Granite Company purchased a machine costing $134,000, terms 3/10, n/30. The machine was shipped FOB shipping point and freight charges were $3,400. The machine requires special mounting and wiring connections costing $11,400. When installing the machine, $2,900 in damages occurred. Compute the cost recorded for this machine assuming Granite paid within the discount period.
Cost recorded for machine = Net purchase price + Freight + Installation = (134,000-3%) + 3,400 + 11,400 = 144,780 |
||
Granite Company purchased a machine costing $134,000, terms 3/10, n/30. The machine was shipped FOB shipping...
Granite Company purchased a machine costing $132,000, terms 1/10, n/30. The machine was shipped FOB shipping point and freight charges were $3,200. The machine requires special mounting and wiring connections costing $11,200. When installing the machine, $2,700 in damages occurred. Compute the cost recorded for this machine assuming Granite paid within the discount period.
The Company purchased a machine costing $126,000, terms 1/10, n/30. The machine was shipped FOB shipping point and freight charges were $2,600. The machine requires special mounting and wiring connections costing $10,600. When installing the machine, $2,100 in damages occurred. Compute the cost recorded for this machine assuming the Company paid within the discount period. Multiple Choice $138,140. $143,200. $141,940. $137,440. $137,940.
Rizio Co. purchases a machine for $9,800, terms 1/10, n/60, FOB shipping point. The seller prepaid the $221 freight charges, adding the amount to the invoice and bringing its total to $10,021. The machine requires special steel mounting and power connections costing $677. Another $319 is paid to assemble the machine and get it into operation. In moving the machine to its steel mounting, $305 in damages occurred. Materials costing $40 are used in adjusting the machine to produce a...
10 Rizio Co. purchases a machine for $13,600, terms 2/10, n/60, FOB shipping point. The seller prepaid the $307 freight charges, adding the amount to the invoice and bringing its total to $13.907. The machine requires special steel mounting and power connections costing $940. Another $443 is paid to assemble the machine and get it into operation. In moving the machine to its steel mounting $260 in damages occurred. Materials costing $40 are used in adjusting the machine to produce...
Rizio Co. purchases a machine for $11,600, terms 2/10, n/60, FOB shipping point. The seller prepaid the $262 freight charges, adding the amount to the invoice and bringing its total to $11,862. The machine requires special steel mounting and power connections costing $802. Another $378 is paid to assemble the machine and get it into operation. In moving the machine to its steel mounting, $275 in damages occurred. Materials costing $40 are used in adjusting the machine to produce a...
Rizio Co. purchases a machine for $14,300, terms 1/10, n/60, FOB
shipping point. The seller prepaid the $323 freight charges, adding
the amount to the invoice and bringing its total to $14,623. The
machine requires special steel mounting and power connections
costing $989. Another $466 is paid to assemble the machine and get
it into operation. In moving the machine to its steel mounting,
$350 in damages occurred. Materials costing $40 are used in
adjusting the machine to produce a...
Rizio Co purchases a machine for $13,800, terms 1/10. n/60, FOB shipping point. The seller prepaid the $312 freight charges, adding the amount to the invoice and bringing its total to $14.112. The machine requires speci $954. Another $450 is paid to assemble the machine and get it into operation. In moving the machine to its steel mounting. $365 in damages occurred. Materials costing $40 are used in adjusting the machine to produce a satisfactory product. The adjustments are normal...
Dalton Company purchased a machine for $12,000, terms 1/10, n/60, FOB shipping point. The seller prepaid the freight charges, $290, and sent a second invoice for the freight. Dalton took advantage of the discount on the first invoice, but the discount was not available on the freight invoice. The machine required a special steel mounting and power connections costing $825, and another $420 was paid to assemble the machine and get it into operation. In moving the machine onto its...
Exercise 8-1 Cost of plant assets LO C1 Rizio Co. purchases a machine for $11,300, terms 2/10, n/60, FOB shipping point. The seller prepaid the $255 freight charges, adding the amount to the invoice and bringing its total to $11,555. The machine requires special steel mounting and power connections costing $781. Another $368 is paid to assemble the machine and get it into operation. In moving the machine to its steel mounting, $360 in damages occurred. Materials costing $40 are...
Dalton Company purchased a machine for $11,000 terms 2/10, 1/60, FOB shipping point. The seller prepaid the freight charges, $280, and sent a second invoice for the freight. Dalton took advantage of the discount on the first Invoice, but the discount was not available on the freight invoice. The machine required a special steel mounting and power connections costing $815, and another $405 was paid to assemble the machine and get it into operation. In moving the machine onto its...