Granite Company purchased a machine costing $134,000, terms 3/10, n/30. The machine was shipped FOB shipping point and freight charges were $3,400. The machine requires special mounting and wiring connections costing $11,400. When installing the machine, $2,900 in damages occurred. Compute the cost recorded for this machine assuming Granite paid within the discount period.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Cost recorded for machine

= Net purchase price + Freight + Installation

= (134,000-3%) + 3,400 + 11,400

= 144,780

Add a comment
Know the answer?
Add Answer to:
Granite Company purchased a machine costing $134,000, terms 3/10, n/30. The machine was shipped FOB shipping...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Granite Company purchased a machine costing $132,000, terms 1/10, n/30. The machine was shipped FOB shipping...

    Granite Company purchased a machine costing $132,000, terms 1/10, n/30. The machine was shipped FOB shipping point and freight charges were $3,200. The machine requires special mounting and wiring connections costing $11,200. When installing the machine, $2,700 in damages occurred. Compute the cost recorded for this machine assuming Granite paid within the discount period.

  • The Company purchased a machine costing $126,000, terms 1/10, n/30. The machine was shipped FOB shipping...

    The Company purchased a machine costing $126,000, terms 1/10, n/30. The machine was shipped FOB shipping point and freight charges were $2,600. The machine requires special mounting and wiring connections costing $10,600. When installing the machine, $2,100 in damages occurred. Compute the cost recorded for this machine assuming the Company paid within the discount period. Multiple Choice $138,140. $143,200. $141,940. $137,440. $137,940.

  • Rizio Co. purchases a machine for $9,800, terms 1/10, n/60, FOB shipping point. The seller prepaid...

    Rizio Co. purchases a machine for $9,800, terms 1/10, n/60, FOB shipping point. The seller prepaid the $221 freight charges, adding the amount to the invoice and bringing its total to $10,021. The machine requires special steel mounting and power connections costing $677. Another $319 is paid to assemble the machine and get it into operation. In moving the machine to its steel mounting, $305 in damages occurred. Materials costing $40 are used in adjusting the machine to produce a...

  • 10 Rizio Co. purchases a machine for $13,600, terms 2/10, n/60, FOB shipping point. The seller...

    10 Rizio Co. purchases a machine for $13,600, terms 2/10, n/60, FOB shipping point. The seller prepaid the $307 freight charges, adding the amount to the invoice and bringing its total to $13.907. The machine requires special steel mounting and power connections costing $940. Another $443 is paid to assemble the machine and get it into operation. In moving the machine to its steel mounting $260 in damages occurred. Materials costing $40 are used in adjusting the machine to produce...

  • Rizio Co. purchases a machine for $11,600, terms 2/10, n/60, FOB shipping point. The seller prepaid the $262 freight cha...

    Rizio Co. purchases a machine for $11,600, terms 2/10, n/60, FOB shipping point. The seller prepaid the $262 freight charges, adding the amount to the invoice and bringing its total to $11,862. The machine requires special steel mounting and power connections costing $802. Another $378 is paid to assemble the machine and get it into operation. In moving the machine to its steel mounting, $275 in damages occurred. Materials costing $40 are used in adjusting the machine to produce a...

  • Rizio Co. purchases a machine for $14,300, terms 1/10, n/60, FOB shipping point. The seller prepaid...

    Rizio Co. purchases a machine for $14,300, terms 1/10, n/60, FOB shipping point. The seller prepaid the $323 freight charges, adding the amount to the invoice and bringing its total to $14,623. The machine requires special steel mounting and power connections costing $989. Another $466 is paid to assemble the machine and get it into operation. In moving the machine to its steel mounting, $350 in damages occurred. Materials costing $40 are used in adjusting the machine to produce a...

  • Rizio Co purchases a machine for $13,800, terms 1/10. n/60, FOB shipping point. The seller prepaid...

    Rizio Co purchases a machine for $13,800, terms 1/10. n/60, FOB shipping point. The seller prepaid the $312 freight charges, adding the amount to the invoice and bringing its total to $14.112. The machine requires speci $954. Another $450 is paid to assemble the machine and get it into operation. In moving the machine to its steel mounting. $365 in damages occurred. Materials costing $40 are used in adjusting the machine to produce a satisfactory product. The adjustments are normal...

  • Dalton Company purchased a machine for $12,000, terms 1/10, n/60, FOB shipping point. The seller prepaid...

    Dalton Company purchased a machine for $12,000, terms 1/10, n/60, FOB shipping point. The seller prepaid the freight charges, $290, and sent a second invoice for the freight. Dalton took advantage of the discount on the first invoice, but the discount was not available on the freight invoice. The machine required a special steel mounting and power connections costing $825, and another $420 was paid to assemble the machine and get it into operation. In moving the machine onto its...

  • Exercise 8-1 Cost of plant assets LO C1 Rizio Co. purchases a machine for $11,300, terms...

    Exercise 8-1 Cost of plant assets LO C1 Rizio Co. purchases a machine for $11,300, terms 2/10, n/60, FOB shipping point. The seller prepaid the $255 freight charges, adding the amount to the invoice and bringing its total to $11,555. The machine requires special steel mounting and power connections costing $781. Another $368 is paid to assemble the machine and get it into operation. In moving the machine to its steel mounting, $360 in damages occurred. Materials costing $40 are...

  • Dalton Company purchased a machine for $11,000 terms 2/10, 1/60, FOB shipping point. The seller prepaid...

    Dalton Company purchased a machine for $11,000 terms 2/10, 1/60, FOB shipping point. The seller prepaid the freight charges, $280, and sent a second invoice for the freight. Dalton took advantage of the discount on the first Invoice, but the discount was not available on the freight invoice. The machine required a special steel mounting and power connections costing $815, and another $405 was paid to assemble the machine and get it into operation. In moving the machine onto its...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT