Question #3 ( 11 marks) A job cost sheet for Norngren Company is shown below: Job No. 5 Direct Materials For 2,000 Units | Di

0 0
Add a comment Improve this question Transcribed image text
Answer #1

1a) Beginning work in process = 3925+6000+4200 = 14125

1b) Overhead rate = 6375/8500 = 75%

2) Journal entry

No General Journal Debit Credit
1 Work in process 8000
Direct material 8000
2 Work in process (8500+4000) 12500
Direct labor 12500
3 Work in process (12500*75%) 9375
Manufacturing overhead 9375
4 Finished goods 44000
Work in process 44000
Add a comment
Know the answer?
Add Answer to:
Question #3 ( 11 marks) A job cost sheet for Norngren Company is shown below: Job...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 1 A job cost sheet for Rolen Company is shown below. Job No. 92 Direct...

    Question 1 A job cost sheet for Rolen Company is shown below. Job No. 92 Direct Materials Direct Labour For 2,000 Units Manufacturing Overhead Date Beginning Balance January 1 $5,000 $2,500 $3,920 6,000 8 12 8,500 5,950 25 2,000 27 3,900 17,400 2,730 11,180 11,920 Cost of completed job: Direct materials Direct labour Manufacturing overhead $11,920 17,400 11,180 $40,500 Total cost Unit cost ($40,500 - 2,000) $20.25 (a) Your answer is correct. On the basis of the foregoing data, answer...

  • Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92...

    Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Date Direct Materials Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 5,200 6,000 4,200 8 6,000 12 10,000 7,500 25 2,700 27 4,000 3,000 13,900 20,000 14,700 Cost of completed job:    Direct materials $13,900    Direct labor 20,000    Manufacturing overhead 14,700 Total cost $48,600 Unit cost ($48,600 ÷ 2,000) $24.30 (a) On the basis of the foregoing data, answer the following questions....

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead 4,900 Date 7,000 Beg. bal. Jan. 1 8 6,000 7,000 12 10,000 8,500 25 2,500 27 4,000 3,400 16,800 15,500 21,000 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($53,300 = 2,000) $15,500 21,000 16,800 $53,300 $26.65 (a) On the basis of the foregoing data, answer the following questions. (1) What...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Direct Materials Direct Labor Manufacturing Overhead Date Beg. bal. Jan. 1 5,100 7,000 4.900 7,000 8,000 6,000 2,800 5,000 3,750 14,900 20,000 14,650 Cost of completed job: Direct materials $14,900 Direct labor 20,000 Manufacturing overhead 14,650 Total cost $49,550 Unit cost ($49,550 = 2,000) $24.78 (a) On the basis of the foregoing data, answer the following questions. (a) On the basis of the...

  • Question 1 A job cost sheet for Rolen Company is shown below. Job No. 92 Direct...

    Question 1 A job cost sheet for Rolen Company is shown below. Job No. 92 Direct Materials Direct Labour For 2,000 Units Manufacturing Overhead Date Beginning Balance January 1 $5,300 $3,180 $4,088 6,250 8 12 8,630 6,904 25 2,090 27 4,810 18,740 3,848 13,932 12,428 Cost of completed job: Direct materials Direct labour Manufacturing overhead Total cost Unit cost ($45,100 + 2,000) $12,428 18,740 13,932 $45,100 $22.55 (a) On the basis of the foregoing data, answer the following questions: 1....

  • Analyze a job cost sheet and prepare entries for manafacturing costs. 2.3 101,2, 3, 4), AP...

    Analyze a job cost sheet and prepare entries for manafacturing costs. 2.3 101,2, 3, 4), AP A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Materials Direct Manufacturing Date Labor 6,000 8,000 4,000 18,000 Overhead 4,200 6,400 3,200 Beg. bal. Jan. 1 5,000 6,000 12 25 27 2,000 13,000 13,800 Cost of completed job: Direct materials Direct labor Manufacturing overhead $13,000 18,000 13,800 $44,800 Total cost Unit cost ($44,800+ 2,000) $22.40...

  • A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Date Direct Materials Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 6,500 6,000 4,200 6,000 8,000 6,800 25 3,000 4,000 18,000 15,500 3,400 14,400 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost (547,900 = 2.000) $15,500 18,000 14,400 $47.900 $23.95 (a) on the basis of the foregoing data, answer the following questions. (1) What was the balance...

  • Using this information:Answer the following, Please explain briefly. A job order cost sheet for Ryan Company...

    Using this information:Answer the following, Please explain briefly. A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Date For 2,000 Units Manufacturing Overhead Direct Labor Beg. bal. Jan. 1 6,000 4,200 6,700 6,000 6,000 4,500 2,500 3,000 4,000 16,000 15,200 11,700 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($42,900 2,000) $15,200 16,000 11,700 $42,900 $21.45 (a) On the basis of the foregoing data, answer the following...

  • A Job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials...

    A Job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan. 1 5,500 6,700 4,690 6,700 8,800 7,040 2,900 4,000 19,500 3,200 14,930 15,100 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($49,530 + 2,000) $15,100 19,500 14,930 $49,530 $24.77 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in...

  • A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000...

    A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Manufacturing Direct Materials Labor Date Overhead Beg. bal 5,9007,400 5,180 Jan. 1 7,400 12 25 27 6,800 5,100 2,400 4,400 15,700 18,600 3,300 13,580 Cost of completed job: Direct materials 15,700 18,600 13,580 $47,880 $23.94 Direct labor Total cost Unit cost ($47,880 2,000) (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in Work...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT