Ans. A 1 | Actual quantity purchased = 76,000 diodes | |||
Actual quantity in ending inventory = 37,000 diodes | ||||
Actual quantity used = Actual quantity purchased - Actual quantity in ending inventory | ||||
76,000 - 37,000 = 39,000 diodes | ||||
*Standard quantity = Actual output * Standard quantity per unit of output | ||||
5,200 * 6 diodes | ||||
31,200 diodes | ||||
Materials quantity variance = (Standard quantity - Actual quantity used) * Standard price | ||||
(31,200 - 39,000) * $0.34 | ||||
-7,800 * $0.34 | ||||
-$2,652 | or $2,652 unfavorable | |||
Ans. A 2 | Materials price variance = (Standard price - Actual price) * Actual quantity purchased | |||
($0.34 - $0.33) * 76,000 | ||||
$0.01 * 76,000 | ||||
$760 | Favorable | |||
Ans. B 1 | Standard direct labor hours = Actual production * Standard hours allowed per unit | |||
5,200 * 1.1 hours | ||||
5,720 hours | ||||
Labor efficiency (quantity) variance = (Standard hours - Actual hours) * Standard rate | ||||
(5,720 - 6,320) * $7.40 | ||||
-600 * $7.40 | ||||
-$4,440 | or $4,440 unfavorable | |||
Ans. B 2 | Labor rate variance = (Standard rate * Actual hours) - Actual labor cost | |||
($7.40 * 6,320) - $48,664 | ||||
$46,768 - $48,664 | ||||
-$1,896 | or $1,896 unfavorable | |||
*If standard items (rate, price, quantity or hours) are higher than the actual then the variance would be favorable. | ||||
*If standard items (rate, price, quantity or hours) are lower than the actual then the variance would be unfavorable. | ||||
Topper Toys has developed a new toy called the Brainbuster. The company has a standard cost...
Topper Toys has developed a new toy called the Brainbuster. The company has a standard cost system to help control costs and has established the following standards for the Brainbuster toy: Direct materials: 7 diodes per toy at $0.33 per diode Direct labor. 1.2 hours per toy at $6.50 per hour During August, the company produced 5,200 Brainbuster toys. Production data on the toy for August follow:. Direct materials: 74,000 diodes were purchased at a cost of $0.30 per diode....
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 6 microns per toy at $0.35 per micron Direct labor: 1.4 hours per toy at $7.40 per hour During July, the company produced 4,700 Maze toys. The toy's production data for the month are as follows: Direct materials: 76,000 microns were purchased at a cost of...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 7 microns per toy at $0.33 per micron Direct labor: 1.1 hours per toy at $6.50 per hour During July, the company produced 5,000 Maze toys. Production data for the month on the toy follow: Direct materials: 76,000 microns were purchased at a cost of $0.30...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 7 microns per toy at $0.34 per micron Direct labor: 1.3 hours per toy at $7.50 per hour During July, the company produced 5,200 Maze toys. Production data for the month on the toy follow: Direct materials: 74,000 microns were purchased at a cost of $0.32...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 8 microns per toy at $0.34 per micron Direct labor: 1.1 hours per toy at $6.80 per hour During July, the company produced 4,800 Maze toys. Production data for the month on the toy follow: Direct materials: 71,000 microns were purchased at a cost of $0.33...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy Direct materials: 6 microns per toy at $0.33 per micron Direct labor: 1.2 hours per toy at $6.60 per hour During July, the company produced 5,300 Maze toys. Production data for the month on the toy follow Direct materials: 72,000 microns were purchased at a cost of $0.30...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 6 microns per toy at $0.34 per micron Direct labor: 1.1 hours per toy at $7.00 per hour During July, the company produced 4,800 Maze toys. Production data for the month on the toy follow: Direct materials: 73,000 microns were purchased at a cost of $0.32...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 6 microns per toy at $1.50 per micron Direct labor: 1.3 hours per toy at $21 per hour During July, the company produced 3,000 Maze toys. The toy's production data for the month are as follows: Direct materials. 25,000 microns were purchased at a cost of...
Dawson Toys, Ltd.. produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy Direct materials: 7 microns per toy at 50.33 per micron Direct labor 1.2 hours per toy at $7.20 per hour During July, the company produced 5,000 Maze toys. Production data for the month on the toy follow Direct materials: 74.000 microns were purchased at a cost of $0.20...
Dawson Toys, Ltd., produces a toy called the Maze. The company has recently established a standard cost system to help control costs and has established the following standards for the Maze toy: Direct materials: 7 microns per toy at $0.31 per micron Direct labor: 1.2 hours per toy at $6.90 per hour During July, the company produced 5,300 Maze toys. The toy's production data for the month are as follows: Direct materials. 80,000 microns were purchased at a cost of...