Question

The solution may be submitted as a Word document, Exc or PDF. The assignment will be from Chapter 11 Problem 11-4 your textbo

0 0
Add a comment Improve this question Transcribed image text
Answer #1
Answer-1

Budgeted Fixed overhead = planned activity* std rate per hour

                            =20,000*4
                            =$ 80,000
Answer-2
Variable Overhead Spending Variance = Actual hours at actual rate- Actual hours at Std rate
Actual rate=55440/23100 = $2.40 per hour
Std rate =$ 2.50 per hour
Variable overhead Spending variance
=(23100*2.4)-(23100*2.5)
=2310 (F)
Answer -3
Fixed overhead Volume variance = Budgeted fixed Overhead- ( Std hours*Std rate)
Std hours =10700*0.5 per hour =5350 hours
Std rate = $4 per hour
Budgeted Fixed Overhead = $80,000
so, Fixed Overhead Volume variance
=80,000- (5350*4)
=58,600 (F)
Answer-4
Actual Fixed Overhead = Total actual Overhead- Actual variable overhead
                        =$ 1,55,900- $ 55,440
                         = $ 100,460
Budgeted Fixed Overhead = $ 80,000
Budgeted Fixed Overhead variance =$ (100460-80000) =$20,460 (U)
Answer-5
Actual variable Overhead = $ 55,440
Applied Variable Overhead =5350 hours @ $ 4 per hour = $ 21,400
So, variable overhead was under applied by $ 42,065
Answer -6
Planned Production =( $ 2* 20,000) $ 40,000
Actual production = 10,700 units.
Based on volume variance , it does appear that lengthy Strike is a strong possibilty.
Add a comment
Know the answer?
Add Answer to:
The solution may be submitted as a Word document, Exc or PDF. The assignment will be...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Maxwell Company uses a standard cost accounting system and applies production overhead to products on the...

    Maxwell Company uses a standard cost accounting system and applies production overhead to products on the basis of machine hours. The following information is available for the year just ended: Standard variable-overhead rate per hour: $2.50 Standard fixed-overhead rate per hour: $4.00 Planned activity during the period: 20,000 machine hours Actual production: 10,700 finished units Machine-hour standard: Two completed units per machine hour Actual variable overhead: $55,440 Actual total overhead: $155,900 Actual machine hours worked: 23,100 Required: 1. Calculate the...

  • B3-5 points (12,5%) Zandi Company uses a standard cost accounting system and applies manufacturing overhead to...

    B3-5 points (12,5%) Zandi Company uses a standard cost accounting system and applies manufacturing overhead to products on the basis of machine hours. The following information is available for the year just ended: Standard variable overhead rate per hour: $2.50 Planned activity during the period: 20,000 machine hours Machine-hour standard: Two completed units per machine hour Actual variable overhead: $55,440 Actual machine hours worked: 23,100 Actual production: 10,700 finished units Required: Calculate the variable overhead variances

  • Maxwell Company uses a standard cost accounting system and applies production overhead to products on the...

    Maxwell Company uses a standard cost accounting system and applies production overhead to products on the basis of machine hours. The following information is available for the year just ended: Standard variable-overhead rate per hour: $7.50 Standard fixed-overhead rate per hour: $12.60 Planned activity during the period: 21,000 machine hours Actual production: 13,200 finished units Machine-hour standard: Two completed units per machine hour Actual variable overhead: $156,200 Actual total overhead: $437,800 Actual machine hours worked: 22,000 Required: 1. Calculate the...

  • Standard machine hours per unit of output 4 hours Standard variable-overhead rate per machine hour 8.00...

    Standard machine hours per unit of output 4 hours Standard variable-overhead rate per machine hour 8.00 Actual variable-overhead rate per machine hour Actual machine hours per unit of output Budgeted fixed overhead |Actual fixed overhead Budgeted production in units Actual production in units Variable-overhead spending variance Variable-overhead efficiency variance Fixed-overhead budget variance Fixed-overhead volume variance Total actual overhead Total budgeted overhead (flexible budget) Total budgeted overhead (static budget) Total applied overhead 9.00 3 S 50,000 25,000 24,000 72,000 Unfavorable 192,000...

  • Company uses standard costing. The company prepared its static budget for 2018 at 2,500,000 machine hours...

    Company uses standard costing. The company prepared its static budget for 2018 at 2,500,000 machine hours for the year. Total budgeted overhead cost is $33,500,000. The variable overhead rate is $11 per machine hour ($22 per unit). Actual result for 2018 as follow: Machine-hours 2,400,000 hours Output 1,230,000 units Variable overhead $27,600,000 Fixed overhead rate variance $1,350,000 U 1. Calculate for the fixed​ overhead: a. Budgeted amount. b. Budgeted cost per​ machine-hour. c. Actual cost. d. ​Production-volume variance. 2. Calculate...

  • OH Variance At the beginning of the year, your company thought . Each product would use 3 direct labor hours. . Fix...

    OH Variance At the beginning of the year, your company thought . Each product would use 3 direct labor hours. . Fixed overhead would be $900,000 for the year. Fixed overhead would be applied based on machine hours and would be $2.50 per machine hour. .Variable overhead would be applied based on direct labor hours and would be $4.00 per direct labor hour e46,000 units would be produced At the end of the year, what happened that year was: 48,000...

  • Acme Company’s production budget for August is 19,000 units and includes the following component unit costs:...

    Acme Company’s production budget for August is 19,000 units and includes the following component unit costs: direct materials, $8.0; direct labor, $11.6; variable overhead, $5.6. Budgeted fixed overhead is $47,000. Actual production in August was 20,445 units. Actual unit component costs incurred during August include direct materials, $9.80; direct labor, $10.00; variable overhead, $6.40. Actual fixed overhead was $50,000. The standard variable overhead rate per unit consists of $5.6 per machine hour and each unit is allowed a standard of...

  • Acme Company's production budget for August is 18,000 units and includes the following component unit costs:...

    Acme Company's production budget for August is 18,000 units and includes the following component unit costs: direct materials. 58.0 direct labor, 510.5, variable overhead, $6.4. Budgeted fixed overhead is $37,000. Actual production in August was 19.950 units. Actual unit component costs incurred during August include direct materials, $8.70; direct labor, $9.90: variable overhead, 5730. Actual fixed overhead was $39.000. The standard variable overhead rate per unit consists of $6.4 per machine hour and each unit is allowed a standard of...

  • marks) Levie Company uses standard costing. The company prepared its static budget for 2018 at 2,500,000...

    marks) Levie Company uses standard costing. The company prepared its static budget for 2018 at 2,500,000 machine-hours for the year. Total budgeted overhead cost is $31,250,000. The variable overhead rate is $11 per machine-hour ($22 per unit). Actual results for 2018 follow: Machine-hours Output Variable overhead Fixed overhead rate variance 2,400,000 hours 1,245,000 units 25200000 $ 1,500,000 Required I 1. Calculate for the fixed overhead: a. Budgeted amount b. Budgeted cost per machine-hour. c. Actual cost. d. Production-volume variance. 2....

  • 2. The following data have been provided by Lopus Corporation: Budgeted production Standard machine-hours per unit Sta...

    2. The following data have been provided by Lopus Corporation: Budgeted production Standard machine-hours per unit Standard lubricants Standard supplies 4,000 units 4.1 machine-hours 5.60 per machine-hour 4.30 per machine-hour $ $ Actual production Actual machine-hours Actual lubricants (total) Actual supplies (total) 4,300 units 9,480 machine-hours $ 54,833 $40,239 Required: Compute the variable overhead rate variances for lubricants and for supplies. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT