Question

HOP# 1 Job #AAI 10, which was completed during January, cosas Job #AAI 11. which was also completed during January, consisted of 70 units. Jobs #AAI 12 and #AAI 13 were not coupleted during January The Job Shop sells units for 140% of their manufacturing cost. January, cousisted of 40 uuts. REQUIRED a. Prepare journal eatries to record the following:w Ca 1. Use of direct materials during Janry 2. The direct labor payroll for the month. 3. Application of mamfacturing ovethead for J 4. Actual manufacturing overhead for January 5. Completion of Jobs #AAI 10 and #AA111 6. A credit sale of 30 units from Job #AAI 10 and 40 January units from Job #AAI 11. b. What is The Job Shops over- or under-applied overhead at the end of January? c. What was the balance of The Job Shops Work-in-Process account on Jaumary 1 20 8? d. What was the balance of The Job Shops Work-in-Process account on January 31 20 8? )lo

HOP#1 The Job Shop prodtuces a variety of products nsing the equipment in their factory. They use job order costing and apply manufacturing overhead on the basis of machine hours worked using a predetertinined overfiead rate. During 20 S, The Job Shop expects to incur S260,000 of minfactnring overhead. They expect to work 10,400 machine hours On January 1, 20-8. The Job Shop had one Job #AA 110 in the factory. The job cost sheet for Job #AAI 10 shows that $5,400 of direct material had been used on the Job 20 7. Direct labor used on the job in 20 7 was S1.050 and manufacturing over applied to the job in 20_7 was $3,450. Production was started on threejobs during January: #AA111, #AAI 12. #AA113. Material requisitioned during January was as follows $800 for #AA110 $6,700 for #AA111 S4.900 for #AAI 12 S3,100 for HAA13 Direct labor incutred during January was as follows S300 for #AA110 $1.500 for #AA111 $900 for #AA112 S500 for #AA113 Machine hours worked during January were as follows 80111h on #AA110 260th on #AA111 150mil ou mAAI 12 I 101nh on #AA113 Manufacturing Overhead incurred during Jannary was as follows: $13.600 of depreciation on plaat and equipment S500 of insurance on the plant $3.100 of utilities, and $3,700 of indirect labor. Job Shop had paid for the insurance in 20 7. Utilities will be paid for in February 20 8.

0 0
Add a comment Improve this question Transcribed image text
Answer #1
a. Sl No. Account titles and explanation Debit Credit
1 Work in process control account 15500
Material control account 15500
(800+6700+4900+3100)
(Direct materials used)
2 Work in process control account 3200
Wages control account 3200
(300+1500+900+500)
(Direct labor payroll for the month)
3 Work in process control account (Note:1) 15000
Manufacturing overhead control account 15000
(Manufacturing overhead applied)
4 Manufacturing overhead control account 20900
Accumulated depreciation 13600
Prepaid insurance (Since paid in Previous year) 500
Utilities payable (Since to be paid in Feb) 3100
Wages control account 3700
(Manufacturing overhead incurred)
5 Finished goods control account (Note:2) 17800
Work in process control account 17800
(Completion of Jobs)
6 Accounts receivable (Note:3) 15015
Sales 15015
(Sales on credit)
Cost of goods sold (Note:4) 10725
Finished goods control account 10725
(Cost of sales recorded)
Note:1
Predetermine overhead rate=Estimated manufacturing overhead/Estimated machine hours=260000/10400=$25 per machine hour
Overhead applied=Machine hours worked* Predetermined overhead rate
Machine hours worked:
mh
#AA110 80
#AA111 260
#AA112 150
#AA113 110
Total 600
Overhead applied=600* 25=$ 15000
Note:2
Cost of completed Jobs:
#AA110 #AA111 Total
Direct material 800 6700
Direct labor 300 1500
Manufacturing overhead 2000 6500
(Machine hours worked* Predetermined overhead rate) (80*25) (260*25)
Total 3100 14700 17800
Note:3
#AA110 #AA111 Total
Cost of jobs 3100 14700
Add: 40% markup 1240 5880
(140% of mfg cost means 40% of markup)
Selling price a 4340 20580
Units produced b 40 70
Selling price per unit c=(a/b) 108.5 294
Units sold d 30 40
Sales value e=(c*d) 3255 11760 15015
Note:4
#AA110 #AA111 Total
Cost of jobs a 3100 14700
Units produced b 40 70
Cost per unit c=(a/b) 77.5 210
Units sold d 30 40
Cost of sales e=(c*d) 2325 8400 10725

Add a comment
Know the answer?
Add Answer to:
HOP# 1 Job #AAI 10, which was completed during January, cosas Job #AAI 11. which was...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Assume a company started and completed numerous jobs during July—two of which were Job Y and...

    Assume a company started and completed numerous jobs during July—two of which were Job Y and Job Z. The company uses two departmental predetermined overhead rates. The rate in the Machining Department is based on machine-hours and the rate in the Assembly Department is based on direct labor-hours. The following additional information from the month of July is available for the company as a whole and for Jobs Y and Z: Machining Assembly Estimated total fixed manufacturing overhead $ 48,000...

