a)At this time, The current cost over(under) on the project is calculated below:
The current cost over(under) on the project = Actual Cost - Budgeted Cost
= $8,120 - $7,650
= $470
At this time, The current cost over on the project is in Dollar = $470*1000 = $470,000
b)At this time, far ahead or behind schedule is the project in the terms of percentage of completion is calculated below:
far ahead or behind schedule is the project in the terms of percentage of completion = Project's Current percentage of completion - Project's Budgeted percentage of completion
= 80.0% - 70.0% = 10.0%
So,the project is ahead the schedule in terms of percentage of completion by 10%
A. Current cost = 80% budgeted cost - 80% actual cost
= 9,180-8,120 = 1,060 (remember that these costs are written in thousands of $)
The project is currently under budget because the budgeted cost is greater than actual cost.
Answer: Current Cost is $1,060,000 under budget
B. Percentage of Completion = Project's Actual Percentage of Completion - Project's Budgeted Percentage of Completion
In this case, we are at 15 weeks so we will subtract Project Actual Percentage at 15 weeks (80%) from Budgeted Percentage at 15 weeks (70%)
=80%-70% = 10%
So,the project is ahead the schedule because Actual Percentage Complete is greater than Budgeted Percentage Complete.
Answer: Percentage of Completion 10% ahead of schedule
Spot Construction builds roads, bridges, and other infrastructure. The following is the budget for a road...
Spot Construction builds roads, bridges, and other infrastructure. The following is the budget for a road project along with the actual results (in thousands of dollars) for the last fifteen months. Month 1 m in Actual Cost Complete $ 0 0.0% $ 700 5.5% $ 1,160 11.2% $ 1,820 13.4% $ 2,270 21.6% $ 2,810 27.5% $ 3,190 34.0% $ 3,870 36.5% $ 4,200 45.0% $ 4,710 48.8% $ 5,400 53.4% $ 5,920 56.7% $ 6,300 62.3% $ 7,190 70.0%...
Spot Construction builds roads, bridges, and other infrastructure. The following is the budget for a road project along with the actual results (in thousands of dollars) for the last fifteen months. Budget Month Cost Complete $ .ex 1 $ 518 5.0% 2 $ 1,020 10.0% 3 $ 1,530 15.0% 4 $ 2,840 20.0% 5 $ 2,55€ 25.0% 6 $ 3,60 38.0% 7 $ 3,578 35.% 8 $ 4,088 48.8% 9 $ 4,592 45.% 10 $ 5,100 50.0% 11 $ 5,610...