No. | Date | General Journal | Debit | Credit |
20X1 | ||||
1. | Construction in process | 290,000 | ||
Cash payables, materials | 290,000 | |||
2. | Accounts receivables | 260,000 | ||
Billings on Contract | 260,000 | |||
3. | Cash | 240,000 | ||
Accounts receivables | 240,000 | |||
4. | Construction expense | 290,000 | ||
Construction in process | 60,000 | |||
Construction revenue | 350,000 | |||
20X2 | ||||
5. | Construction in process | 150,000 | ||
Cash payables, materials | 150,000 | |||
6. | Accounts receivables | 265,000 | ||
Billings on Contract | 265,000 | |||
7. | Cash | 285,000 | ||
Accounts receivables | 285,000 | |||
8. | Construction expense | 150,000 | ||
Construction in process | 25,000 | |||
Construction revenue | 175,000 | |||
9. | Billings on Contract | 525,000 | ||
Construction in process | 525,000 | |||
2)
No. | Date | General Journal | Debit | Credit |
20X1 | ||||
1. | Construction in process | 290,000 | ||
Cash payables, materials | 290,000 | |||
2. | Accounts receivables | 260,000 | ||
Billings on Contract | 260,000 | |||
3. | Cash | 240,000 | ||
Accounts receivables | 240,000 | |||
20X2 | ||||
4. | Construction in process | 150,000 | ||
Cash payables, materials | 150,000 | |||
5. | Accounts receivables | 265,000 | ||
Billings on Contract | 265,000 | |||
6. | Cash | 285,000 | ||
Accounts receivables | 285,000 | |||
7. | Construction expense | 440,000 | ||
Billings on Contract | 525,000 | |||
Construction in process | 440,000 | |||
Construction revenue | 525,000 |
Workings:
20X1 | 20X2 | |
Contract price | 525,000 | 525,000 |
Less: Estimated cost | ||
Costs incurred to date | 290,000 | 150,000 |
Estimated cost to complete | 145,000 | |
Estimated total costs | 435,000 | 150,000 |
Estimated gross profit | 90,000 | 375,000 |
Percentage of completion | 66.67% | 100% |
Gross profit earned | 60,000 | 375,000 |
Less: Previous gross profit | 60,000 | |
Gross profit recognized | 60,000 | 315,000 |
Saved Help Save & MSK Construction Company contracted to construct a factory building for $525.000. Construction...
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and was completed in 20x2. Information relating to the contract follows: 20x1 20x2 Costs incurred during the year $299,000 $ 150,000 Estimated additional cost to complete 15,000 Billings during the year @, eee 265,000 Cash collections during the year 240, eee 285,000 Required: 1. Record the preceding transactions in MSK's books assuming it recognizes revenue over time and uses costs incurred to measure the extent...
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows 2019 $290,000 145,000 260,000 240,000 2020 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year $150,000 265,000 285,000 Required 1. Record the preceding transactions in MSK's books assuming it recognizes revenue over time and uses costs incurred to measure the extent to which its...
MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 20X1 and was completed in 20x2. Information relating to the contract follows: 2ex2 $150,000 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year 2ex1 $290,000 145,000 260,000 240,000 265, eee 285, eee Required: 1. Record the preceding transactions in MSK's books assuming it recognizes revenue over time and uses costs incurred to measure the extent to...
Problem 3-3 Revenue recognition over time and at a point in time under ASC Topic 606 (LO3-4) MSK Construction Company contracted to construct a factory building for $525,000. Construction started during 2019 and was completed in 2020. Information relating to the contract follows: 2020 $150,000 Costs incurred during the year Estimated additional cost to complete Billings during the year Cash collections during the year 2019 $290,000 145,000 260,000 240,000 265,000 285,000 Required: 1. Record the preceding transactions in MSK's books...
Bridgeport, Inc. began work on a $7,043,000 contract in 2020 to construct an office building. During 2020, Bridgeport, Inc. incurred costs of $1.891,800, billed its customers for $1,315,000, and collected $939,000. At December 31, 2020. the estimated additional costs to complete the project total $3,363.200. Prepare Bridgeport's 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Please help!
On February 1, 2021, Arrow Construction Company entered into a three-vear construction contract to build a bridge for a price of $8,200,000. During 2021, costs of $2,080,000 were incurred, with estimated costs of $4,080,000 yet to be incurred. Billings of $2,596,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,596,000 with remaining costs estimated to be $3.720.000. 2022 billings were $2,846,000, and $2,555,000 cash was collected. The project was completed in 2023 after additional...
Saved Help Save & Exit Submit Exercise 6-21 (Algo) Long-term contract; revenue recognition over time; loss projected on entire project (LO6-9) On February 1, 2021, Arrow Construction Company entered into a three year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2.130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2,630,000 with remaining costs estimated...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2.130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2.630,000 with remaining costs estimated to be $3,795,000.2022 billings were $2,880,000 and $2,605,000 cash was collected. The project was completed in 2023 after additional costs of $3,930,000...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8.210,000. During 2021, costs of $2,070,000 were incurred with estimated costs of $4,070,000 yet to be incurred. Billings of $2,570,000 were sent, and cash collected was $2,320,000. In 2022, costs incurred were $2,570,000 with remaining costs estimated to be $3,705.000. 2022 billings were $2.820,000 and $2,545,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2021, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2022, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2022 billings were $2.990,000, and $2,675,000 cash was collected. The project was completed in 2023 after additional costs of...