Question

Saved Help Save & MSK Construction Company contracted to construct a factory building for $525.000. Construction started duri
Required 1 Required 2 Record the preceding transactions in MSKs books assuming it recognizes revenue over time and us extent
Required Required Record the preceding transactions in MSKs books assuming it recognizes revenue at a point factory is trans
0 0
Add a comment Improve this question Transcribed image text
Answer #1
No. Date General Journal Debit Credit
20X1
1. Construction in process 290,000
Cash payables, materials 290,000
2. Accounts receivables 260,000
Billings on Contract 260,000
3. Cash 240,000
Accounts receivables 240,000
4. Construction expense 290,000
Construction in process 60,000
Construction revenue 350,000
20X2
5. Construction in process 150,000
Cash payables, materials 150,000
6. Accounts receivables 265,000
Billings on Contract 265,000
7. Cash 285,000
Accounts receivables 285,000
8. Construction expense 150,000
Construction in process 25,000
Construction revenue 175,000
9. Billings on Contract 525,000
Construction in process 525,000

2)

No. Date General Journal Debit Credit
20X1
1. Construction in process 290,000
Cash payables, materials 290,000
2. Accounts receivables 260,000
Billings on Contract 260,000
3. Cash 240,000
Accounts receivables 240,000
20X2
4. Construction in process 150,000
Cash payables, materials 150,000
5. Accounts receivables 265,000
Billings on Contract 265,000
6. Cash 285,000
Accounts receivables 285,000
7. Construction expense 440,000
Billings on Contract 525,000
Construction in process 440,000
Construction revenue 525,000

Workings:

20X1 20X2
Contract price 525,000 525,000
Less: Estimated cost
Costs incurred to date 290,000 150,000
Estimated cost to complete 145,000
Estimated total costs 435,000 150,000
Estimated gross profit 90,000 375,000
Percentage of completion 66.67% 100%
Gross profit earned 60,000 375,000
Less: Previous gross profit 60,000
Gross profit recognized 60,000 315,000
Add a comment
Know the answer?
Add Answer to:
Saved Help Save & MSK Construction Company contracted to construct a factory building for $525.000. Construction...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and...

    MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and was completed in 20x2. Information relating to the contract follows: 20x1 20x2 Costs incurred during the year $299,000 $ 150,000 Estimated additional cost to complete 15,000 Billings during the year @, eee 265,000 Cash collections during the year 240, eee 285,000 Required: 1. Record the preceding transactions in MSK's books assuming it recognizes revenue over time and uses costs incurred to measure the extent...

  • MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and...

    MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows 2019 $290,000 145,000 260,000 240,000 2020 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year $150,000 265,000 285,000 Required 1. Record the preceding transactions in MSK's books assuming it recognizes revenue over time and uses costs incurred to measure the extent to which its...

  • MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and...

    MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and was completed in 20x2. Information relating to the contract follows: 2ex2 $150,000 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year 2ex1 $290,000 145,000 260,000 240,000 265, eee 285, eee Required: 1. Record the preceding transactions in MSK's books assuming it recognizes revenue over time and uses costs incurred to measure the extent to...

  • Problem 3-3 Revenue recognition over time and at a point in time under ASC Topic 606...

    Problem 3-3 Revenue recognition over time and at a point in time under ASC Topic 606 (LO3-4) MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows: 2020 $150,000 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year 2019 $290,000 145,000 260,000 240,000 265,000 285,000 Required: 1. Record the preceding transactions in MSK's books...

  • Bridgeport, Inc. began work on a $7,043,000 contract in 2020 to construct an office building. During...

    Bridgeport, Inc. began work on a $7,043,000 contract in 2020 to construct an office building. During 2020, Bridgeport, Inc. incurred costs of $1.891,800, billed its customers for $1,315,000, and collected $939,000. At December 31, 2020. the estimated additional costs to complete the project total $3,363.200. Prepare Bridgeport's 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...

  • Please help! On February 1, 2021, Arrow Construction Company entered into a three-vear construction contract to...

    Please help! On February 1, 2021, Arrow Construction Company entered into a three-vear construction contract to build a bridge for a price of $8,200,000. During 2021, costs of $2,080,000 were incurred, with estimated costs of $4,080,000 yet to be incurred. Billings of $2,596,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,596,000 with remaining costs estimated to be $3.720.000. 2022 billings were $2,846,000, and $2,555,000 cash was collected. The project was completed in 2023 after additional...

  • Saved Help Save & Exit Submit Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss...

    Saved Help Save & Exit Submit Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project (LO6-9) On February 1, 2021, Arrow Construction Company entered into a three year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2.130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2,630,000 with remaining costs estimated...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2.130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2.630,000 with remaining costs estimated to be $3,795,000.2022 billings were $2,880,000 and $2,605,000 cash was collected. The project was completed in 2023 after additional costs of $3,930,000...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8.210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705.000. 2022 billings were $2.820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2021, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2022, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2022 billings were $2.990,000, and $2,675,000 cash was collected. The project was completed in 2023 after additional costs of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT