•The following information is available for completed Job No. 402: Direct materials, $80,000; direct labor, $120,000; manufacturing overhead applied, $60,000; units produced, 5,000 units; units sold, 4,000 units. The cost of the finished goods on hand from this job is
Answer is $52,000
Solution:
Direct materials | $ 80,000.00 | ||||
Direct labor | $ 120,000.00 | ||||
manufacturing overhead applied | $ 60,000.00 | ||||
Total cost | $ 260,000.00 | ||||
Units produced | 5000 | units | |||
Unit cost | = | $260000/5000= $52 | |||
units produced | 5000 | units | |||
Units Sold | 4000 | units | |||
The cost of the finished goods on hand from this job is = | 1000 | units = | 1000*52 | $52,000 |
•The following information is available for completed Job No. 402: Direct materials, $80,000; direct labor, $120,000;...
Current Attempt in Progress The following information is available for completed Job No. 402: Direct materials. $20000; direct labor, $80000; manufacturing overhead applied $10000; units produced, 8000 units; units sold, 6000 units. The cost of the finished goods on hand from this job is $25000 O $110000 $27500. $82500 Save for Later Attempts: 0 of 1 used Submit Answer MacBook Air esc 2 3 % 5 &
Question 9 5 pts The following information is available for completed Job No. 503: Direct materials, $260,000; direct labor, $560,000; manufacturing overhead applied, $280,000; units produced, 100,000 units; units sold, 80,000 units. The cost of the finished goods on hand from this job is O $1,100,000 $220,000 $840,000 $880,000 Question 10 5 pts
Sportly, Inc. completed Job No. B14 during 2019. The job cost sheet listed the following: Direct materials used $100,000 Direct labor $80,000 Manufacturing overhead applied $70,000 Units produced 5,000 units Units on hand 2,000 units How much is the cost of the finished goods sold from this job?
--/1 Question 32 View Policies Current Attempt in Progress The following information is available for completed Job No. 402: Direct materials, $220000; direct labor, $280000; manufacturing overhead applied, $210000; units produced, 5000 units; units sold, 3000 units. The cost of the finished goods on hand from this job is $426000 $710000. $200000. $284000. Save for Later Attempts: 0 of 1 used 1 used Submit Answer Sulimit Answer Send to Gradebook
the cost of the finished goods on hand from this job is? View Policies Current Attempt in Progress The following information is available for completed Job No. 402: Direct materials, $20000; direct labor, $80000; manufacturing overhead applied, $10000; units produced, 8000 units; units sold, 6000 units. The cost of the finished goods on hand from this job is $82500. $25000 $110000. $27500 Save for Later
0 m CALCULATOR PRINTER VERSION BACK NEXT Multiple Choice Question 76 The following information is available for completed Job No. 402: Direct materials, $120000; direct labor, 5180000; manufacturing overhead applied, $110000 units produced, 8000 units units sold, 5000 units. The cost of the finished goods on hand from this job is 5410000 5102500 $307500 $75000
Fannin Company completed Job No. A20 during 2017. The job cost sheet listed the following: Direct materials $10,300 Direct labor $5,600 Manufacturing overhead applied Units produced $4,600 Units sold 1,000 units 400 units How much is the cost of the finished goods on hand for this job? $30,750 $12,300 $20,500 $8,200
Sheridan Company completed Job No. B14 during 2019. The job cost sheet listed the following: Direct materials Direct labor Manufacturing overhead applied Units produced Units sold $60000 $50000 $30000 5000 units 4800 units How much is the cost of the finished goods on hand from this job? O $178800 O $ 5600 O $140000 O $134400
Question 12 of 15 -/3.25 E View Policies Current Attempt in Progress The following information is available for completed Job No. 402: Direct materials, $70000; direct labor, $130000; manufacturing overhead applied, $60000; units produced, 4000 units; units sold, 3000 units. The cost of the finished goods on hand from this job is $195000. $260000 $50000 $65000 Save for Later Attempts: 0 of 1 used Submit Answer
Spruce Inc. completed Job No. A20 during 2020. The job cost sheet listed the following: Job No. A20 Costs for 5000 units produced: Direct materials $30,000 Direct labor $45,000 Manufacturing overhead applied $20,000 Units sold 2,000 units How much is the cost of the finished goods on hand at the end of the period from this job? $30,000 $57,000 $38,000 $45,000