 hours 5.00 5.00 Fixed Manufacturing Overhead 1.0 hours 20.00...
PROBLEM 11-2 Compute variances, and prepare income statement. AAABest Corporation accumulates the following data relative to jobs started and finished during the month of June 2017 Costs and Production Data Actual Standard Raw materials unit cost $2.25 $2.10 Raw materials units used 10.600 10.000 Direct labor payroll $120,960 $120.000 Direct labor hours worked 14,400 15,000 Manufacturing overhead incurred $189,500 Manufacturing overhead applied $193,500 Machine hours expected to be used at normal capacity 42,500 Budgeted fixed overhead for June $55,250 Variable...
Rudd Clothiers is a small company that manufactures tall-men’s suits. The company has used a standard cost accounting system. In May 2017, 10,000 suits were produced. The following standard and actual cost data applied to the month of May when normal capacity was 14,500 direct labor hours. All materials purchased were used. Cost Element Standard (per unit) Actual Direct materials 10 yards at $4.50 per yard $443,080 for 100,700 yards ($4.40 per yard) Direct labor 1.10 hours at $14.00 per...