As project 2 has unconventional cash flows, IRR rule is reliable for project 1 and Project 3. A conventional cash flow pattern is one which has only a single change in cash flow direction.
Formulae
You have 3 projects with the following cash flows: O Year Project 1 Project 2 -...
20. You have 3 projects with the following cash flows: Year 0 1 2 3 Proient Project 1 -150 20 40 60 80 Project 2 -825 0 0 7000 -6500 Project 3 20 40 60 80 -245 a. For which of these projects is the IRR rule reliable? b. Estimate the IRR for each project to the nearest 1%). c. What is the NPV of each project if the cost of capital is 5%? 20%? 50%?!
You have 3 projects with the following cash flows: (Click on the following icon in order to copy its contents into a spreadsheet.)Year01234Project 1−$152$21$42$60$80Project 2 −826007,006−6,498Project 322396181 −246a. For which of these projects is the IRR rule reliable?b. Estimate the IRR for each project (to the nearest 1%).c. What is the NPV of each project if the cost of capital is 5%? 20%? 50%?
You are considering the following two projects and can only take one. Your cost of capital is 11.4 %. The cash flows for the two projects are as follows ($ million): Project Year 0 Year 1 Year 2 Year 3 Year 4 A −$102 $27 $31 $39 $49 B −$102 $49 $39 $31 $20 a. What is the IRR of each project? b. What is the NPV of each project at your cost of capital? c. At what cost of...
1. Consider two projects with the following (after-tax) cash flows. Project A: CF1 50, CF2 55, CF3 85. Project B: CF1 140. Both projects require an initial investment of 100. Assume the cost of capital for both projects is r 5%. (a) Compute NPV and IRR for project A. (b) Compute NPV and IRR for project B. (c) Assume you replicate project B twice, i.e. reinvest 100 in t 1 and t2. Compute the NPV and IRR of the replicated...
You are choosing between two projects. The cash flows for the
projects are given in the following table ($ million):
a. What are the IRRs of the two projects?
The IRR for project A is ______%. (Round to one decimal
place.)
The IRR for project B is ______%. (Round to one decimal
place.)
b. If your discount rate is 4.8 %, what are the NPVs of the
two projects?
If your discount rate is 4.8%, the NPV for project A...
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 1 Year 2 Year 0 - $51 - $102 $26 $20 Year 3 $20 $49 Year 4 $12 $58 $21 $38 a. What are the IRRs of the two projects? b. If your discount rate is 4.7%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What...
You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): Project Year 0 Year 1 Year 2 -$52 $26 $22 - $102 $20 $41 Year 4 Year 3 $21 $49 $14 $58 a. What are the IRRs of the two projects? b. If your discount rate is 5.5%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? a. What are...
Problem 8-27 (bookmatch) Question Help O You are considering the following two projects and can take only one. Your cost of capital is 11.0%. The cash flows for the two projects are as follows ($ million): Project Year 1 Year 0 - $100 - $100 $25 $50 Year 2 $30 $40 $30 Year 3 $40 $30 Year 4 $50 $20 a. What is the IRR of each project? b. What is the NPV of each project at your cost of...
1. You have the chance to participate in a project that produces the following cash flows: Cash Flows ($) C0 C1 C2 4,600 4,400 –10,800 a. The internal rate of return is 12.69%. If the opportunity cost of capital is 12%, what is the NPV of the project? (A negative answer should be indicated by a minus sign. Do not round intermediate calculations. Round your answer to 2 decimal places.) NPV $ __________. 2. Consider the following projects: Cash Flows...
1) A project has annual cash flows of $5,000 for the next 10 years and then $6,500 each year for the following 10 years. The IRR of this 20-year project is 12%. If the firm's WACC is 11%, what is the project's NPV? Do not round intermediate calculations. Round your answer to the nearest cent. 2) Project S costs $12,000 and its expected cash flows would be $7,000 per year for 5 years. Mutually exclusive Project L costs $25,000 and...