1 | ||
Estimated variable manufacturing overhead | 6800 | =(2500*1.4)+(1500*2.2) |
Estimated total fixed manufacturing overhead | 25000 | |
Estimated total manufacturing overhead | 31800 | |
Divide by Estimated total machine-hours used | 4000 | |
Predetermined overhead rate | 7.95 | per MH |
View previous company has two manufacturing departments--Molding and Fabrication. It started, completed, and sold only two...
two manufacturing departments. Molding and Fabrication. It started, completed, and sold only two jobs during March --Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and (all data and questions relate to the month of March): Estimated total machine-hours used Molding Fabrication Total 2,500 Estimated total fixed manufacturing overhead 1,500 4,000 $13,250 $16,950 $30,200 Estimated variable manufacturing overhead per machine-hour $ 2.70 Direct materials Direct labor cost Actual...
two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and (all data and questions relate to the month of March Part of Estimated total achie-hours used Estimated total fixed manufacturing overhead Eatiated variable manufacturing overhead per machine-hour $ 15,600 526,600 27 Directoriale Direct labor cost Actualmine hours used $17.000 $24,200 Job 10.000 9,100...
9. What were the company’s predetermined
overhead rates in the Molding Department and the Fabrication
Department? (Round your answers to 2 decimal
places.)
10. How much manufacturing overhead was applied
from the Molding Department to Job P and how much was applied to
Job Q? (Do not round intermediate
calculations.)
11. How much manufacturing overhead was applied
from the Fabrication Department to Job P and how much was applied
to Job Q? (Do not round intermediate
calculations.)
12. If Job...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours used Estimated total fixed manufacturing overhead Estimated variable manufacturing overhead...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Estimated total machine-hours used Estimated total fixed manufacturing overhead Estimated variable manufacturing overhead per...
The Foundational 15 (LO2-1, LO2-2, LO2-3, LO2-4) [The following information applies to the questions displayed below.) Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the...
8 Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments-Molding and Fabrication. It started, completed, and sold only two jobs during March- Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March); Estimated total machine-hours used Estimated total fixed manufacturing overhead Estimated variable manufacturing...
2. How much
manufacturing overhead was applied to Job P and how much was
applied to Job Q?
Required information (The following information applies to the questions displayed below.] Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments --Molding and Fabrication. It started, completed, and sold only two jobs during March-Job P and Job Q. The following additional information is available for the company as a whole and...
Sweeten Company had no jobs in progress at the beginning of March and no beginning inventories. The company has two manufacturing departments --Molding and Fabrication. It started, completed, and sold only two jobs during March-Job P and Job Q. The following additional information is available for the company as a whole and for Jobs P and Q (all data and questions relate to the month of March): Molding Fabrication Total Estimated total machine-hours used 2,500 1,500 4,000 Estimated total fixed...