Answer-1 | ||||
Budgeted Fixed overhead = planned activity* std rate per hour |
||||
=20,000*4 | ||||
=$ 80,000 | ||||
Answer-2 | ||||
Variable Overhead Spending Variance = Actual hours at actual rate- Actual hours at Std rate | ||||
Actual rate=55440/23100 = $2.40 per hour | ||||
Std rate =$ 2.50 per hour | ||||
Variable overhead Spending variance | ||||
=(23100*2.4)-(23100*2.5) | ||||
=2310 (F) | ||||
Answer -3 | ||||
Fixed overhead Volume variance = Budgeted fixed Overhead- ( Std hours*Std rate) | ||||
Std hours =10700*0.5 per hour =5350 hours | ||||
Std rate = $4 per hour | ||||
Budgeted Fixed Overhead = $80,000 | ||||
so, Fixed Overhead Volume variance | ||||
=80,000- (5350*4) | ||||
=58,600 (F) | ||||
Answer-4 | ||||
Actual Fixed Overhead = Total actual Overhead- Actual variable overhead | ||||
=$ 1,55,900- $ 55,440 | ||||
= $ 100,460 | ||||
Budgeted Fixed Overhead = $ 80,000 | ||||
Budgeted Fixed Overhead variance =$ (100460-80000) =$20,460 (U) | ||||
Answer-5 | ||||
Actual variable Overhead = $ 55,440 | ||||
Applied Variable Overhead =5350 hours @ $ 4 per hour = $ 21,400 | ||||
So, variable overhead was under applied by $ 42,065 | ||||
Answer -6 | ||||
Planned Production =( $ 2* 20,000) $ 40,000 | ||||
Actual production = 10,700 units. | ||||
Based on volume variance , it does appear that lengthy Strike is a strong possibilty. |
The solution may be submitted as a Word document, Exc or PDF. The assignment will be...
Maxwell Company uses a standard cost accounting system and applies production overhead to products on the basis of machine hours. The following information is available for the year just ended: Standard variable-overhead rate per hour: $2.50 Standard fixed-overhead rate per hour: $4.00 Planned activity during the period: 20,000 machine hours Actual production: 10,700 finished units Machine-hour standard: Two completed units per machine hour Actual variable overhead: $55,440 Actual total overhead: $155,900 Actual machine hours worked: 23,100 Required: 1. Calculate the...
B3-5 points (12,5%) Zandi Company uses a standard cost accounting system and applies manufacturing overhead to products on the basis of machine hours. The following information is available for the year just ended: Standard variable overhead rate per hour: $2.50 Planned activity during the period: 20,000 machine hours Machine-hour standard: Two completed units per machine hour Actual variable overhead: $55,440 Actual machine hours worked: 23,100 Actual production: 10,700 finished units Required: Calculate the variable overhead variances
Maxwell Company uses a standard cost accounting system and applies production overhead to products on the basis of machine hours. The following information is available for the year just ended: Standard variable-overhead rate per hour: $7.50 Standard fixed-overhead rate per hour: $12.60 Planned activity during the period: 21,000 machine hours Actual production: 13,200 finished units Machine-hour standard: Two completed units per machine hour Actual variable overhead: $156,200 Actual total overhead: $437,800 Actual machine hours worked: 22,000 Required: 1. Calculate the...
Standard machine hours per unit of output 4 hours Standard variable-overhead rate per machine hour 8.00 Actual variable-overhead rate per machine hour Actual machine hours per unit of output Budgeted fixed overhead |Actual fixed overhead Budgeted production in units Actual production in units Variable-overhead spending variance Variable-overhead efficiency variance Fixed-overhead budget variance Fixed-overhead volume variance Total actual overhead Total budgeted overhead (flexible budget) Total budgeted overhead (static budget) Total applied overhead 9.00 3 S 50,000 25,000 24,000 72,000 Unfavorable 192,000...
Company uses standard costing. The company prepared its static budget for 2018 at 2,500,000 machine hours for the year. Total budgeted overhead cost is $33,500,000. The variable overhead rate is $11 per machine hour ($22 per unit). Actual result for 2018 as follow: Machine-hours 2,400,000 hours Output 1,230,000 units Variable overhead $27,600,000 Fixed overhead rate variance $1,350,000 U 1. Calculate for the fixed overhead: a. Budgeted amount. b. Budgeted cost per machine-hour. c. Actual cost. d. Production-volume variance. 2. Calculate...
OH Variance At the beginning of the year, your company thought . Each product would use 3 direct labor hours. . Fixed overhead would be $900,000 for the year. Fixed overhead would be applied based on machine hours and would be $2.50 per machine hour. .Variable overhead would be applied based on direct labor hours and would be $4.00 per direct labor hour e46,000 units would be produced At the end of the year, what happened that year was: 48,000...
Acme Company’s production budget for August is 19,000 units and includes the following component unit costs: direct materials, $8.0; direct labor, $11.6; variable overhead, $5.6. Budgeted fixed overhead is $47,000. Actual production in August was 20,445 units. Actual unit component costs incurred during August include direct materials, $9.80; direct labor, $10.00; variable overhead, $6.40. Actual fixed overhead was $50,000. The standard variable overhead rate per unit consists of $5.6 per machine hour and each unit is allowed a standard of...
Acme Company's production budget for August is 18,000 units and includes the following component unit costs: direct materials. 58.0 direct labor, 510.5, variable overhead, $6.4. Budgeted fixed overhead is $37,000. Actual production in August was 19.950 units. Actual unit component costs incurred during August include direct materials, $8.70; direct labor, $9.90: variable overhead, 5730. Actual fixed overhead was $39.000. The standard variable overhead rate per unit consists of $6.4 per machine hour and each unit is allowed a standard of...
marks) Levie Company uses standard costing. The company prepared its static budget for 2018 at 2,500,000 machine-hours for the year. Total budgeted overhead cost is $31,250,000. The variable overhead rate is $11 per machine-hour ($22 per unit). Actual results for 2018 follow: Machine-hours Output Variable overhead Fixed overhead rate variance 2,400,000 hours 1,245,000 units 25200000 $ 1,500,000 Required I 1. Calculate for the fixed overhead: a. Budgeted amount b. Budgeted cost per machine-hour. c. Actual cost. d. Production-volume variance. 2....
2. The following data have been provided by Lopus Corporation: Budgeted production Standard machine-hours per unit Standard lubricants Standard supplies 4,000 units 4.1 machine-hours 5.60 per machine-hour 4.30 per machine-hour $ $ Actual production Actual machine-hours Actual lubricants (total) Actual supplies (total) 4,300 units 9,480 machine-hours $ 54,833 $40,239 Required: Compute the variable overhead rate variances for lubricants and for supplies. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect...