A manager has projected demand for the next six months (below). Given this information, prepare a LEVEL aggregate plan for pr
TOTAL Period FORECAST 1 S00 2 40 6 450 4 300 370 550 OUTPUT Regular Overtime Subcontract Output - Forecast INVENTORY Beginnin
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Period 1    2 3 4 5 6 TOTAL

OUTPUT FORECAST 500 440 300 370 550 450

REGULAR 350 350 300 350 350 350 2050

OVERTIME 75 75 0 20 75 75 320

SUBCONTRACT 75 15 0 0 125 25 240

OUTPUT-FORECAST 500 440 300 370 550 450 2610


INVENTORY

BEGINING 0 0 0 50 0 0 50

ENDING 0 0 50 0 0 0 50

AVERAGE 0 0 25 25 0 0 50

BACKORDERS 0 0 0 0 0 0 0

COSTS

OUTPUT

REGULAR 3500 3500 3000 3500 3500 3500 20500  

OVERTIME 1125 1125 0 300 1125 1125 4800

SUBCONTRACT 1500 300 0 0 2500 500 4800

INVENTORY 0 0 100 100 0 0 200

BACKORDERS 0 0 0 0 0 0 0

A) If the budget for this plan is $50,000 then plan is accepted

B) NO, because subcontracting cost is very high , so it is possible to increase regular units production limit

C) Yes, customers will be happy because their demand for the satisfied

D) Long Term Strategic plan is to increase regular production capacity of unit from current production levels,

with increase production capacity overtime cost and subcontracting cost saved easily

Add a comment
Know the answer?
Add Answer to:
A manager has projected demand for the next six months (below). Given this information, prepare a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Given the projected demands for the next six months, prepare an aggregate plan that uses inventor...

    Given the projected demands for the next six months, prepare an aggregate plan that uses inventory, regular time, overtime, subcontract and backorders. Regular time is limited to 150 units per month (Cost per Unit = $30 ). Overtime is limited to a maximum of 20 units per month (Cost per Unit -S45). Units purchased from the subcontractor (Cost per Unit = $54 ) cannot exceed 60 per month and the total purchases from the subcontractor over the 6 month period...

  • Manager Chris Channing of Fabric Mills, Inc., has developed the forecast shown in the table for...

    Manager Chris Channing of Fabric Mills, Inc., has developed the forecast shown in the table for bolts of cloth. The figures are in hundreds of bolts. The department has a normal capacity of 275(00) bolts per month, except for the seventh month, when capacity will be 250(00) bolts. Normal output has a cost of $40 per hundred bolts. Workers can be assigned to other jobs if production is less than normal. The beginning inventory is zero bolts. Month Forecast Total...

  • Manager Chris Channing of Fabric Mills, Inc., has developed the forecast shown in the table for...

    Manager Chris Channing of Fabric Mills, Inc., has developed the forecast shown in the table for bolts of cloth. The figures are in hundreds of bolts. The department has a normal capacity of 275(00) bolts per month, except for the seventh month, when capacity will be 250(00) bolts. Normal output has a cost of $40 per hundred bolts. Workers can be assigned to other jobs if production is less than normal. The beginning inventory is zero bolts. Month 1 2...

  • Electric Sheep has the following projected demands for the next six months for one of its...

    Electric Sheep has the following projected demands for the next six months for one of its products. Regular time is 160 units per month and overtime is a maximum of 20 units per month. Regular time is $20 per unit, overtime cost is $30 per unit, backorder cost is $20 per unit, inventory holding cost is $1 per unit and . Calculate the total inventory/backorder cost for a level production plan. Month Forecast 1 150 2 160 3 180 4...

  • PP.72 A manufacturer of solid state drives (SSDs) has projected the next six months of demand...

    PP.72 A manufacturer of solid state drives (SSDs) has projected the next six months of demand to be as shown the table below: Supply/Demand Info Beginning Jan Feb Mar Apr May Jun Forecast (demand) 48,000 52,000 60,000 54,000 58,000 64,000 Regular production Overtime production Subcontract production Ending inventory 6,000 Hired employees Fired employees Total employees 200 Cost variables as as follows: Cost Variables Labor cost/hour $14 Overtime cost/unit $32 Subcontracting cost/unit $29 Holding cost/unit/month $8 Hiring cost/employee $2,500 Firing cost/employee...

  • Given the following demand forecasts, costs, and constraints for a company. Regular Prod. Capacity = 27,000...

    Given the following demand forecasts, costs, and constraints for a company. Regular Prod. Capacity = 27,000 units/qtr Regular Prod. Cost = $12/unit Overtime Prod. Capacity = 3000 units/qtr Overtime Prod. Cost = $20/unit Subcontracting Capacity = 16,000 units/qtr Subcontracting Cost = $25/unit Inventory Capacity = 32,000 units/qtr Inventory Cost = $5/unit/qtr Beginning Inventory = 0 Backorder Cost = $15/unit/qtr Quarter Demand (units) 1 19,200 2 42,000 3 27,000 4 10,800 What is the cost if the company uses level production...

  • Demand over the next four months are 450, 500, 350, and 400 respectively. Regular time production costs $10 per item, an...

    Demand over the next four months are 450, 500, 350, and 400 respectively. Regular time production costs $10 per item, and we can make a maximum of 400 items in a given month in regular time. Overtime production costs $16 per item, and as many as 200 items may be produced in overtime each month (in addition to the regular time production). Keeping an item in inventory incurs a cost of $1 per period; backorders cost $3 per period per...

  • Jerusalem Medical Ltd., an Israeli producer of portable kidney dialysis units and other medical products, develops...

    Jerusalem Medical Ltd., an Israeli producer of portable kidney dialysis units and other medical products, develops a 4-month aggregate plan. Demand and capacity (in units) are forecast as follows: Month 1 Month 2 Month 3 Month 4 Capacity Source Labor 275 28 15 318 300 26 13 331 300 28 15 305 Regular time Overtime 225 15 Subcontract Demand 240 The cost of producingeach dialysis unit is $875 on regular time, $1,310 on overtime, and $1,600 on a subcontract. Inventory...

  • needing help with solving in Excel 6. Given the following forecast and cost information, determine the...

    needing help with solving in Excel 6. Given the following forecast and cost information, determine the total cost of a plan that uses regular time production output of 600 units per month, overtime is used when needed up to a maximum of 60 units per month, and subcontracting is used if additional units are needed to meet the forecast. Month 1 2 3 5 6 Forecast 570 600 630 650 670 690 Regular time cost = $40 per unit Overtime...

  • Ram Roy's firm has developed the following supply, demand, cost, and inventory data Supply Available Regular...

    Ram Roy's firm has developed the following supply, demand, cost, and inventory data Supply Available Regular Time 30 30 40 Demand Period Overtime Subcontract Forecast 15 15 20 40 45 60 Initial inventory Regular-time cost per unit Overtime cost per unit Subcontract cost per unit Carrying cost per unit per month 20 units $100 $150 $200 $6 Assume that the initial inventory has no holding cost in the first period and backorders are not permitted Allocating production capacity to meet...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT