Project K costs $70,000, its expected cash inflows are $10,000 per year for 8 years, and its WACC is 13%. What is the project's payback? Round your answer to two decimal places.
Period | Cash flow | PV factor 13% | PV of cash flow | Cumulative Cash flow |
0 | -70000 | 1.0000 | (70,000.00) | (70,000.00) |
1 | 10000 | 0.8850 | 8,849.56 | (61,150.44) |
2 | 10000 | 0.7831 | 7,831.47 | (53,318.98) |
3 | 10000 | 0.6931 | 6,930.50 | (46,388.47) |
4 | 10000 | 0.6133 | 6,133.19 | (40,255.29) |
5 | 10000 | 0.5428 | 5,427.60 | (34,827.69) |
6 | 10000 | 0.4803 | 4,803.19 | (30,024.50) |
7 | 10000 | 0.4251 | 4,250.61 | (25,773.90) |
8 | 10000 | 0.3762 | 3,761.60 | (22,012.30) |
Since cumulative is cash flow is negative no payback period
Project K costs $70,000, its expected cash inflows are $10,000 per year for 8 years, and...
Project K costs $45,000, its expected cash inflows are $15,000 per year for 8 years, and its WACC is 11%. What is the project's MIRR? Round your answer to two decimal places. Project K costs $55,000, its expected cash inflows are $13,000 per year for 8 years, and its WACC is 7%. What is the project's discounted payback? Round your answer to two decimal places.
11-8: Payback Period Payback period Project K costs $70,000, its expected cash inflows are $15,000 per year for 9 years, and its WACC is 14%. what is the project's payback? Round your answer to two decimal places. years
1A. Project L costs $35,000, its expected cash inflows are $9,000 per year for 8 years, and its WACC is 10%. What is the project's NPV? Round your answer to the nearest cent. Do not round your intermediate calculations. 1B. Project L costs $46,724.57, its expected cash inflows are $9,000 per year for 11 years, and its WACC is 9%. What is the project's IRR? Round your answer to two decimal places. 1C. Project L costs $65,000, its expected cash...
Project K costs $45,000, its expected cash inflows are $11,000 per year for 8 years, and its WACC is 8%. What is the project's discounted payback? Round your answer to two decimal places.
1.Project L costs $35,000, its expected cash inflows are $13,000 per year for 9 years, and its WACC is 9%. What is the project's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. 2.Project L costs $50,011.04, its expected cash inflows are $12,000 per year for 8 years, and its WACC is 11%. What is the project's IRR? Round your answer to two decimal places 3.Project L costs $60,000, its expected cash inflows are $15,000 per...
Project L costs $65,000, its expected cash inflows are $10,000 per year for 9 years, and its WACC is 13%. What is the project's payback? Round your answer to two decimal places. _____years
Project K costs $55,000, its expected cash inflows are $13,000 per year for 8 years, and its WACC is 7%. What is the project's discounted payback? Round your answer to two decimal places.
3. Project L costs $70,000, its expected cash inflows are $13,000 per year for 8 years, and its WACC is 10%. What is the project's payback? Round your answer to two decimal places. (Please show work so I understand the process.) _________ years Please do not answer if you are not sure thank you! :)
4.Project L costs $35,000, its expected cash inflows are $15,000 per year for 8 years, and its WACC is 12%. What is the project's payback? Round your answer to two decimal places. 5.Project L costs $60,000, its expected cash inflows are $14,000 per year for 8 years, and its WACC is 13%. What is the project's discounted payback? Do not round intermediate calculations. Round your answer to two decimal places.
Project K costs $48,457.36, its expected cash inflows are $10,000 per year for 11 years, and its WACC is 12%. What is the project's IRR? Round your answer to two decimal places.