Solution: $1,940
Working:
Actual variable overhead $55,440
Applied overhead: Standard hours allowed * standard rate = 10,700 * 2 * $2.50 = 53,500
Thus Underapplied variable overhead = $1,940
B3-5 points (12,5%) Zandi Company uses a standard cost accounting system and applies manufacturing overhead to...
Maxwell Company uses a standard cost accounting system and applies production overhead to products on the basis of machine hours. The following information is available for the year just ended: Standard variable-overhead rate per hour: $2.50 Standard fixed-overhead rate per hour: $4.00 Planned activity during the period: 20,000 machine hours Actual production: 10,700 finished units Machine-hour standard: Two completed units per machine hour Actual variable overhead: $55,440 Actual total overhead: $155,900 Actual machine hours worked: 23,100 Required: 1. Calculate the...
Maxwell Company uses a standard cost accounting system and applies production overhead to products on the basis of machine hours. The following information is available for the year just ended: Standard variable-overhead rate per hour: $7.50 Standard fixed-overhead rate per hour: $12.60 Planned activity during the period: 21,000 machine hours Actual production: 13,200 finished units Machine-hour standard: Two completed units per machine hour Actual variable overhead: $156,200 Actual total overhead: $437,800 Actual machine hours worked: 22,000 Required: 1. Calculate the...
The solution may be submitted as a Word document, Exc or PDF. The assignment will be from Chapter 11 Problem 11-4 your textbook. PI Overt Varia (LO 1 2. Va Maxwell Company uses a standard cost accounting system and applies production overhead to products on the basis of machine hours. The following information is available for the year just ended: Standard variable-overhead rate per hour: $2.50 Standard fixed-overhead rate per hour: $4.00 Planned activity during the period: 20,000 machine hours...
Priority Company, which applies overhead to production on the basis of machine hours, reported the following data for the period just ended: Actual units produced: 12,000 Actual variable overhead incurred: $50,400 Actual machine hours worked: 17,000 Standard variable overhead cost per machine hour: $3.10 If Priority estimates 1.60 hours to manufacture a completed unit, the company's variable-overhead efficiency variance is:
Orlando Company, which applies overhead to production on the basis of machine hours, reported the following data for the period just ended: Actual units produced: 16,000 Actual variable overhead incurred: $67,700 Actual machine hours worked: 19,100 Standard variable overhead cost per machine hour: $4.10 If Orlando estimates 1.10 hours to manufacture a completed unit, the company's variable-overhead spending variance is:
Lane Company manufactures a single product and applies overhead cost to that product using standard direct labor-hours. The budgeted variable manufacturing overhead is $2.80 per direct labor-hour and the budgeted fixed manufacturing overhead is $612,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $5.00 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $12.40 per hour. The company planned to operate at a...
Lane Company manufactures a single product and applies overhead cost to that product using standard direct labor-hours. The budgeted variable manufacturing overhead is $5.40 per direct labor-hour and the budgeted fixed manufacturing overhead is $2,679,000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $11.50 per pound. The standard direct labor-hours per unit is 1.5 hours and the standard labor rate is $13.70 per hour. The company planned to operate at a...
Lane Company manufactures a single product and applies overhead cost to that product using standard direct labor-hours. The budgeted variable manufacturing overhead is $3.40 per direct labor hour and the budgeted fixed manufacturing overhead is $999.000 per year. The standard quantity of materials is 4 pounds per unit and the standard cost is $6.50 per pound. The standard direct labor-hours per unit is 15 hours and the standard labor rate is $12.70 per hour. The company planned to operate at...
Primara Corporation has a standard cost system in which it applies overhead to products based on the standard direct labor-hours allowed for the actual output of the period. Data concerning the most recent year appear below: Total budgeted fixed overhead cost for the year Actual fixed overhead cost for the year Budgeted direct labor-hours (denominator level of activity) Actual direct labor-hours Standard direct labor-hours allowed for the actual output $ 473,600 $ 467,000 64,000 65,000 62,000 Required: 1. Compute the...
Soriano Manufacturing Company uses a standard cost accounting system to account for the manufacturing of exhaust fans. In July 2020, it accumulates the following data for 1,500 units started and finished: Cost and Production Data Actual Standard Raw materials Units purchased 21,000 Units used 21,000 22,000 Unit cost $3.40 $3.00 Direct labour Hours worked 3,450 3,600 Hourly rate $11.80 $12.50 Manufacturing overhead Incurred $101,500 Applied $108,000 Manufacturing overhead was applied based on direct labour hours. Normal capacity for the month...