Question

Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units...

Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 50,100 machine hours per year, which represents 25,050 units of output. Annual budgeted fixed factory overhead costs are $250,500 and the budgeted variable factory overhead cost rate is $2.00 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was 18,500 units, which took 39,100 machine hours. Actual fixed factory overhead costs for the year amounted to $246,100 while the actual variable overhead cost per unit was $1.90.

Based on the information provided above, calculate the following factory overhead variances for the year. Indicate whether each variance is favorable (F) or unfavorable (U). (Do not round intermediate calculations. Round your final answers to nearest whole dollar amount.)

(a) Total overhead variance Unfavorable
(b) Total flexible-budget variance Favorable
(c) Production volume variance $65,500 Unfavorable
Based on the information provided above, provide an appropriate end-of-year closing entry for each of the following two independent situations: (a) the net factory overhead cost variance is closed entirely to Cost of Goods Sold (CSG), and (b) the net factory overhead variance is allocated among WIP Inventory, Finished Goods Inventory, and CGS using the following percentages: 20%, 20%, and 60%, respectively. (Do not round intermediate calculations. Round your final answers to nearest whole dollar amount. If no entry is required for a transaction/event, select "No journal entry required" in the first account field.)
0 0
Add a comment Improve this question Transcribed image text
✔ Recommended Answer
Answer #1
Answer
Standard time for producing one unit of output = 50100 / 25050 = 2 hours per unit of output
Budgeted Fixed Overhead = $250500  
Budgeted overhead absorption rate per hour = $2,50,500 / 50100 hours = $5 per hour.
Budgeted units produced during the year was 18500 units. Standard hours for 18500 units = 2 x 18500 = 37000 hours.
Answer A Total Fixed Overhead Variance = standard hours allowed for actual production x standard overhead absorption rate per hour - Actual Fixed overhead cost incurred
37000 hrs. x $5 per hour - $2,46100 = $61,100 (U).
Standard Variable Overhead rate = $2 per unit.
Variable Overhead Variance = Actual output x Standard rate per unit - Actual variable overhead
18500 units x $ 2. per unit – 18500 units x $1.9 per unit = 1,850 (F).
Total Overhead Variance = Total Fixed Overhead Variance + Total Variable Overhead Variance = $61100 (U) + $1850 (F) = $59250(U).
Answer B When flexible budget will be prepared for actual production of 18500 units, the fixed expense will remain same as the budget i.e. $2,61,000.
Flexible overhead budget total for actual output of 18500 units = $2,50500 + 18500 x $2
$213500
Actual overhead expense = $246100+ 18500 x $1.9 = $210950
Total Flexible budget variance = $213500-$ 210950 = $2550(F).
Answer C Production Volume Variance
(Budgeted Hours - Standard Hours required for actual production) x Standard overhead rate per hour = (50100 hrs – 18500 units x 2 hrs /unit) x $5/hr = $65500
Please hit LIKE button if this helped.
Add a comment
Know the answer?
Add Answer to:
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units...

    Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 52,200 machine hours per year, which represents 26,100 units of output. Annual budgeted fixed factory overhead costs are $261,000 and the budgeted variable factory overhead cost rate is $2.70 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was...

  • Required information The following information applies to the questions displayed below] Patel and Sons Inc. uses...

    Required information The following information applies to the questions displayed below] Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 53,100 machine hours per year, which represents 26,550 units of output. Annual budgeted fixed factory overhead costs are $265,500 and the budgeted variable factory overhead cost rate is $3.00 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed...

  • [The following information applies to the questions displayed below.] Patel and Sons, Inc., uses a standard...

    [The following information applies to the questions displayed below.] Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced. Practical capacity for the plant is defined as 55,800 machine hours per year, which represents 27,900 units of output. Annual budgeted fixed overhead costs are $279,000 and the budgeted variable overhead cost rate is $3.90 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and...

  • Check my work Required information [The following information applies to the questions displayed below.] Patel and Sons...

    Check my work Required information [The following information applies to the questions displayed below.] Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 55,200 machine hours per year, which represents 27,600 units of output. Annual budgeted fixed factory overhead costs are $276,000 and the budgeted variable factory overhead cost rate is $3.70 per unit. Factory overhead costs are applied on the basis of standard...

  • The standard costs and actual costs for factory overhead for the manufacture of 2,700 units of...

    The standard costs and actual costs for factory overhead for the manufacture of 2,700 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.76 per hour Variable overhead 3 hours per unit @ $2.02 per hour Actual Costs     Total variable cost, $18,200     Total fixed cost, $8,100 The amount of the total factory overhead cost variance is a.$4,726 favorable b.$3,282 favorable c.$3,282 unfavorable d.$1,838 unfavorable

  • Under a two-variance breakdown (decomposition) of the total factory overhead variance, the fixed overhead production volume...

    Under a two-variance breakdown (decomposition) of the total factory overhead variance, the fixed overhead production volume variance, to the nearest whole dollar, is: Multiple Choice $400 favorable. $600 unfavorable. $1,400 favorable. $1,400 unfavorable. $2,000 favorable. b. Under a two-variance breakdown (decomposition) of the total factory overhead variance, the total flexible-budget variance, to the nearest whole dollar, is: Multiple Choice $400 favorable. $600 unfavorable. $1,400 favorable. $1,400 unfavorable. $2,000 favorable. The following information for the past year is available from Thinnews...

  • The data related to Shunda Enterprises Inc.’s factory overhead cost for the production of 50,000 units...

    The data related to Shunda Enterprises Inc.’s factory overhead cost for the production of 50,000 units of product are as follows: Actual: Variable factory overhead $263,300 Fixed factory overhead 188,800 Standard: 76,000 hrs. at $6 ($3.50 for variable factory overhead) 456,000 Productive capacity at 100% of normal was 75,000 hours, and the factory overhead cost budgeted at the level of 76,000 standard hours was $453,300. Based on these data, the chief cost accountant prepared the following variance analysis: Variable factory...

  • Factory Overhead Cost Variance Report Tannin Products Inc. prepared the following factory overhead cost budget for...

    Factory Overhead Cost Variance Report Tannin Products Inc. prepared the following factory overhead cost budget for the Trim Department for July of the current year, during which it expected to use 14,000 hours for production: Variable overhead costs: Indirect factory labor $47,600 Power and light 10,360 Indirect materials 15,400    Total variable overhead cost $73,360 Fixed overhead costs: Supervisory salaries $56,430 Depreciation of plant and equipment 14,850 Insurance and property taxes 27,720    Total fixed overhead cost 99,000 Total factory overhead cost...

  • The standard costs and actual costs for factory overhead for the manufacture of 2,900 units of...

    The standard costs and actual costs for factory overhead for the manufacture of 2,900 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.76 per hour Variable overhead 3 hours per unit @ $2.05 per hour Actual Costs Total variable cost, $17,800 Total fixed cost, $8,000 The amount of the fixed factory overhead volume variance is a. $988 unfavorable b. $790 unfavorable c. $790 favorable d. $0

  • The standard costs and actual costs for factory overhead for the manufacture of 2,700 units of...

    The standard costs and actual costs for factory overhead for the manufacture of 2,700 units of actual production are as follows: Standard Costs 3 hours per unit $0.72 per hour 3 hours per unit@ $2.08 per hour Fixed overhead (based on 10,000 hours) Variable overhead Actual Costs Total variable cost, $18,000 Total fixed cost, $8,200 The amount of the fixed factory overhead volume variance is Oa. $1,368 unfavorable ob. $1,094 unfavorable OC. $0 cd. $1,094 favorable Prevous Next

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT