Answer: $29,000
Calculations:
i. Calculation of Unit cost:
Direct materials | $110,000 |
Direct labor | $100,000 |
Manufacturing overhead applied | $80,000 |
Total Cost | $290,000 |
÷ Total units produced | 2,000 |
= Unit cost | $145 |
ii. Calculation of Units on Hand:
Units produced | 2,000 units |
Units sold | -1,800 units |
Units on hand | 200 units |
iii.The cost of the finished goods on hand from this job:
Cost of the finished goods on hand= Units on hand x Unit cost
= 200 x $145
= $29,000
BACK Multiple Choice Question 77 Sunland Company completed Job No. B14 during 2019. The job cost...
Sheridan Company completed Job No. B14 during 2019. The job cost sheet listed the following: Direct materials Direct labor Manufacturing overhead applied Units produced Units sold $60000 $50000 $30000 5000 units 4800 units How much is the cost of the finished goods on hand from this job? O $178800 O $ 5600 O $140000 O $134400
Sportly, Inc. completed Job No. B14 during 2019. The job cost sheet listed the following: Direct materials used $100,000 Direct labor $80,000 Manufacturing overhead applied $70,000 Units produced 5,000 units Units on hand 2,000 units How much is the cost of the finished goods sold from this job?
a isnt correct 14.Sportly, Inc. completed Job No. B14 during 2011. The job cost sheet listed the following: Direct materials $44,000 Direct labor $24,000 Manufacturing overhead applied $16,000 Units produced 3,000 units Units sold 1,800 units How much is the cost of the finished goods on hand from this job? a. $84,000 A b. $50,400 c. $33,600 d. $40,800
0 m CALCULATOR PRINTER VERSION BACK NEXT Multiple Choice Question 76 The following information is available for completed Job No. 402: Direct materials, $120000; direct labor, 5180000; manufacturing overhead applied, $110000 units produced, 8000 units units sold, 5000 units. The cost of the finished goods on hand from this job is 5410000 5102500 $307500 $75000
Current Attempt in Progress Marigold Corp.completed Job No. B14 during 2017. The job cost sheet listed the following: Direct materials Direct labor Manufacturing overhead applied Units produced $60000 $50000 $30000 4000 units Units sold 2800 units How much is the cost of the finished goods on hand from this job? $42000 $106000 $140000 $98000 Save for Later Attempts: 0 F ODO F5 DIL
the cost of the finished goods on hand from this job is? View Policies Current Attempt in Progress The following information is available for completed Job No. 402: Direct materials, $20000; direct labor, $80000; manufacturing overhead applied, $10000; units produced, 8000 units; units sold, 6000 units. The cost of the finished goods on hand from this job is $82500. $25000 $110000. $27500 Save for Later
Fannin Company completed Job No. A20 during 2017. The job cost sheet listed the following: Direct materials $10,300 Direct labor $5,600 Manufacturing overhead applied Units produced $4,600 Units sold 1,000 units 400 units How much is the cost of the finished goods on hand for this job? $30,750 $12,300 $20,500 $8,200
Current Attempt in Progress The following information is available for completed Job No. 402: Direct materials. $20000; direct labor, $80000; manufacturing overhead applied $10000; units produced, 8000 units; units sold, 6000 units. The cost of the finished goods on hand from this job is $25000 O $110000 $27500. $82500 Save for Later Attempts: 0 of 1 used Submit Answer MacBook Air esc 2 3 % 5 &
Spruce Inc. completed Job No. A20 during 2020. The job cost sheet listed the following: Job No. A20 Costs for 5000 units produced: Direct materials $30,000 Direct labor $45,000 Manufacturing overhead applied $20,000 Units sold 2,000 units How much is the cost of the finished goods on hand at the end of the period from this job? $30,000 $57,000 $38,000 $45,000
Multiple Choice Question 106 During 2017, Waterway Industries expected Job No. 26 to cost $300000 of overhead, $500000 of materials, and $200000 in labor. Waterway applied overhead based on direct labor cost. Actual production required an overhead cost of $290000, $470000 in materials used, and $190000 in labor. All of the goods were completed. What amount was transferred to Finished Goods? $950000 $960000 $945000 $1000000 Multiple Choice Question 111 Crane Company developed the following data for the current year: Beginning...