a)
D' SALAI COMPANY | ||
Schedule of Cost of Goods Manufactured | ||
For the Month of May | ||
Beginning raw materials | 8500 | |
Add: Raw material purchases | 48000 | |
Raw materials available for use | 56500 | |
Less: Ending raw materials | 4700 | |
Direct materials used | 51800 | |
Direct labor | 24510 | |
Manufacturing overhead applied* | 22610 | |
Total current manufacturing costs | 98920 | |
Add: Beginning work in process** | 13304 | |
Total cost of work in process | 112224 | |
Less: Ending work in process | 19536 | |
Cost of goods manufactured | 92688 |
*Manufacturing overhead applied = 1900 x RM11.90 = RM22610
**Beginning work in process = RM1400 + RM6192 + RM5712 = RM13304
b) Actual manufacturing overhead costs incurred RM21000 - Manufacturing overhead costs applied RM22610 = Over-applied manufacturing overhead RM1610
Account Titles and Explanation | Debit | Credit |
Manufacturing overhead | 1610 | |
Cost of goods sold | 1610 | |
(To dispose over-applied overheads) |
Per HOMEWORKLIB RULES the first question has been answered. Please post the remaining independent question separately. Thank you.
QUESTION 2 (25 MARKS) A. D'Salai Company had only one job in process on 19 May....
Dacosta Corporation had only one job in process on May 1. The job had been charged with $2,250 of direct materials, $6,990 of direct labor, and $10,062 of manufacturing overhead cost. The company assigns overhead cost to jobs using the predetermined overhead rate of $19.30 per direct labor-hour. During May, the following activity was recorded: Raw materials (all direct materials): Beginning balance $ 8,950 Purchased during the month $ 38,450 Used in production $ 39,750 Labor: Direct labor-hours worked during...
Dacosta Corporation had only one job in process on May 1. The job had been charged with $2,200 of direct materials, $6,966 of direct labor, and $10,048 of manufacturing overhead cost. The company assigns overhead cost to jobs using the predetermined overhead rate of $19.20 per direct labor- hour. During May, the following activity was recorded: $ 8,900 $38, 400 $39, 700 Raw materials (all direct materials): Beginn balance Purchased during the month Used in production Labor: Direct labor-hours worked...
Dacosta Corporation had only one job in process on May 1. The job had been charged with $2,500 of direct materials, $6,966 of direct labor, and $10,132 of manufacturing overhead cost. The company assigns overhead cost to jobs using the predetermined overhead rate of $19.80 per direct labor-hour. During May, the following activity was recorded: Raw materials (all direct materials): Beginning balance $ 9,200 Purchased during the month $ 38,700 Used in production $ 40,000 Labor: Direct labor-hours worked during...
Dacosta Corporation had only one job in process on May 1. The job had been charged with $2,600 of direct materials, $6,966 of direct labor, and $10,160 of manufacturing overhead cost. The company assigns overhead cost to jobs using the predetermined overhead rate of $20.00 per direct labor-hour. During May, the following activity was recorded: $ 9,300 $38,800 $40,100 Raw materials (all direct materials): Beginning balance Purchased during the month Used in production Labor: Direct labor-hours worked during the month...
Dacosta Corporation had only one job in process on May 1. The job had been charged with $2,200 of direct materials, $6,966 of direct labor, and $10,048 of manufacturing overhead cost. The company assigns overhead cost to jobs using the predetermined overhead rate of $19.20 per direct labor-hour. During May, the following activity was recorded: Raw materials (all direct materials): Beginning balance $ 8,900 Purchased during the month $ 38,400 Used in production $ 39,700 Labor: Direct labor-hours worked during...
4) Dacosta Corporation had only one job in process on May 1. The job had been charged 4) with $2800 of direct materials, S6966 of direct labor, and $10,216 of manufacturing overhead cost. The company assigns overhead cost to jobs using the predetermined overhead rate of $20.40 per direct labor-hour. During May, the following activity was recorded: Raw materials (all direct materials) Beginning balance Purchased during the month Used in production Labor: Direct labor-hours worked during the month Direct labor...
Dacosta Corporation had only one job in process on May 1. The job had been charged with $1,850 of direct materials. $6.990 of direct labor, and $9.950 of manufacturing overhead cost. The company assigns overhead cost to jobs using the predetermined overhead rate of $18.50 per direct labor-hour. During May, the following activity was recorded: $ 8,550 $38,050 $39,350 Raw materials (all direct materials Beginning balance Purchased during the month Used in production Labor: Direct labor-hours worked during the month...
18 Dacosta Corporation had only one job in process on May 1 The job had been charged with $2,800 of direct materials. 56,966 of director and $10.216 of manufacturing overhead cost. The company assigns overhead cost to jobs using the predetermined overhead rate of $20.40 per direct labor hour During May, the following activity was recorded av saterials (all direct materiala) Beginning balance Purchased during the month Used in production Labor Direct labor-hours worked during the month Direct labor cost...
Saved Help Save & Exit Dacosta Corporation had only one job in process on May 1. The job had been charged with $2,600 of direct materials, $6,966 of direct labor, and $10,16 of manufacturing overhead cost. The company assigns overhead cost to jobs using the predetermined overhead rate of $20.00 per direct labor-hour. During May, the following activity was recorded: $ 9,300 $38,800 $40,100 Raw materials (all direct materials): Beginning balance Purchased during the month Used in production Labor: Direct...
TB MC Qu. 3-204 Dacosta Corporation had only one job... Dacosta Corporation had only one job in process on May 1. The job had been charged with $1,850 of direct materials, $6,990 of direct labor, and $9,950 of manufacturing overhead cost. The company assigns overhead cost to jobs using the predetermined overhead rate of $18.50 per direct labor-hour. During May, the following activity was recorded: $ 8,550 $38,050 $39,350 Raw materials (all direct materials): Beginning balance Purchased during the month...