a: IRR rule is applicable to Project 1 since it has conventional cash flows and only 1 sign change
b and c
IRR | NPV at 5% | NPV at 20% | NPV at 50% | |
Project 1 | 10.24% | 22.98 | -32.25 | -85.31 |
Project 2 | 10.30% | -125.70 | 91.28 | -34.88 |
Project 3 | 33.36% | -59.94 | -16.86 | 8.64 |
Workings
20. You have 3 projects with the following cash flows: Year 0 1 2 3 Proient...
You have 3 projects with the following cash flows: O Year Project 1 Project 2 - $149 $21 $42 4 $79 -6,500 - 246 0 0 $58 6,996 81 - 826 20 41 58 a. For which of these projects is the IRR rule reliable? b. Estimate the IRR for each project (to the nearest 1%). c. What is the NPV of each project if the cost of capital is 5%? 20%? 50%? b. Estimate the IRR for each project...
You have 3 projects with the following cash flows: (Click on the following icon in order to copy its contents into a spreadsheet.)Year01234Project 1−$152$21$42$60$80Project 2 −826007,006−6,498Project 322396181 −246a. For which of these projects is the IRR rule reliable?b. Estimate the IRR for each project (to the nearest 1%).c. What is the NPV of each project if the cost of capital is 5%? 20%? 50%?
14) Cedric is considering between two mutually exclusive projects. The following table gives the cash flows of each project: 0 1 2 3 4 A -$50 25 20 20 15 B -$100 20 40 50 60 a. If your discount rate is 6%, what are the NPVs of the two projects? b. What are the IRRs of the two projects? c. Why do IRR and NPV rank the two projects differently? NPV IRR
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 - $50 - $100 Year 1 $25 $18 Year 2 $20 $38 Year 3 $19 $48 Year 4 $16 $60 a. What are the IRRs of the two projects? b. If your discount rate is 5.4%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What...
You are considering the following two projects and can only take one. Your cost of capital is 11.4 %. The cash flows for the two projects are as follows ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$102 $27 $31 $39 $49 B −$102 $49 $39 $31 $20 a. What is the IRR of each project? b. What is the NPV of each project at your cost of capital? c. At what cost of...
You are choosing between two projects. The cash flows for the
projects are given in the following table ($ million):
a. What are the IRRs of the two projects?
The IRR for project A is ______%. (Round to one decimal
place.)
The IRR for project B is ______%. (Round to one decimal
place.)
b. If your discount rate is 4.8 %, what are the NPVs of the
two projects?
If your discount rate is 4.8%, the NPV for project A...
Consider the following two independent investment projects: Cash flows of project A: 0 1 2 3 T + + 100 -130 50 5 Cash flows of project B: 0 2 3 4 5 + + + + 다. -130 90 40 40 40 40 If management only accepts projects that pay back in 3 years or less, according to the discounted payback period rule, which projects will be selected? Use a discount rate of 10%.
Refer to two projects with the following cash flows: Year Project A Project B 0 -$120 -$120 1 50 60 2 50 60 3 50 60 4 50 If the opportunity cost of capital is 13%, what is the profitability index for each project? (Round to 4 decimal places.) Does the profitability index rank the projects A and B correctly?
Your boss hands you the following information for a pair of mutually exclusive projects and asks for your recommendation. What should you do? Project Cost of Capital 13% 13% IRR 18% 28% Year 0 - $10,000 - $10,000 Cash Flows Year 1 Year 2 $7000 $4000 $2500 $7000 Year 3 $2000 $8000 The NPV of project A is $ , and the NPV of project B is $ (Round to two decimal places as needed.) . Using the NPV rule,...
Here are the expected cash flows for three projects: Project Year: 2 0 - 5,300 - 1,300 - 5,300 Cash Flows (dollars) 1 + 1,075 + 1,075 + 3,150 0 + 1,300 + 2,150 + 1,075 + 1,075 + 3,150 0 + 3,150 + 5,150 a. What is the payback period on each of the projects? b. If you use the payback rule with a cutoff period of 2 years, which projects will you accept? c. If you use a...