  • Jorgensen Corporation uses standard costs with its job order cost accounting system. In January, an order (Job No. 12) for 2,000 units of Product B was received. The standard cost of one unit of Produ...

    Jorgensen Corporation uses standard costs with its job order cost accounting system. In January, an order (Job No. 12) for 2,000 units of Product B was received. The standard cost of one unit of Product B is as follows. Direct materials 3 pounds at $1.10 per pound $3.30 Direct labor 1.70 hour at $8.00 per hour 13.60 Overhead 2 hours (variable $4.40 per machine hour; fixed $2.70 per machine hour) 14.20 Standard cost per unit $31.10 Normal capacity for the...

  • Problem 11-6A (Part Level Submission) Jorgensen Corporation uses standard costs with its job order cost accounting system. In January, an order (Job No. 12) for 2,000 units of Product B was receiv...

    Problem 11-6A (Part Level Submission) Jorgensen Corporation uses standard costs with its job order cost accounting system. In January, an order (Job No. 12) for 2,000 units of Product B was received. The standard cost of one unit of Product B is as follows. 3 pounds at $1.30 per pound $3.90 Direct materials Direct labor 1.30 hour at $10.00 per hour 13.00 2 hours (variable $4.50 per machine hour; fixed $2.60 per machine hour) 14.20 Overhead $31.10 Standard cost per...

  • Job 243 was recently completed. The following data have been recorded on its job cost sheet:...

    Job 243 was recently completed. The following data have been recorded on its job cost sheet: Direct materials Direct labor-hours Direct labor wage rate Machine-hours Number of units completed $57,370 490 labor-hours $ 12 per labor-hour 571 machine-hours 4,400 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $12 per machine-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to 2...

  • Job 243 was recently completed. The following data have been recorded on its job cost sheet...

    Job 243 was recently completed. The following data have been recorded on its job cost sheet $57,870 Direct materials Direct labor-hours Direct labor wage rate Machine-hours Number of units completed 495 labor-hours 11 per labor-hour 576 machine-hours 4,500 units The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $13 per machine- hour Required Compute the unit product cost that would appear on the job cost sheet for this job. (Round your answer to 2...

  • Jorgensen Corporation uses standard costs with its job order cost accounting system. In January, an order...

    Jorgensen Corporation uses standard costs with its job order cost accounting system. In January, an order (Job No. 12) for 1,000 units of Product B was received. The standard cost of one unit of Product B is as follows. 3 pounds at $1.00 per pound Direct materials $3.00 Direct labor 1.50 hour at $10.00 per hour 15.00 2 hours (variable $4.30 per machine hour; fixed $3.30 per machine hour) Overhead 15.20 $33.20 Standard cost per unit Normal capacity for the...

  • Question 10 16 pts The following data has been recorded for recently completed job 674 on...

    Question 10 16 pts The following data has been recorded for recently completed job 674 on its job cost sheet for 3 units. Direct materials cost was $2.039. A total of 32 direct labor hours and 175 machine hours were worked on the job. The direct labor wage rate was $14 per labor hour. The company applies manufacturing overhead on the basis of machine-hours. The predetermined overhead rate is $15 per machine hour. a. What is the direct labor cost...

  • answers to questions 1-6 4-31 Job costing, accounting for manufacturing overhead, budgeted rates. The Fasano Company...

    answers to questions 1-6 4-31 Job costing, accounting for manufacturing overhead, budgeted rates. The Fasano Company uses a job-costing system at its Dover, Delaware, plant. The plant has a machining department and a finishing department. Fasano uses normal costing with two direct-cost categories (direct materials and direct manu- facturing labor) and two manufacturing overhead cost pools (the machining department with machine- hours as the allocation base, and the finishing department with direct manufacturing labor costs as the allocation base). The...

  • 1. Job cost sheets show the following information: Job January February March Completed Sold AA2 $2,400    ...

    1. Job cost sheets show the following information: Job January February March Completed Sold AA2 $2,400     $1,000     February Not sold AA4 4,836     January February AA5 3,260     February March AA3 3,409     $2,320 April Not sold Total $7,236     $7,669     $2,320 What are the balances in the work in process inventory, finished goods inventory, and cost of goods sold for January, February, and March? Work in Process Finished Goods COGS January $2400 $4836 0 February 3409 ??? $4836 March 5729 ??? 3260 ***Need...

  • 4-31 Job costing, accounting for manufacturing overhead, budgeted rates. The Fasano Company uses a job-costing system...

    4-31 Job costing, accounting for manufacturing overhead, budgeted rates. The Fasano Company uses a job-costing system at its Dover, Delaware, plant. The plant has a machining department and a finishing department. Fasano uses normal costing with two direct-cost categories (direct materials and direct manu. facturing labor) and two manufacturing overhead cost pools (the machining department with machine. hours as the allocation base, and the finishing department with direct manufacturing labor costs as the allocation base). The 2011 budget for the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT