Question

Question 14: A firm is considering Projects S and L, whose cash flows are shown below....

Question 14:

A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable.

r:

6.00%

Year

0

1

2

3

4

CFS

−$1,025

$380

$380

$380

$380

CFL

−$2,150

$765

$765

$765

$765

The CEO wants to use the IRR criterion, while the CFO favors the NPV method.

You were hired to advise on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose?

(this question is very challenging. It is fine if you can figure out the solution.)

0 0
Add a comment Improve this question Transcribed image text
Answer #1

IRR is the internal rate of return such that the Net Present Value of a set of cashflows from an investment/project will equal to its initial investment. This inturn determines the performance return of the project investment.

NPV on the other hand is the sum of the discounted values of all the cashflows to today's value discounted by the interest rate.

In the example, we will calculate IRR using Excel IRR method which takes in the set of cash flows and NPV by discounting each cash flow by 6%. This is copied in the table below:

Year Year CFS CFL PV PV
01-Jan-10 0 -1025 -2150 -1025 -2150
01-Jan-11 1 $380 $765 $358.49 $721.70
01-Jan-12 2 $380 $765 $338.20 $680.85
01-Jan-13 3 $380 $765 $319.06 $642.31
01-Jan-14 4 $380 $765 $301.00 $605.95
IRR 17.861% 15.781% NPV $291.74 $500.81

Copying the formula sheet below:

r 0.06
Year CFS CFL PV PV
0 -1025 -2150 =B4 =C4
1 380 765 =B5/(1+$B$1)^$A5 =C5/(1+$B$1)^$A5
2 380 765 =B6/(1+$B$1)^$A6 =C6/(1+$B$1)^$A6
3 380 765 =B7/(1+$B$1)^$A7 =C7/(1+$B$1)^$A7
4 380 765 =B8/(1+$B$1)^$A8 =C8/(1+$B$1)^$A8
IRR =IRR(B4:B8) =IRR(C4:C8) NPV =SUM(E4:E8) =SUM(F4:F8)

IRR criterion is best suited when multiple projects that are compared have the same initial investment. This gives a fair comparison criteria as the one with higher returns will be preferred.

When it comes to improving the profitability of the firm, then the project with higher NPV will be profitable because it gives higher profit as compared to other projects.

In this case, IRR of CFS is higher than CFL, however NPV of CFL is higher than CFS.

Hence, if IRR is used instead of NPV, then there is a potential loss of NPV(CFL) - NPV(CFS) = 500.81 - 291.74 = $209.07

Add a comment
Know the answer?
Add Answer to:
Question 14: A firm is considering Projects S and L, whose cash flows are shown below....
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A firm is considering Projects S and L, whose cash flows are shown below. These projects...

    A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 6.75% 0 1 2 3 4 CFS -$1,025 $380 $380 $380 $380 CFL -$2,150...

  • A firm is considering Projects S and L, whose cash flows are shown below. These projects...

    A firm is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise the firm on the best procedure. If the wrong decision criterion is used, how much potential value would the firm lose? WACC: 6.75% 0 1 2 3 4 CFS -$1,025 $380 $380 $380 $380 CFL -$2,150...

  • Murray Inc. is considering Projects S and L, whose cash flows are shown below. These projects...

    Murray Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO wants to use the IRR criterion, while the CFO favors the NPV method. You were hired to advise Murray on the best procedure. If the wrong decision criterion is used, how much potential value would Murray lose? r. 6.00% Year 0 1 2 3 4 CFS −$1,025 $380 $380 $380 $380 CFL −$2,150 $765...

  • Stalwork Enterprises is considering Projects Land M, whose cash flows are as follows: Project L cash...

    Stalwork Enterprises is considering Projects Land M, whose cash flows are as follows: Project L cash flows will be -$1,025, $380, $380, $380, $380. Project M cash flows will be -$2,150, $765, $765, $765, $765. The CEO wants to use the IRR criterion, while the CFO favors the NPR method. You were hired to advise the firm on the best method. If the wrong decision criterion is used, how much potential value would the firm lose? A) $214.44 B) $186.47...

  • Moerdyk & Co. is considering Projects S and L, whose cash flows are shown below. These...

    Moerdyk & Co. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, i.e., no...

  • Question 3 of 24 Tesar Chemicals is considering Projects S and L, whose cash flows are...

    Question 3 of 24 Tesar Chemicals is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates the NPV. If the decision is made by choosing the project with the higher IRR rather than the one with the higher NPV, how much, if any, value will be forgone, i.e., what's the chosen NPV versus the...

  • 1) Last month, Standard Systems analyzed the project whose cash flows are shown below. However, before...

    1) Last month, Standard Systems analyzed the project whose cash flows are shown below. However, before the decision to accept or reject the project took place, the Federal Reserve changed interest rates and therefore the firm's cost of capital (r). The Fed's action did not affect the forecasted cash flows. By how much did the change in the r affect the project's forecasted NPV? Note that a project's expected NPV can be negative, in which case it should be rejected....

  • Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...

    Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? WACC: 8% Year 0 1 2 3 4 CFS -$1,100 $380 $380 $380 $380 CFL -2,200 $730 $730 $730 $730 Options: 59.24, 52,83, 48,56, 43.70, 39.24

  • Sexton Inc. is considering Projects S and L, whose cash flows are shown below. These projects...

    Sexton Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, so no value...

  • Carolina Company is considering Projects S and L, whose cash flows are shown below. These projects...

    Carolina Company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and are not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under some conditions choosing projects on the basis of the IRR will cause $0.00 value to be lost. Identify also the range of discounting rates in which project L will be selected. WACC: Year...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT