3.given the following cost expenditures for a small warehouse project calculate the peak financial requirementand average overdraft.

3. Given the following cost house project calculate the and the average overdraft. expenditures for a small ware- Peak financMonth 69000 9000 9183541460-53 61008 91835 41460.53 61008.03 43980.75 (-13330.7 Over darft end of month interest an over drat

Add a comment
Know the answer?
Add Answer to:
Given the following cost expenditures for a small warehouse project to include direct and indirect costs),...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • PLEASE I JUST DONT NEED THE TABLE BUT ALSO ALL THE CALCULATIONS IN DETAILS ON HOW...

    PLEASE I JUST DONT NEED THE TABLE BUT ALSO ALL THE CALCULATIONS IN DETAILS ON HOW YOU GET EACH FIGURE THANK YOU Given the followingcost expenditures forasmall warehouse project to include direct and indirect charges), calculate the peak financial requirement, the average overdraft, and the ROR on invested money. Sketch a diagram of the overdraft profile. Assume 12% markup Retainage 10% throughout project Finance charge 15% month Payments are billed at end of anth and received one month later Month...

  • dont calculate ROR please show work 12.1 Given the following cost expenditures for a small warehouse...

    dont calculate ROR please show work 12.1 Given the following cost expenditures for a small warehouse project to include direct and indirect charges), calculate the peak financial requirement, the average overdraft, and the ROR on invested money. Sketch a diagram of the overdraft profile. Assume 12% markup Retainage 10% throughout project Finance charge = 1.5% month Payments are billed at end of month and received one month later. TABLE 12.3 Overdraft Calculations with Mobilization Payment Month 1 Direct cost $25,000...

  • Given the following monthly total direct and indirect costs, what are the overdraft in the 2nd mo...

    Given the following monthly total direct and indirect costs, what are the overdraft in the 2nd month and payment received at the end of the 3rd month? Answers are provided in the form of Overdraft 2nd and Payment 3rd] Month: 2 3 Total cost: $25,000 $55,000 $80,000 $20,000 (Direct+Indirect) Assume 12% for markup, 10% for retainage, and 1% for finance charge. Payments are billed at the end of the month and received one month later. $55,050 and $98,560 $81,053 and...

  • 12.3 Given the following data with the direct costs for each activity as shown, calculate the...

    12.3 Given the following data with the direct costs for each activity as shown, calculate the ROR of the contractor. Assume that (a) the markup is 15%; (b) retainage is 5% on the first 50% of worth, and 0% thereafter; (c) payment requests are submitted at the end of each month, and payments are received one month later; and (d) the finance charge is 1% per month of the amount of the overdraft at the end of the month Timing...

  • CE 210 please show all work TABLE 12.3 Overdraft Calculations with Mobilization Payment Month 1 Direct...

    CE 210 please show all work TABLE 12.3 Overdraft Calculations with Mobilization Payment Month 1 Direct cost $25,000 $65,000 $75,000 $15,000 ndirect cost 5,000 5.000 5.000 5.000 Subtotal 30,000 70,000 80,000 20,000 Markup (25%) 7.500 17.500 20,000 5.000 Total billed 37,500 87,500 100,000 25,000 Retainage withheld (10%) 3.750 8,750 Payment received $20,000 $33,750 $78,750 $100,000 Total cost to date 30,000 100,000 180,000 200,000 200,000 Total amount billed to date 37,500 125,000 225,000 250,000 250,000 Total paid to date $20,000 $53,750...

  • CE413 CONSTRUCTION METHODS Due 4/24/2017 I. A contractor has a five-month project with the expected direct costs as...

    CE413 CONSTRUCTION METHODS Due 4/24/2017 I. A contractor has a five-month project with the expected direct costs as follows: 1 month 25,000, 2d month $40,000, 3d month $65,000, 4th month $80,000, and 5th month $30,000. It is assumed that ( 1 ) the monthly indirect cost is $6,000, (b) retainage is 10% for the first three months, and 0% thereafter; (c) the markup is 25%; and, (d) the monthly interest rate is 1%. The contractor submits payment requests at the...

  • TABLE 12.3 Overdraft Calculations with Mobilization Payment Month 1 Direct cost $25,000 $65,000 $75,000 $15,000 ndirect...

    TABLE 12.3 Overdraft Calculations with Mobilization Payment Month 1 Direct cost $25,000 $65,000 $75,000 $15,000 ndirect cost 5,000 5.000 5.000 5.000 Subtotal 30,000 70,000 80,000 20,000 Markup (25%) 7.500 17.500 20,000 5.000 Total billed 37,500 87,500 100,000 25,000 Retainage withheld (10%) 3.750 8,750 Payment received $20,000 $33,750 $78,750 $100,000 Total cost to date 30,000 100,000 180,000 200,000 200,000 Total amount billed to date 37,500 125,000 225,000 250,000 250,000 Total paid to date $20,000 $53,750 $132,000 $232,500 Overdraft end of month...

  • Ch Problem 1-18 Direct and Indirect Costs; Variable Costs [LO1-1, LO1-4] The following costidata pertain to...

    Ch Problem 1-18 Direct and Indirect Costs; Variable Costs [LO1-1, LO1-4] The following costidata pertain to the operations of Montgomery Department Stores, Inc., .or the month of July. Corporate legal office salaries Apparel Department cost of sales-Evendale Store Corporate headquarters building lease Store manager's salary-Evendale Store Apparel Department sales commission-Evendale Store Store utilities-Evendale Store Apparel Department manager's salary-Evendale Store Central warehouse lease cost Janitorial costs-Evendale Store 69,000 117,900 63,900 18,000 $ 10,009 13,400 12,800 23,800 $11,200 The Evendale Store is...

  • Problem 1-18 Direct and Indirect Costs; Variable Costs [L01-1, LO1-4] The following cost data pertain to...

    Problem 1-18 Direct and Indirect Costs; Variable Costs [L01-1, LO1-4] The following cost data pertain to the operations of Montgomery Department Stores, Inc., for the month of July Corporate legal office salaries Apparel Department cost of sales-Evendale Store Corporate headquarters building lease Store manager's salary-Evendale Store Apparel Department sales commission-Evendale Store Store utilities-Evendale Store Apparel Department manager s salary-Evendale Store Central warehouse lease cost Janitorial costs-Evendale Store s 65,600 $ 107,100 $58,600 $ 19,900 $11,600 $ 12,200 $8,050 $ 24,600...

  • plzz help Problem 1-18 Direct and Indirect Costs; Variable Costs [L01-1, LO1-4] The following cost data pertain to the o...

    plzz help Problem 1-18 Direct and Indirect Costs; Variable Costs [L01-1, LO1-4] The following cost data pertain to the operations of Montgomery Department Stores, Inc., for the month of July. Corporate legal office salaries Apparel Department cost of sales-Evendale Store Corporate headquarters building lease Store manager's salary-Evendale Store Apparel Department sales commission-Evendale Store Store utilities-Evendale Store Apparel Department manager's salary-Evendale Store Central warehouse lease cost Janitorial costs-Evendale Store $ 60,900 $ 117,300 $ 53,400 $ 12,400 $ 9,850 $ 18,800...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT