Rent = r = 10000
Wages = w = 5000
K = 5
Material cost = 2000 ( Variable cost )
Production function = Q = 5KL
Q = 5*5*L
L = Q/25
Total cost = Variable cost + fixed cost
Variable cost = Material cost * Production function+ wL
VC = 2000Q + (5000*Q/25)
VC = 2200Q
Fixed cost = FC = rK
FC = 10000*5 = 50000
TC = Total cost = VC + FC
TC = 2200Q+50000
Answer: d
A company produces car engines with the following technology: Q=5KL where K denotes the number of...
A company produces car engines with the following technology: Q=5KL where K denotes the number of conveyor belts and L denotes the number of working teams. The rent for one conveyor belt is 10000 per week and one team of workers costs 5000 per week. Additionally, each engine requires materials costing 2000. Imagine that the number of conveyor belts is fixed to five in the short-run What is the average short-run production cost of one engine, when total output equals...