Question
a isnt correct
14.Sportly, Inc. completed Job No. B14 during 2011. The job cost sheet listed the following: Direct materials $44,000 Direct
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer is option c. $33600

Total cost of 3000 goods completed.

Direct materials + direct labour +manufacturing overhead applied.

=44000+24000+16000 = 84000$

Per unit cost is =$84000/3000

=$28 per unit

Goods on hand is total goods less goods sold

=3000-1800 =1200 units

Cost is 1200 *28. =$33600

Add a comment
Know the answer?
Add Answer to:
a isnt correct 14.Sportly, Inc. completed Job No. B14 during 2011. The job cost sheet listed...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT