Ans.
Units of Finished goods in hand= Total units produced- Unit solds
=100,000 units - 80,0000 units
= 20,000 units
So, the cost finished goods in hand = No of units in hnad * Per unit cost
= 20,000 units * $11
= $ 220,000 ( Option "B")
Question 9 5 pts The following information is available for completed Job No. 503: Direct materials,...
•The following information is available for completed Job No. 402: Direct materials, $80,000; direct labor, $120,000; manufacturing overhead applied, $60,000; units produced, 5,000 units; units sold, 4,000 units. The cost of the finished goods on hand from this job is
Current Attempt in Progress The following information is available for completed Job No. 402: Direct materials. $20000; direct labor, $80000; manufacturing overhead applied $10000; units produced, 8000 units; units sold, 6000 units. The cost of the finished goods on hand from this job is $25000 O $110000 $27500. $82500 Save for Later Attempts: 0 of 1 used Submit Answer MacBook Air esc 2 3 % 5 &
Sportly, Inc. completed Job No. B14 during 2019. The job cost sheet listed the following: Direct materials used $100,000 Direct labor $80,000 Manufacturing overhead applied $70,000 Units produced 5,000 units Units on hand 2,000 units How much is the cost of the finished goods sold from this job?
--/1 Question 32 View Policies Current Attempt in Progress The following information is available for completed Job No. 402: Direct materials, $220000; direct labor, $280000; manufacturing overhead applied, $210000; units produced, 5000 units; units sold, 3000 units. The cost of the finished goods on hand from this job is $426000 $710000. $200000. $284000. Save for Later Attempts: 0 of 1 used 1 used Submit Answer Sulimit Answer Send to Gradebook
Fannin Company completed Job No. A20 during 2017. The job cost sheet listed the following: Direct materials $10,300 Direct labor $5,600 Manufacturing overhead applied Units produced $4,600 Units sold 1,000 units 400 units How much is the cost of the finished goods on hand for this job? $30,750 $12,300 $20,500 $8,200
0 m CALCULATOR PRINTER VERSION BACK NEXT Multiple Choice Question 76 The following information is available for completed Job No. 402: Direct materials, $120000; direct labor, 5180000; manufacturing overhead applied, $110000 units produced, 8000 units units sold, 5000 units. The cost of the finished goods on hand from this job is 5410000 5102500 $307500 $75000
Sheridan Company completed Job No. B14 during 2019. The job cost sheet listed the following: Direct materials Direct labor Manufacturing overhead applied Units produced Units sold $60000 $50000 $30000 5000 units 4800 units How much is the cost of the finished goods on hand from this job? O $178800 O $ 5600 O $140000 O $134400
BACK Multiple Choice Question 77 Sunland Company completed Job No. B14 during 2019. The job cost sheet listed the following: Direct materials $110000 Direct labor $100000 Manufacturing overhead applied $80000 Units produced 2000 units Units sold 1800 units How much is the cost of the finished goods on hand from this job? $332000 $ 29000 $290000 $261000
Spruce Inc. completed Job No. A20 during 2020. The job cost sheet listed the following: Job No. A20 Costs for 5000 units produced: Direct materials $30,000 Direct labor $45,000 Manufacturing overhead applied $20,000 Units sold 2,000 units How much is the cost of the finished goods on hand at the end of the period from this job? $30,000 $57,000 $38,000 $45,000
the cost of the finished goods on hand from this job is?
View Policies Current Attempt in Progress The following information is available for completed Job No. 402: Direct materials, $20000; direct labor, $80000; manufacturing overhead applied, $10000; units produced, 8000 units; units sold, 6000 units. The cost of the finished goods on hand from this job is $82500. $25000 $110000. $27500 Save for Later