Question

MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows 2019 $290,000 145,000 260,000 240,000 2020 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year $150,000 265,000 285,000 Required 1. Record the preceding transactions in MSKs books assuming it recognizes revenue over time and uses costs incurred to measure the extent to which its performance obligation has been satisfied 2. Record the preceding transactions in MSKs books assuming it recognizes revenue at a point in time when control of the completed factory is transferred to the customer at the end of the project. Answer is not complete Complete this question by entering your answers in the tabs below Required 1Required 2 Record the preceding transactions in MSKs books assuming it recognizes revenue over time and uses costs incurred to measure the extent to which its performance obligation has been satisfied. (If no entry is required for a transaction/event, select No journal entry required in the first account field.) No Date General Journal Debit Credit 2019 Construction in progress 290,000 Cash, payables, materials, etc 290,000

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Credit Debit $290,000 2019 $525,000 2020 $525,000 No. Date General Journal 1 1 2019 Construction in prgress Cash, Payables, m

Add a comment
Know the answer?
Add Answer to:
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and...

    MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and was completed in 20x2. Information relating to the contract follows: 20x1 20x2 Costs incurred during the year $299,000 $ 150,000 Estimated additional cost to complete 15,000 Billings during the year @, eee 265,000 Cash collections during the year 240, eee 285,000 Required: 1. Record the preceding transactions in MSK's books assuming it recognizes revenue over time and uses costs incurred to measure the extent...

  • Saved Help Save & MSK Construction Company contracted to construct a factory building for $525.000. Construction...

    Saved Help Save & MSK Construction Company contracted to construct a factory building for $525.000. Construction started during 20X1 and was completed in 20X2. Information relating to the contract follows: 20x2 $150,000 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year 20x1 $290,000 145,000 260,000 240,000 265,000 285,000 Required: 1. Record the preceding transactions in MSK's books assumingit recognizes revenue over time and uses costs incurred to measure the extent...

  • MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and...

    MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and was completed in 20x2. Information relating to the contract follows: 2ex2 $150,000 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year 2ex1 $290,000 145,000 260,000 240,000 265, eee 285, eee Required: 1. Record the preceding transactions in MSK's books assuming it recognizes revenue over time and uses costs incurred to measure the extent to...

  • Problem 3-3 Revenue recognition over time and at a point in time under ASC Topic 606...

    Problem 3-3 Revenue recognition over time and at a point in time under ASC Topic 606 (LO3-4) MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows: 2020 $150,000 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year 2019 $290,000 145,000 260,000 240,000 265,000 285,000 Required: 1. Record the preceding transactions in MSK's books...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa ...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,542,000 $ 3,772,000 $ 2,074,600 Estimated costs to complete as of year-end 5,658,000 1,886,000 0 Billings during the year 2,020,000 4,294,000 3,686,000 Cash collections during the year 1,810,000 3,800,000 4,390,000 Westgate recognizes revenue over time according to...

  • On July 1, 2019, Grams Construction, Inc. agreed to construct a factory for a customer. The...

    On July 1, 2019, Grams Construction, Inc. agreed to construct a factory for a customer. The contract called for payments to Grams totaling $2 million. Grams has correctly determined that it is appropriate to recognize revenue over time, and it uses its costs as a measure of completion. The same cost information is used to determine the portion of the contract price Grams is entitled to receive. The following information describes the costs incurred and expected remaining costs at December...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: during the year $2,100,000 $2,450,000 $2,695,000 Estimated costs to complete as of year-end Billings during the year Cash collections during the year 4,900,000 2,450,000 2,200,000 2,350,000 5,450,000 1,900,000 2,300,000 5, 800,000 3 28 Westgate recognizes revenue over time according to percentage of completion Required: ances 1....

  • Cady Construction received a contract to construct a hospital for $2,500,000. Construction began in 2019 and...

    Cady Construction received a contract to construct a hospital for $2,500,000. Construction began in 2019 and ended in 2020. Cost and other data are presented below: 2019 2020 Costs incurred during the year $1,500,000 $1,300,000 Estimated costs to complete 1,200,000 0 Billings during the year 1,200,000 1,300,000 Cash collections during the year 1,000,000 1,500,000 What is gross profit recognized during 2020 if Cady recognizes revenue over time according to percentage of completion? a. $100,000 b. $200,000 c. ($200,000) d. $0...

  • On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabr...

    On March 1, 2017, Bonita Construction Company contracted to construct a factory building for Fabrik Manufacturing Inc. for a total contract price of $8,450,000. The building was completed by October 31, 2019. The annual contract costs incurred, estimated costs to complete the contract, and accumulated billings to Fabrik for 2017, 2018, and 2019 are given below: 2017 2018 2019 Contract costs incurred during the year $2,824,800 $2,086,300 $2,418,900 Estimated costs to complete the contract at 12/31 3,595,200 2,418,900 –0– Billings...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT