Equivalent units for direct material = units started and completed + ending units
= (80800-4800)*100% +4000*100%
= 80000 units
Equivalent Units of Materials Cost The Rolling Department of Oak Ridge Steel Company had 4,800 tons...
Equivalent Units of Material Cost The Rolling Department of Oak Ridge Steel Company had 4,800 tons in being work in process inventory (40% complete) on July 1. During July, 79,400 tons were completed. The ending work in process inventory on July 31 was 4,000 tons (30% complete) What are the total equivalent units for direct materials for July if materials are added at the beginning of the process
Equivalent Units of Materials Cost The Rolling Department of Oak Ridge Steel Company had 4,500 tons in beginning work in process inventory (40% complete) on July 1. During July, 74,300 tons were completed. The ending work in process inventory on July 31 was 3,700 tons (40% complete). What are the total equivalent units for direct materials for July if materials are added at the beginning of the process?
Equivalent Units of Materials Cost The Rolling Department of Oak Ridge Steel Company had 2,200 tons in beginning work in process inventory (30% complete) on July 1. During July, 37,000 tons were completed. The ending work in process inventory on July 31 was 1,900 tons (10% complete). What are the total equivalent units for direct materials for July if materials are added at the beginning of the process? units
Equivalent Units of Conversion Costs The Rolling Department of Oak Ridge Steel Company had 6,064 tons in beginning work in process inventory (40 % complete) on July 1. During July, 75,800 tons were completed. The ending work in process inventory on July 31 was 4,548 tons (80 % complete). What are the total equivalent units for conversion costs? Round to the nearest whole unit. units
Equivalent units of Conversion Costs The Rolling Department of Oak Ridge Steel Company had 6,064 tons in beginning work in process inventory (40% complete) on July 1. During July, 75.000 tons were completed. The ending work in process inventory on July 31 was 4,548 tons (80% complete). What are the total equivalent units for conversion costs? Round to the nearest whole unit T X units
Equivalent Units of Conversion Costs The Rolling Department of Oak Ridge Steel Company had 5,863 tons in beginning work in process inventory (30% complete) on July 1. During July, 53,300 tons were completed. The ending work in process inventory on July 31 was 2,665 tons (10% complete). What are the total equivalent units for conversion costs? Round to the nearest whole unit. units
Equivalent Units of Conversion Costs The Rolling Department of Oak Ridge Steel Company had 5,576 tons in beginning work in process inventory (50% complete) on July 1. During July, 69,700 tons were completed. The ending work in process inventory on July 31 was 5,576 tons (90% complete). What are the total equivalent units for conversion costs? Round to the nearest whole unit. 5765 units
Equivalent Units of Conversion Costs The Rolling Department of Oak Ridge Steel Company had 10,206 tons in beginning work in process inventory (10% complete) on July 1. During July, 72,900 tons were completed. The ending work in process inventory on July 31 was 6,561 tons (50% complete). What are the total equivalent units for conversion costs? Round to the nearest whole unit. ______ units
Equivalent Units of Conversion Costs The Rolling Department of Oak Ridge Steel Company had 6,842 tons in beginning work in process inventory (30% complete) on July 1. During July, 62,200 tons were completed. The ending work in process inventory on July 31 was 3,732 tons (30% complete). What are the total equivalent units for conversion costs? Round to the nearest whole unit. ________ units
EBOOK SHOW ME HOW i Calculator Equivalent Units of Materials Cost The Rolling Department of Oak Ridge Steel Company had 3,700 tons in beginning work in process inventory (70% complete) on July 1. During July, 62,400 tons were completed. The ending work in process inventory on July 31 was 3,100 tons (70% complete). What are the total equivalent units for direct materials for July if materials are added at the beginning of the process? units