No further information is given so not able to complete the table
Overdraft calculations with Mobilization Payment
Month
Particular | 1 | 2 | 3 | 4 | 5 | 6 | |||||
Direct cost | $25000 | 65000 | 75000 | 15000 | |||||||
Indirect cost | 5000 | 5000 | 5000 | 5000 | |||||||
subtotal | 30000 | 70000 | 80000 | 20000 | |||||||
Markup (25%) | 7500 | 17500 | 20000 | 5000 | |||||||
Total billed | 37500 | 87500 | 100000 | 25000 | |||||||
Retainage withheld (10%) | 3750 | 8750 | 10000 | 2500 | |||||||
Payment received | 20000 | 33750 | 78750 | 100000 | 17500 | ||||||
Total cost to date | 30000 | 100000 | 180000 | 200000 | 200000 | 200000 | |||||
Total amount billed to date | 37500 | 125000 | 225000 | 250000 | 250000 | 250000 | |||||
Total paid to date | 20000 | 53750 | 132000 | 232500 | 250000 | ||||||
Overdraft end of month | 30000 | 80300 | 127353 | 69877 | (29424) | (46924) | |||||
interest on overdraft balance | 300 | 803 | 1274 | 699 | 0 | 0 | |||||
Total amount financed | $30300 | $81103 | $128627 | $70576 | (29424) | (46924) |
TABLE 12.3 Overdraft Calculations with Mobilization Payment Month 1 Direct cost $25,000 $65,000 $75,000 $15,000 ndirect...
CE 210 please show all work TABLE 12.3 Overdraft Calculations with Mobilization Payment Month 1 Direct cost $25,000 $65,000 $75,000 $15,000 ndirect cost 5,000 5.000 5.000 5.000 Subtotal 30,000 70,000 80,000 20,000 Markup (25%) 7.500 17.500 20,000 5.000 Total billed 37,500 87,500 100,000 25,000 Retainage withheld (10%) 3.750 8,750 Payment received $20,000 $33,750 $78,750 $100,000 Total cost to date 30,000 100,000 180,000 200,000 200,000 Total amount billed to date 37,500 125,000 225,000 250,000 250,000 Total paid to date $20,000 $53,750...
dont calculate ROR please show work 12.1 Given the following cost expenditures for a small warehouse project to include direct and indirect charges), calculate the peak financial requirement, the average overdraft, and the ROR on invested money. Sketch a diagram of the overdraft profile. Assume 12% markup Retainage 10% throughout project Finance charge = 1.5% month Payments are billed at end of month and received one month later. TABLE 12.3 Overdraft Calculations with Mobilization Payment Month 1 Direct cost $25,000...