Question

12.1 Given the following cost expenditures for a small warehouse project to include direct and indirect charges), calculate t
TABLE 12.3 Overdraft Calculations with Mobilization Payment Month 1 Direct cost $25,000 $65,000 $75,000 $15,000 ndirect cost
dont calculate ROR
please show work
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Overdraft Calculations with Mobilization Payment
Month
1 2 3 4 5 6
Direct cost $   25,000 $   65,000 $   75,000 $   15,000
Indirect cost $      5,000 $      5,000 $      5,000 $      5,000
Subtotal $   30,000 $   70,000 $   80,000 $   20,000
Markup (12%) $      3,600 $      8,400 $      9,600 $      2,400
Total Billed $   33,600 $   78,400 $   89,600 $   22,400
Retainage withheld (10%) $      3,360 $      7,840 $      8,960 $      2,240
Payment received $ 20,000 $ 30,240 $   78,750 $ 100,000 $   17,500
Total cost to date $   30,000 $ 100,000 $ 180,000 $ 200,000 $ 200,000
Total amount billed to date $   33,600 $ 112,000 $ 201,600 $ 224,000 $ 224,000
Total paid to date $ 20,000 $ 50,240 $ 128,990 $ 228,990 $ 246,490
Overdraft end of month $   30,000 $   80,450 $ 131,417 $   74,638 -$   24,242 -$   41,742
Interest on overdraft balance (1.5%) $         450 $      1,207 $      1,971 $      1,120
Total amount financed $   30,450 $   81,657 $ 133,388 $   75,758 -$   24,242 -$   41,742
Add a comment
Know the answer?
Add Answer to:
dont calculate ROR please show work 12.1 Given the following cost expenditures for a small warehouse...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • TABLE 12.3 Overdraft Calculations with Mobilization Payment Month 1 Direct cost $25,000 $65,000 $75,000 $15,000 ndirect...

    TABLE 12.3 Overdraft Calculations with Mobilization Payment Month 1 Direct cost $25,000 $65,000 $75,000 $15,000 ndirect cost 5,000 5.000 5.000 5.000 Subtotal 30,000 70,000 80,000 20,000 Markup (25%) 7.500 17.500 20,000 5.000 Total billed 37,500 87,500 100,000 25,000 Retainage withheld (10%) 3.750 8,750 Payment received $20,000 $33,750 $78,750 $100,000 Total cost to date 30,000 100,000 180,000 200,000 200,000 Total amount billed to date 37,500 125,000 225,000 250,000 250,000 Total paid to date $20,000 $53,750 $132,000 $232,500 Overdraft end of month...

  • CE 210 please show all work TABLE 12.3 Overdraft Calculations with Mobilization Payment Month 1 Direct...

    CE 210 please show all work TABLE 12.3 Overdraft Calculations with Mobilization Payment Month 1 Direct cost $25,000 $65,000 $75,000 $15,000 ndirect cost 5,000 5.000 5.000 5.000 Subtotal 30,000 70,000 80,000 20,000 Markup (25%) 7.500 17.500 20,000 5.000 Total billed 37,500 87,500 100,000 25,000 Retainage withheld (10%) 3.750 8,750 Payment received $20,000 $33,750 $78,750 $100,000 Total cost to date 30,000 100,000 180,000 200,000 200,000 Total amount billed to date 37,500 125,000 225,000 250,000 250,000 Total paid to date $20,000 $53,750...

  • Given the following cost expenditures for a small warehouse project to include direct and indirect costs),...

    Given the following cost expenditures for a small warehouse project to include direct and indirect costs), develop an overdraft calculations' table, calculate the peak financial requirement, the average overdraft, and the ROR on invested money. Based on the prior calculations, sketch a diagram of the overdraft profile. Assume 12% markup. Retainage 10% throughout project. Finance charge is 1.5% month. Payments are billed at end of month and received one month later. Month Indirect + Direct Cost (S) $69,000 $21,800 $17.800...

  • 12.3 Given the following data with the direct costs for each activity as shown, calculate the...

    12.3 Given the following data with the direct costs for each activity as shown, calculate the ROR of the contractor. Assume that (a) the markup is 15%; (b) retainage is 5% on the first 50% of worth, and 0% thereafter; (c) payment requests are submitted at the end of each month, and payments are received one month later; and (d) the finance charge is 1% per month of the amount of the overdraft at the end of the month Timing...

  • Given the following monthly total direct and indirect costs, what are the overdraft in the 2nd mo...

    Given the following monthly total direct and indirect costs, what are the overdraft in the 2nd month and payment received at the end of the 3rd month? Answers are provided in the form of Overdraft 2nd and Payment 3rd] Month: 2 3 Total cost: $25,000 $55,000 $80,000 $20,000 (Direct+Indirect) Assume 12% for markup, 10% for retainage, and 1% for finance charge. Payments are billed at the end of the month and received one month later. $55,050 and $98,560 $81,053 and...

  • Please show all caculations and all work. each pic is a different problem Snowy Inc had the following job cost...

    Please show all caculations and all work. each pic is a different problem Snowy Inc had the following job costs for January Job: 23 24 25 Dec. Work in Process $ 5,000 $ 2,000 January Direct Materials $20,000 $18,000 $6,000 January Direct Labor $10,000 $25,000 $2,000 January Overhead $5,000 $12,500 $1,000 Prepare the journal entries to record the January job costs to all the jobs and transfer job 23 to finished goods. You can type your answers below Gotta Have...

  • If you could please explain and show your work that would be great! Thank you so...

    If you could please explain and show your work that would be great! Thank you so much! You have been engaged as a consultant to design a master budget model and then to assist Helping Hand Corp. in making some management decisions based on that master budget. Helping Hand is a small, rapidly growing wholesaler of consumer electronic products. The company's main product lines are small kitchen appliances and power tools. The marketing manager has recently completed a sales forecast....

  • PLEASE SHOW ALL WORK!! You have been engaged as a consultant to design a master budget...

    PLEASE SHOW ALL WORK!! You have been engaged as a consultant to design a master budget model and then to assist Helping Hand Corp. in making some management decisions based on that master budget. Helping Hand is a small, rapidly growing wholesaler of consumer electronic products. The company’s main product lines are small kitchen appliances and power tools. The marketing manager has recently completed a sales forecast. She believes the company’s sales will increase by 2 percent each month over...

  • Please show ALL work, including formulas used and equations for excel You have been engaged as...

    Please show ALL work, including formulas used and equations for excel You have been engaged as a consultant to design a master budget model and then to assist Helping Hand Corp. in making some management decisions based on that master budget. Helping Hand is a small, rapidly growing wholesaler of consumer electronic products. The company’s main product lines are small kitchen appliances and power tools. The marketing manager has recently completed a sales forecast. She believes the company’s sales will...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT