Question

25) Figure 5-5 (4pts) Tonneau Corporation had the following information available for October 2016: Work in Process, October
Job Z3 35,000 Job Z4 18,750 Jobs 23 and 24 were not completed at the end of December. Refer to Figure 5-5. What is the balanc
0 0
Add a comment Improve this question Transcribed image text
Answer #1

D) $53,750

Explanation:

There are 2 methods to determine the work in process.

METHOD I:

Work-in-process will be sum total of the costs allocated to the jobs that are not complete at the end of the period. Therefore, work-in-process will be sum total of cost allocated to Job Z3 and Job Z4.

Work-in-process = $35,000 + $18,750

= $53,750

METHOD II:

We will calculate the cost transferred to the manufacturing process and then deduct the cost associated with the jobs completed to find out the work-in-process.

Total cost allocated to manufacturing process = Beginning work-in-progress + Material + Labor + Factory Overheads

= $20,000 + $27,500 + $37,500 + (150% of $37,500)

= $141,250

Cost allocated to completed jobs = Cost allocated to Job Z1 and Z2

= $32,500 + $55,000

= $87,500

Closing Work-in-process = Cost allocated to manufacturing process - cost allocated to completed jobs

= $141,250 - $87,500

= $53,750

Note: to solve the question in its spirit, December is assumed to be replaced with October. If we do not assume the same, it is not possible to solve the question.

Add a comment
Know the answer?
Add Answer to:
25) Figure 5-5 (4pts) Tonneau Corporation had the following information available for October 2016: Work in...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Tonneau Corporation had the following information available for October 2016: Work in Process, October 1 $20,000...

    Tonneau Corporation had the following information available for October 2016: Work in Process, October 1 $20,000 27,500 Materials placed into production, October Direct labor, October 37,500 Factory overhead rate is 150 percent of direct labor costs. Job cost sheets had the following balances: $32,500 Job ZI 55,000 Job Z2 35,000 Job Z3 Job 24 18,450 Jobs Z3 and Z4 were not completed at the end of December Refer to Figure 5-5. What is the balance in Work-in-Process for Tonneau at...

  • Kapanga Manufacturing Corporation uses a job-order costing system and started the month of October with a...

    Kapanga Manufacturing Corporation uses a job-order costing system and started the month of October with a zero balance in its work in process and finished goods inventory accounts. During October Kapanga worked on three jobs and incurred the following direct costs on those jobs Direct materials Direct labor Job 318 $ 12,000 $ 8,000 Job 319 $ 25,000 $ 10,000 Job C11 $ 18,000 $ 5,000 Kapanga applies manufacturing overhead at a rate of 150% of direct labor cost. During...

  • Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job...

    Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job A260. At the end of October, the job cost sheets for these jobs contained the following data: Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job A260. At the end of October, the job cost sheets for these jobs contained the following data: Job A256 Job A257 Job A258 Job A260 $ 1,070 $ 630 $ $...

  • Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job...

    Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job A260. At the end of October, the job cost sheets for these jobs contained the following data: Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job A260. At the end of October, the job cost sheets for these jobs contained the following data: Job A256 Job A257 Job A258 Job A260 $ 1,020 $ 680 $ 0...

  • Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job...

    Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job A260. At the end of October, the job cost sheets for these jobs contained the following data: Job A256 $1,010 Job Job A257 A258 $ 670 $ 0 Job A260 $ 0 Beginning balance Charged to the jobs during October: Direct materials Direct labor Manufacturing overhead applied Units completed Units in process at the end of October Units sold during October $ 2,790 $3,900...

  • Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job...

    Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job A260. At the end of October, the job cost sheets for these jobs contained the following data: Job Job Job Job A256 A257 A258 A260 $1,100 $ 580 $0 $ 0 Beginning balance Charged to the jobs during October Direct materials Direct labor Manufacturing overhead applied Units completed Units in process at the end of October Units sold during October $2,860 $4,050 $1,580 $3,770...

  • Techuxia Corporation worked on four jobs during October. Job A256, Job A257, Job A258, and Job...

    Techuxia Corporation worked on four jobs during October. Job A256, Job A257, Job A258, and Job A260. At the end of October, the job cost sheets for these jobs contained the following data: Job A256 Job A257 Job A258 Job A260 Beginning balance $ 970 $ 660 $ Charged to the jobs during October: Direct materials $2,820 $3,950 $1,440 $3,660 Direct labor $1,290 $ 950 $ 530 $ 360 Manufacturing overhead applied $4,616 $1,840 $3,366 $ 498 Units completed 202...

  • Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job...

    Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job A260. At the end of October, the job cost sheets for these jobs contained the following data:    Job A256 Job A257 Job A258 Job A260 Beginning balance $ 1,000 $ 660 $ 0 $ 0 Charged to the jobs during October: Direct materials $ 2,800 $ 4,020 $ 1,580 $ 3,790 Direct labor $ 1,170 $ 910 $ 620 $ 320 Manufacturing overhead applied...

  • Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job...

    Techuxia Corporation worked on four jobs during October: Job A256, Job A257, Job A258, and Job A260. At the end of October, the job cost sheets for these jobs contained the following data: Job A256 Job A257 Job A258 Job A260 Beginning balance $ 1,020 $ 510 $ 0 $ 0 Charged to the jobs during October: Direct materials $ 2,800 $ 3,990 $ 1,470 $ 3,630 Direct labor $ 1,170 $ 850 $ 510 $ 360 Manufacturing overhead applied...

  • The Polaris Company uses a job-order costing system. The following transactions occurred in October: a. Raw...

    The Polaris Company uses a job-order costing system. The following transactions occurred in October: a. Raw materials purchased on account, $209,000. b. Raw materials used in production, $190,000 ($152,000 direct materials and $38,000 indirect materials) c. Accrued direct labor cost of $49,000 and indirect labor cost of $21,000. d. Depreciation recorded on factory equipment, $105,000. e. Other manufacturing overhead costs accrued during October, $131,000 f The company applies manufacturing overhead cost to production using a predetermined rate of $8 per...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT