a) Calculation of Total Overhead Variance (Amounts in $)
Budgeted machine hrs required per unit = 53,100 hrs/26,550 units = 2 hrs per unit
Budgeted Fixed overhead cost per hour = Budgeted Fixed Overheads/Budgeted Machine hrs
= $265,500/53,100 hrs = $5 per hour
Budgeted Variable overhead cost per hour = (Budgeted units*Budgeted rate per unit)/Budgeted Machine hrs
= (26,550 units*$3 per unit)/53,100 hrs = $1.50 per hour
Total budgeted overhead cost per hour = $5+$1.50 = $6.50 per hour
Total Overhead Variance = Overhead applied to actual production - Actual Overhead
= (20,500 units*2 per hour*$6.50 per hr) - [(20,500 units*$2.90)+$257,100]
= $266,500 - $316,550 = $50,050 Unfavorable
b) Calculation of Total Flexible Budget Variance
Fixed Overhead Flexible budget variance = Flexible budget based on actual output - Actual Overhead
= $265,500 - $257,100 = $8,400 Favorable
Variable Overhead Flexible budget variance = Flexible budget based on actual output - Actual Overhead
= (20,500*2 hrs*$1.5) - (20,500 units*$2.90)
= $61,500 - $59,450 = $2,050 Favorable
Total Flexible budget variance = $8,400 F+$2,050 F = $10,450 F
c) Calculation of Production Volume Variance
Fixed Overhead Production Volume Variance = Applied Fixed Overhead - Budgeted Fixed Overhead
= (20,500*2 hrs*$5) - 265,500
= $205,000 - $265,500 = $60,500 Unfavorable
a) | Total overhead variance | $50,050 U |
b) | Total flexible budget variance | $10,450 F |
c) | Production volume variance | $60,500 U |
Required information The following information applies to the questions displayed below] Patel and Sons Inc. uses...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 52,200 machine hours per year, which represents 26,100 units of output. Annual budgeted fixed factory overhead costs are $261,000 and the budgeted variable factory overhead cost rate is $2.70 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was...
Check my work Required information [The following information applies to the questions displayed below.] Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 55,200 machine hours per year, which represents 27,600 units of output. Annual budgeted fixed factory overhead costs are $276,000 and the budgeted variable factory overhead cost rate is $3.70 per unit. Factory overhead costs are applied on the basis of standard...
[The following information applies to the questions displayed below.] Patel and Sons, Inc., uses a standard cost system to apply overhead costs to units produced. Practical capacity for the plant is defined as 55,800 machine hours per year, which represents 27,900 units of output. Annual budgeted fixed overhead costs are $279,000 and the budgeted variable overhead cost rate is $3.90 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and...
Patel and Sons Inc. uses a standard cost system to apply factory overhead costs to units produced. Practical capacity for the plant is defined as 50,100 machine hours per year, which represents 25,050 units of output. Annual budgeted fixed factory overhead costs are $250,500 and the budgeted variable factory overhead cost rate is $2.00 per unit. Factory overhead costs are applied on the basis of standard machine hours allowed for units produced. Budgeted and actual output for the year was...
Required information The following information applies to the questions displayed below] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. $4.80 per 1b.) Direct labor (6 hrs. e $14 per hr.) Factory overhead-variable (6 hrs.e $7 per hr.) Factory overhead-fixed (6 hrs. e $12 per hr.) $144.00 84.00 42.00 72.00 Total standard cost $342.00 The predetermined overhead rate is based on a planned operating volume of 80 % of the productive capacity of...
Required information Use the following information for the Problems below. [The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 lbs. @ $4.80 per Ib.) Direct labor (8 hrs. @ $16 per hr.) Factory overhead-variable (8 hrs. @ $9 per hr.) Factory overhead-fixed (8 hrs. @ $12 per hr.) Total standard cost $ 144.00 128.00 72.00 96.00 $ 440.00 The predetermined overhead rate is based on...
Use the following information for the Problems below. (The following information applies to the questions displayed below.) Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $4.40 per Ib.) Direct labor (6 hrs. @ $14 per hr.) Factory overhead-variable (6 hrs. @ $9 per hr.) Factory overhead-fixed (6 hrs. @ $12 per hr.) Total standard cost $132.00 84.00 54.00 72.00 $342.00 $372.00 The predetermined overhead rate is based on a planned operating...
Required information The following Information applies to the questions displayed below] Sedona Company set the following standard costs for one unlt of Its product for 2017 Direct aterial (20 Ibs. $3.30 per Ib. Direct labor (15 hrs. $6.00 per hr.) Eactory variable overhead (15 hrs. $2.80 per hr.) Factory fixed overhead (15 hs $1.20 per hr.) Standard cost 66.00 90.00 42.00 1B.00 $216.00 The $400 ($280-$120) total overhead rate per direct labor hour is based on an expected operating level...
Required information [The following information applies to the questions displayed below.] Sedona Company set the following standard costs for one unit of its product for 2017. Direct material (20 Ibs. @ $3.20 per Ib.) $ 64.00 Direct labor (10 hrs. @ $8.30 per hr.) 83.00 Factory variable overhead (10 hrs. @ $4.70 per hr.) 47.00 Factory fixed overhead (10 hrs. @ $2.30 per hr.) 23.00 Standard cost $ 217.00 The $7.00 ($4.70 + $2.30) total overhead rate per direct labor...
[The following information applies to the questions displayed below.] Trico Company set the following standard unit costs for its single product. Direct materials (30 Ibs. @ $5.10 per Ib.) $ 153.00 Direct labor (8 hrs. @ $14 per hr.) 112.00 Factory overhead—variable (8 hrs. @ $6 per hr.) 48.00 Factory overhead—fixed (8 hrs. @ $12 per hr.) 96.00 Total standard cost $ 409.00 The predetermined overhead rate is based on a planned operating volume of 80% of the productive capacity...