2.
Multiple Production Department Factory Overhead Rates
The total factory overhead for Bardot Marine Company is budgeted for the year at $1,238,250, divided into two departments: Fabrication, $1,053,000, and Assembly, $185,250. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require two direct labor hours in Fabrication and two direct labor hours in Assembly. The bass boats require four direct labor hours in Fabrication and one direct labor hour in Assembly. Each product is budgeted for 6,500 units of production for the year.
If required, round all per unit answers to the nearest cent.
a. Determine the total number of budgeted direct labor hours for the year in each department.
b. Determine the departmental factory overhead rates for both departments.
c. Determine the factory overhead allocated per unit for each product using the department factory overhead allocation rates.
3.
Activity-Based Costing: Factory Overhead Costs
The total factory overhead for Bardot Marine Company is budgeted for the year at $1,382,400, divided into four activities: fabrication, $588,000; assembly, $240,000; setup, $302,400; and inspection, $252,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The activity-base usage quantities for each product by each activity are as follows:
Fabrication | Assembly | Setup | Inspection | |||||
Speedboat | 10,500 | dlh | 30,000 | dlh | 76 | setups | 131 | inspections |
Bass boat | 31,500 | 10,000 | 554 | 919 | ||||
42,000 | dlh | 40,000 | dlh | 630 | setups | 1,050 | inspections |
Each product is budgeted for 3,500 units of production for the year.
a. Determine the activity rates for each activity.
b. Determine the activity-based factory overhead per unit for each product. Round to the nearest whole dollar.
4.
Activity-Based Costing: Selling and Administrative Expenses
Jungle Junior Company manufactures and sells outdoor play equipment. Jungle Junior uses activity-based costing to determine the cost of the sales order processing and the customer return activity. The sales order processing activity has an activity rate of $20 per sales order, and the customer return activity has an activity rate of $100 per return. Jungle Junior sold 2,500 swing sets, which consisted of 750 orders and 80 returns.
a. Determine the total sales order processing and customer return activity cost for swing sets.
b. Determine the per-unit sales order
processing and customer return activity cost for swing sets. Round
your answer to the nearest cent.
5. Single Plantwide Factory Overhead Rate
Kennedy Appliance Inc.’s Machining Department incurred $99,000 of factory overhead cost in producing hoses and valves. The two products consumed a total of 3,000 direct machine hours. Of that amount, hoses consumed 1,400 direct machine hours.
Determine the total amount of factory overhead that should be allocated to hoses using machine hours as the allocation base.
2. | ||||
a. | ||||
Budgeted units of Speedboats | 6500 | |||
Budgeted units of Bassboats | 6500 | |||
Department | Speed boats (DL/ unit) | Bassboats (DL/ unit) | Total Direct labour hours in each department | |
Fabrication | 2 | 4 | = (2*6500) + (4*6500) | 39000 |
Assembly | 2 | 1 | = (2*6500) + (1*6500) | 19500 |
b. | ||||
Total Factory Overhead = $ 1,238,250 | ||||
Department | Fabrication ($) | Assembly ($) | ||
Factory Overhead | 1053000 | 185250 | ||
Department | Fabrication ($) | Assembly ($) | ||
Factory Overhead Rate (per labour hour)= Factory Overhead / Direct labour hours in each department | = 1053000/39000 | = 185250/19500 | ||
= 27 | = 9.5 | |||
c. | ||||
factory overhead allocated per unit | ||||
Department | OH cost per Speed boat = No. of labour hours * OH rate per labour hour | OH cost per Bassboat = No. of labour hours * OH rate per labour hour | ||
Fabrication (A) | = 2*27 | = 4*27 | ||
= 54 | = 108 | |||
Assembly (B) | = 2 * 9.5 | = 1 * 9.5 | ||
= 19 | = 9.5 | |||
factory overhead allocated per unit (A+B) | = 73 | = 117.5 |
2. Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $495,000, divided into two departments: Fabrication, $382,500, and Assembly, $112,500. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require four direct labor hours in Fabrication and three direct labor hours in Assembly. The bass boats require two direct labor hours in Fabrication and two direct labor hours in Assembly. Each product is budgeted for 3,000...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $505,500, divided into two departments: Fabrication, $321,000, and Assembly, $184,500. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require two direct labor hours in Fabrication and two direct labor hours in Assembly. The bass boats require two direct labor hours in Fabrication and four direct labor hours in Assembly. Each product is budgeted for 3,000...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $1,481,250, divided into two departments: Fabrication, $881,250, and Assembly, $600,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require one direct labor hour in Fabrication and four direct labor hours in Assembly. The bass boats require four direct labor hours in Fabrication and four direct labor hours in Assembly. Each product is budgeted for 7,500...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $1,365,000, divided into two departments: Fabrication, $1,071,000, and Assembly, $294,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require four direct labor hours in Fabrication and three direct labor hours in Assembly. The bass boats require two direct labor hours in Fabrication and one direct labor hour in Assembly. Each product is budgeted for 7,000...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $810,875, divided into two departments: Fabrication, $453,375, and Assembly, $357,500 Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require one direct labor hour in Fabrication and four direct labor hours in Assembly. The bass boats require two direct labor hours in Fabrication and one direct labor hour in Assembly. Each product is budgeted for 6,500...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $528,750, divided into two departments: Fabrication, $363,750, and Assembly, $165,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require two direct labor hours in Fabrication and two direct labor hours in Assembly. The bass boats require one direct labor hour in Fabrication and one direct labor hour in Assembly. Each product is budgeted for 5,000...
Multiple Production Department Factory Overhead Rates The total factory overhead for Bardot Marine Company is budgeted for the year at $723,375, divided into two departments: Fabrication, $588,000, and Assembly, 5138,375. Bardot Marine manufactures two types of boats speedboats and bass boats. The speedboatsregione director hour is Fabrication and one director hour in Assembly. The bes t require four direct labor hours in Fabrication and two drector hours in Assembly. Each product is budgeted for 4.500 units of production for the...
BE 4-2 Multiple production department factory overhead rates Obj. 3 The total factory overhead for Bardot Marine Company is budgeted for the year at $600,000 divided into two departments: Fabrication, $420,000, and Assembly, $180,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require 8 direct labor hours in Fabrication and 4 direct labor hours in Assembly. The bass boats require 4 di- rect labor hours in Fabrication and 8 direct labor hours in Assembly. Each...
The total factory overhead for Bardot Marine Company is budgeted for the year at $897,000, divided into two departments: Fabrication, $711,000, and Assembly, $186,000. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require three direct labor hours in Fabrication and three direct labor hours in Assembly. The bass boats require three direct labor hours in Fabrication and one direct labor hour in Assembly. Each product is budgeted for 6,000 units of production for the year....
The total factory overhead for Bardot Marine Company is budgeted for the year at $1,027,000, divided into two departments: Fabrication, $526,500, and Assembly, $500,500. Bardot Marine manufactures two types of boats: speedboats and bass boats. The speedboats require one direct labor hour in Fabrication and three direct labor hours in Assembly. The bass boats require two direct labor hours in Fabrication and four direct labor hours in Assembly. Each product is budgeted for 6,500 units of production for the year....