1.
Units completed = 36,300 + 90,800 - 33,800 = 93,300
Physical units | Physical units | |||
Beginning units | 36,300 | Units completed | 93,300 | |
Units started | 90,800 | Ending units | 33,800 | |
Total units | 127,100 | Total units | 127,100 |
2.
Conversion ending units = 33,800 X 20% = 6,760
Equivalent | Units | ||
Physical units | Direct material | Conversion | |
Units completed | 93,300 | 93,300 | 93,300 |
Ending inventory | 33,800 | 33,800 | 6,760 |
Total units | 127,100 | 127,100 | 100,060 |
3.
Cost per equivalent units = (Beginning cost + May cost) / Equivalent units
Direct material | Conversion | |
Cost per equivalent unit | $1.32258 | $2.77434 |
4.
Direct material | Conversion | Total cost | |
Units completed | $123,397 | $258,846 | $382,243 |
Ending inventory | $44,703 | $18,754 | $63,457 |
Total cost accounted for | $168,100 | $277,600 | $445,700 |
(The following information applies to the questions displayed below.) Legacy Company manufactures umbrellas and has the...
Legacy Company manufactures umbrellas and has the following information available for the month of May Work in process, May 1 (100% complete for materials, 86% for conversion) Direct materials Conversion cost 78,000 units $131,000 $176,000 Number of units started 183,000 units May costs Direct materials Conversion cost $200,000 $377,000 Work in process, May 31 (100% complete for materials, 22% for conversion) 57,000 units Required: Using the weighted-average method of process costing, complete each the following steps: 1. Reconcile the number...
[The following information applies to the questions displayed below.] Silver Company manufactures kites and has the following information available for the month of April: Work in process, April 1 (100% complete for materials, 40% for conversion) 58,000 units Direct materials $ 86,000 Conversion cost $ 116,000 Number of units started 164,000 units April costs Direct materials $ 232,000 Conversion cost $ 342,000 Work in process, April 30 (100% complete for materials, 20% for conversion) 83,000 units Required: Using the weighted-average...
e-Built Problems Required information (The following information applies to the questions displayed below) Mirada Company manufactures handheld calculators and has the following information available for the month of July. Work in process, July 1 (100% complete for materials, 25% for conversion) Direct materials Conversion cost 124,000 units $ 238,000 $ 392,000 Number of units started 218,000 units July costs Direct materials Conversion cost $ 424,000 $ 482,000 Work in process, July 31 (100% complete for materials, 10% for conversion) 142,000...
Required information [The following information applies to the questions displayed below.] Stem Games manufactures playing cards. It has three departments: Printing, Cutting & Collating, and Wrapping. Transferred-in costs are considered materials costs. The following information is available for the Wrapping department for the month of October: Physical Units 283,000 Beginning work in process (100% complete for materials, 80% complete for conversion) Decks transferred in Decks completed and transferred to Finished Goods Inventory Ending Work in Process (100% complete for materials,...
Required information (The following information applies to the questions displayed below. 1.5 points Stem Games manufactures playing cards. It has three departments: Printing, Cutting & Collating, and Wrapping. Transferred-in costs are considered materials costs. The following information is available for the Wrapping department for the month of October: eBook Physical Units 280,000 Hint Beginning work in process (100% complete for materials, 808 completo for conversion) Decks transferred in Decks completed and transferred to Finished Goods Inventory Ending Work in Process...
Required information [The following information applies to the questions displayed below.) Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows: Costs Units 127,800 $ 182,000 334,000 $ 516,000 Beginning work in process (30% complete) Direct materials Conversion cost Total cost of beginning work in process Number of units started Number of units completed and transferred to finished goods Ending work...
Required information [The following information applies to the questions displayed below.] Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows: Units Costs Beginning work in process (30% complete) 127,800 Direct materials $ 182,000 Conversion cost 334,000 Total cost of beginning work in process $ 516,000 Number of units started 233,000 Number of units completed and transferred to finished goods 333,800...
[The following information applies to the questions displayed below.] Saddleback Company makes camping lanterns using a single production process. All direct materials are added at the beginning of the manufacturing process. Information for the month of March follows: Units Costs Beginning work in process (30% complete) 121,300 Direct materials $ 199,000 Conversion cost 351,000 Total cost of beginning work in process $ 550,000 Number of units started 250,000 Number of units completed and transferred to finished goods 335,500 Ending work...
Silver Company manufactures kites and has the following information available for the month of April: Work in process, April 1 (100% complete for materials, 40% for conversion) Direct materials Conversion cost 44,000 units $ 72,000 $ 102,000 Number of units started 150,000 units April costs Direct materials Conversion cost $ 218,000 $ 328,000 Work in process, April 30 (100% complete for materials, 20% for conversion) 76,000 units Required: Using the weighted average method, complete each of the following steps: 1....
Silver Company manufactures kites and has the following information available for the month of April: Work in process, April 1 (100% complete for materials, 40% for conversion) 44,000 units Direct materials $ 72,000 Conversion cost $ 102,000 Number of units started 150,000 units April costs Direct materials $ 218,000 Conversion cost $ 328,000 Work in process, April 30 (100% complete for materials, 20% for conversion) 76,000 units Required: Using the weighted-average method, complete each of the following steps: 2. Calculate...