Question

PROBLEM 11-2 Compute variances, and prepare income statement. AAABest Corporation accumulates the following data relative to

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Solution a:

Direct Material Cost Variance
Actual Cost Standard cost for actual quantity Standard Cost
AQ * AP = AQ * SP = SQ * SP =
10600 $2.25 $23,850.00 10600 $2.10 $22,260.00 10000 $2.10 $21,000.00
$1,590.00 Unfavorable $1,260.00 Unfavorable
Direct Material Price Variance Direct Material Qty variance
Direct material price variance $1,590.00 Unfavorable
Direct material quantity variance $1,260.00 Unfavorable
Total direct material variance $2,850.00 Unfavorable
Direct Labor Cost Variance
Actual Cost Standard cost for actual quantity Standard Cost
AH * AR = AH * SR = SH * SR =
14400 $8.40 $120,960.00 14400 $8.00 $115,200.00 15000 $8.00 $120,000.00
$5,760.00 Unfavorable $4,800.00 Favorable
Direct Labor rate Variance Direct Labor Efficiency Variance
Direct Labor Rate variance $5,760.00 Unfavorable
Direct Labor Efficiency variance $4,800.00 Favorable
Total direct labor variance $960.00 Unfavorable

Solution b:

Total overhead variance = Overhead applied - Actual overhead

= $193,500 - $189,500 = $4,000 Favorable

Add a comment
Know the answer?
Add Answer to:
PROBLEM 11-2 Compute variances, and prepare income statement. AAABest Corporation accumulates the following data relative to...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...

    Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.25 $2.10 Raw materials units 10,600 10,000 Direct labor payroll $120,960 $120,000 Direct labor hours 14,400 15,000 Manufacturing overhead incurred $189,500 Manufacturing overhead applied $193,500 Machine hours expected to be used at normal capacity 42,500 Budgeted fixed overhead for June $55,250 Variable overhead rate per machine hour $3.00 Fixed overhead rate per...

  • Actual Costs and Production Data Standard $2.25 $2.10 Raw materials unit cost Raw materials units 10,600...

    Actual Costs and Production Data Standard $2.25 $2.10 Raw materials unit cost Raw materials units 10,600 10,000 Direct labor payroll $120,960 $120,000 Direct labor hours 15,000 14,400 $189,500 Manufacturing overhead incurred $193,500 Manufacturing overhead applied Machine hours expected to be used at normal capacity 42,500 $55,250 Budgeted fixed overhead for June $3.00 Variable overhead rate per machine hour $1.30 Fixed overhead rate per machine hour Overhead is applied on the basis of standard machine hours. 3.00 hours of machine time...

  • Problem 23-2A (Part Level Submission) Ayala Corporation accumulates the following data relative to jobs started and...

    Problem 23-2A (Part Level Submission) Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017 CALCULATOR PRINTER VERSION Standard Costs and Production Data Raw materials unit cost Raw materials units used Direct labor payroll Direct labor hours worked Manufacturing overhead incurred Manufacturing overhead applied Machine hours expected to be used at normal capacity Budgeted fixed overhead for June Variable overhead rate per machine hour Fixed overhead rate per machine hour Actual $2.20...

  • Sarasota Corporation accumulates the following data relative to jobs started and finished during the month of...

    Sarasota Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.30 $2.15 Raw materials units used 11,400 10,500 Direct labor payroll $172,840 $168,720 Direct labor hours worked 14,900 15,200 Manufacturing overhead incurred $223,276 Manufacturing overhead applied $226,176 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $73,950 Variable overhead rate per machine hour $3.10 Fixed overhead...

  • Sarasota Corporation accumulates the following data relative to jobs started and finished during the month of...

    Sarasota Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.30 $2.15 Raw materials units used 11,400 10,500 Direct labor payroll $172,840 $168,720 Direct labor hours worked 14,900 15,200 Manufacturing overhead incurred $223,276 Manufacturing overhead applied $226,176 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $73,950 Variable overhead rate per machine hour $3.10 Fixed overhead...

  • Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...

    Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017. Costs and Production Data Actual Standard Raw materials unit cost $2.20 $2.00 Raw materials units used 11,200 10,300 Direct labor payroll $175,820 $169,830 Direct labor hours worked 14,900 15,300 Manufacturing overhead incurred $202,750 Manufacturing overhead applied $206,550 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $65,250 Variable overhead rate per machine hour $3.00 Fixed overhead...

  • Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of...

    Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.30 $2.20 Raw materials units 11,100 10,300 Direct labor payroll $170,200 $164,160 15,200 Direct labor hours 14,800 $202.600 Manufacturing overhead incurred $205,200 Manufacturing overhead applied Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $65,250 Variable overhead rate per machine hour $3.00 Fixed overhead rate per...

  • Ayala Corporation accumulates the following data relative to jobs started and finished during the month of...

    Ayala Corporation accumulates the following data relative to jobs started and finished during the month of June 2017 Costs and Production Data Raw materials unit cost Raw materials units used Direct labor payroll Direct labor hours worked Manufacturing overhead incurred Manufacturing overhead applied Machine hours expected to be used at normal capacity Budgeted fixed overhead for June Variable overhead rate per machine hour Fixed overhead rate per machine hour Actual Standard $2.10 $1.90 11,300 10,700 $175,500 $171,360 15.000 15.300 $212,930...

  • Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of...

    Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.30 $2.20 Raw materials units 11,100 10,300 Direct labor payroll $170,200 $164,160 Direct labor hours 14,800 15,200 Manufacturing overhead incurred $202,600 Manufacturing overhead applied $205,200 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $65,250 Variable overhead rate per machine hour $3.00 Fixed overhead rate per...

  • Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of...

    Pharoah Corporation accumulates the following data relative to jobs started and finished during the month of June 2020. Costs and Production Data Actual Standard Raw materials unit cost $2.30 $2.20 Raw materials units 11,100 10,300 Direct labor payroll $170,200 $164,160 Direct labor hours 14,800 15,200 Manufacturing overhead incurred $202,600 Manufacturing overhead applied $205,200 Machine hours expected to be used at normal capacity 43,500 Budgeted fixed overhead for June $65,250 Variable overhead rate per machine hour $3.00 Fixed overhead rate per...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT