Answer: Corret option b. $ 57,000 |
Calculation of cost of the finished goods on hand at the end of the period is as follows: |
Cost of finished goods = ( Total cost / units produced ) * Ending inventory |
= ( $ 95,000 / 5,000 units ) * 3,000 units |
= $ 57,000 |
Thus, Cost of the finished goods on hand at the end of the period is $ 57,000 |
Working note: |
Total cost = Direct materials + Direct labor +Manufacturing overhead |
= $ 30,000 + $ 45,0000 + $ 20,000 |
= $ 95,000 |
Ending inventory = Units produced - Unit sold |
= 5000 units - 2000 units |
= 3000 units |
Spruce Inc. completed Job No. A20 during 2020. The job cost sheet listed the following: Job...
Fannin Company completed Job No. A20 during 2017. The job cost sheet listed the following: Direct materials $10,300 Direct labor $5,600 Manufacturing overhead applied Units produced $4,600 Units sold 1,000 units 400 units How much is the cost of the finished goods on hand for this job? $30,750 $12,300 $20,500 $8,200
Sportly, Inc. completed Job No. B14 during 2019. The job cost sheet listed the following: Direct materials used $100,000 Direct labor $80,000 Manufacturing overhead applied $70,000 Units produced 5,000 units Units on hand 2,000 units How much is the cost of the finished goods sold from this job?
Sheridan Company completed Job No. B14 during 2019. The job cost sheet listed the following: Direct materials Direct labor Manufacturing overhead applied Units produced Units sold $60000 $50000 $30000 5000 units 4800 units How much is the cost of the finished goods on hand from this job? O $178800 O $ 5600 O $140000 O $134400
a isnt correct 14.Sportly, Inc. completed Job No. B14 during 2011. The job cost sheet listed the following: Direct materials $44,000 Direct labor $24,000 Manufacturing overhead applied $16,000 Units produced 3,000 units Units sold 1,800 units How much is the cost of the finished goods on hand from this job? a. $84,000 A b. $50,400 c. $33,600 d. $40,800
BACK Multiple Choice Question 77 Sunland Company completed Job No. B14 during 2019. The job cost sheet listed the following: Direct materials $110000 Direct labor $100000 Manufacturing overhead applied $80000 Units produced 2000 units Units sold 1800 units How much is the cost of the finished goods on hand from this job? $332000 $ 29000 $290000 $261000
Current Attempt in Progress Marigold Corp.completed Job No. B14 during 2017. The job cost sheet listed the following: Direct materials Direct labor Manufacturing overhead applied Units produced $60000 $50000 $30000 4000 units Units sold 2800 units How much is the cost of the finished goods on hand from this job? $42000 $106000 $140000 $98000 Save for Later Attempts: 0 F ODO F5 DIL
•The following information is available for completed Job No. 402: Direct materials, $80,000; direct labor, $120,000; manufacturing overhead applied, $60,000; units produced, 5,000 units; units sold, 4,000 units. The cost of the finished goods on hand from this job is
Job 397 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Number of units completed $ 49,000 670 DLHS $ 12 per DLH 2,000 units The company applies manufacturing overhead on the basis of direct labor-hours. The predetermined overhead rate is $10 per direct labor-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to 2...
A job cost sheet of Ivanhoe Company is given below. JOB NO. 469 Job Cost Sheet Quantity White Lion Cages Date Requested Todd Company Date Completed Direct Direct Materials Labor FOR 2.500 7/2 7/31 Manufacturing Overhead Date 7/10 700 900 400 1,675 1,575 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost Your answer is partially correct. Try again. Answer the following questions. (1) What are the source documents for direct materials, direct labor, and...
Question 9 5 pts The following information is available for completed Job No. 503: Direct materials, $260,000; direct labor, $560,000; manufacturing overhead applied, $280,000; units produced, 100,000 units; units sold, 80,000 units. The cost of the finished goods on hand from this job is O $1,100,000 $220,000 $840,000 $880,000 Question 10 5 pts