Question

Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units...

Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 52,200 machine hours per year, which represents 26,100 units of output. Annual budgeted fixed factory overhead costs are $261,000 and the budgeted variable factory overhead cost rate is $2.70 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was 19,700 units, which took 41,200 machine hours. Actual fixed factory overhead costs for the year amounted to $253,800 while the actual variable overhead cost per unit was $2.60.

Based on the information provided above, calculate the following factory overhead variances for the year. Indicate whether each variance is favorable (F) or unfavorable (U). (Do not round intermediate calculations. Round your final answers to nearest whole dollar amount.)

a. Total overhead Variance
b. Total flexible-budget Variance
c. Production Volume Variance

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Standard time for producing one unit of output = 52,200 / 26,100 = 2 hours per unit of output

Budgeted Fixed Overhead = $2,61,000    

Budgeted overhead absorption rate per hour = $2,61,000 / 52,200 hours = $5 per hour.

Budgeted units produced during the year was 19700 units. Standard hours for 19,700 units = 2 x 19,700 = 39,400 hours.

a) Total Fixed Overhead Variance = standard hours allowed for actual production x standard overhead absorption rate per hour - Actual Fixed overhead cost incurred

= 39,400 hrs. x $5 per hour - $2,53,800 = $56,800 (U).

Standard Variable Overhead rate = $2.70 per unit.

Variable Overhead Variance = Actual output x Standard rate per unit - Actual variable overhead

= 19,700 units x $ 2.70 per unit – 19,700 units x $2.60 per unit = 1,970 (F).

Total Overhead Variance = Total Fixed Overhead Variance + Total Variable Overhead Variance = $56,800 (U) + $1970 (F) = $54,830 (U).

b) When flexible budget will be prepared for actual production of 19700 units, the fixed expense will remain same as the budget i.e. $2,61,000.

Flexible overhead budget total for actual output of 19,700 units = $2,61,000 + 19,700 x $2.70

= $3,14,190.

Actual overhead expense = $2,53,800 + 19,700 x $2.60 = $3,05,020.

Total Flexible budget variance = $3,14,190 - $3,05,020 = $9,170 (F).

c) Production Volume Variance

= (Budgeted Hours - Standard Hours required for actual production) x Standard overhead rate per hour = (52,200 hrs – 19,700 units x 2 hrs /unit) x $5/hr = $64,000

Add a comment
Know the answer?
Add Answer to:
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units...

    Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 50,100 machine hours per year, which represents 25,050 units of output. Annual budgeted fixed factory overhead costs are $250,500 and the budgeted variable factory overhead cost rate is $2.00 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was...

  • Required information The following information applies to the questions displayed below] Patel and Sons Inc. uses...

    Required information The following information applies to the questions displayed below] Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 53,100 machine hours per year, which represents 26,550 units of output. Annual budgeted fixed factory overhead costs are $265,500 and the budgeted variable factory overhead cost rate is $3.00 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed...

  • [The following information applies to the questions displayed below.] Patel and Sons, Inc., uses a standard...

    [The following information applies to the questions displayed below.] Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced. Practical capacity for the plant is defined as 55,800 machine hours per year, which represents 27,900 units of output. Annual budgeted fixed overhead costs are $279,000 and the budgeted variable overhead cost rate is $3.90 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and...

  • Check my work Required information [The following information applies to the questions displayed below.] Patel and Sons...

    Check my work Required information [The following information applies to the questions displayed below.] Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 55,200 machine hours per year, which represents 27,600 units of output. Annual budgeted fixed factory overhead costs are $276,000 and the budgeted variable factory overhead cost rate is $3.70 per unit. Factory overhead costs are applied on the basis of standard...

  • Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates...

    Overhead Variances, Four-Variance Analysis Oerstman, Inc., uses a standard costing system and develops its overhead rates from the current annual budget. The budget is based on an expected annual output of 122,000 units requiring 488,000 direct labor hours. (Practical capacity is 508,000 hours.) Annual budgeted overhead costs total $795,440, of which $566,080 is fixed overhead. A total of 119,100 units using 486,000 direct labor hours were produced during the year. Actual variable overhead costs for the year were $261,000, and...

  • The standard costs and actual costs for factory overhead for the manufacture of 2,900 units of...

    The standard costs and actual costs for factory overhead for the manufacture of 2,900 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.76 per hour Variable overhead 3 hours per unit @ $2.05 per hour Actual Costs Total variable cost, $17,800 Total fixed cost, $8,000 The amount of the fixed factory overhead volume variance is a. $988 unfavorable b. $790 unfavorable c. $790 favorable d. $0

  • The standard costs and actual costs for factory overhead for the manufacture of 2,700 units of...

    The standard costs and actual costs for factory overhead for the manufacture of 2,700 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.76 per hour Variable overhead 3 hours per unit @ $2.02 per hour Actual Costs     Total variable cost, $18,200     Total fixed cost, $8,100 The amount of the total factory overhead cost variance is a.$4,726 favorable b.$3,282 favorable c.$3,282 unfavorable d.$1,838 unfavorable

  • The standard costs and actual costs for factory overhead for the manufacture of 2,700 units of...

    The standard costs and actual costs for factory overhead for the manufacture of 2,700 units of actual production are as follows: Standard Costs 3 hours per unit $0.72 per hour 3 hours per unit@ $2.08 per hour Fixed overhead (based on 10,000 hours) Variable overhead Actual Costs Total variable cost, $18,000 Total fixed cost, $8,200 The amount of the fixed factory overhead volume variance is Oa. $1,368 unfavorable ob. $1,094 unfavorable OC. $0 cd. $1,094 favorable Prevous Next

  • Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 34...

    Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 34 setups and 34,000 machine hours to manufacture 8,500 units for the year. Selected data for 2019 follow: Budgeted fixed factory overhead: Setup cost $ 85,000 Other 186,000 $ 271,000 Total factory overhead cost incurred $ 485,000 Variable factory overhead rate: Per setup $ 400 Per machine hour $ 5.00 Total standard machine hours allowed for the units manufactured 27,000 hours Machine hours actually worked...

  • Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 40...

    Alden Company uses a three-variance analysis for factory overhead variances. Practical capacity is defined as 40 setups and 40,000 machine hours to manufacture 8,000 units for the year. Selected data for 2019 follow: Budgeted fixed factory overhead: Setup cost $ 76,800 Other 230,000 $ 306,800 Total factory overhead cost incurred $ 484,000 Variable factory overhead rate: Per setup $ 550 Per machine hour $ 4.00 Total standard machine hours allowed for the units manufactured 28,000 hours Machine hours actually worked...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT