Solution
Material | Conversion | |
Equivalent Units of Production | 509,250 | 489,750 |
.
Material | Conversion | |
Cost per equivalent Unit | $ 1.22 | $ 0.16 |
.
Material | Conversion | Total | |
Ending Inventory | $ 35,685 | $ 1,560 | $ 37,245 |
.
Material | Conversion | Total | |
Units Completed and transferred | $ 585,600 | $ 76,800 | $ 662,400 |
.
Cost Reconciliation | |
Costs to be accounted for: | |
Beginning Wip cost | $ 112,300 |
Cost incurred during period | $ 587,345 |
Total cost to be accounted for | $ 699,645 |
Costs accounted for as follows: | |
Cost of Units Transferred Out | $ 662,400 |
Cost of Ending Wip | $ 37,245 |
Total cost accounted for | $ 699,645 |
Working
Statement of Equivalent Units(Weighted average) | |||||||
Material | Conversion cost | ||||||
Units | Complete % | Equivalent units | Complete % | Equivalent units | |||
Transferred out | 480,000 | 100% | 480,000 | 100% | 480,000 | ||
Ending WIP | 39,000 | 75% | 29,250 | 25% | 9,750 | ||
Total | 519,000 | Total | 509,250 | Total | 489,750 |
.
Cost per Equivalent Units (Weighted average) | ||||
COST | Material | Conversion cost | TOTAL | |
Beginning WIP Inventory Cost | $ 100,200 | $ 12,100 | $ 112,300 | |
Cost incurred during period | $ 521,085 | $ 66,260 | $ 587,345 | |
Total Cost to be accounted for | $ 621,285 | $ 78,360 | $ 699,645 | |
Total Equivalent Units | 509,250 | 489,750 | ||
Cost per Equivalent Units | $ 1.22 | $ 0.16 | $ 1.38 |
.
Statement of cost (Weighted average) | |||||
Cost | Equivalent Cost/unit | Ending WIP | Transferred | ||
Units | Cost Allocated | Units | Cost Allocated | ||
Material | $ 1.22 | 29,250 | $ 35,685.00 | 480,000 | $ 585,600 |
Conversion cost | $ 0.16 | 9,750 | $ 1,560.00 | 480,000 | $ 76,800 |
TOTAL | $ 699,645 | TOTAL | $ 37,245 | TOTAL | $ 662,400 |
Builder Products, Inc., uses the weighted average method in its process costing system. It manufactures a...
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: 79,000 440,000 ? 39,000 Production data: Pounds in process, May 1; materials 100% complete; conversion 901 complete Pounds started into production during May Pounds completed and transferred out Pounds in process, May 31; materials 758 complete; conversion 256 complete Cost data:...
Builder Products, Inc., uses the weighted average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: 81,000 460,000 55,000 Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete Pounds started into production during May Pounds completed and transferred out Pounds in process, May 31; materials 80% complete; conversion 20% complete Cost data:...
Builder Products, Inc., uses the weighted average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: 80,000 450,000 Production data: Pounds in process, May 1; materials 100% complete: conversion 90% complete Pounds started into production during May Pounds completed and transferred out Pounds in process, May 31; materials 60% complete; conversion 48% complete Cost data: Work...
Builder Products, Inc., uses the weighted average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete 60,000 Pounds started into production during May 250,000 Pounds completed and transferred out Pounds in process, May 31; materials 608 complete; conversion 40% complete 20,000 Cost data:...
Builder Products, Inc., uses the weighted average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion Information on work in the first department, Cooking, is given below for May 83.009 480,000 Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete Pounds started into production during May Pounds completed and transferred out Pounds in process, May 31; materials 75% complete; conversion 25% complete Cost data: Work...
Builder Products, Inc., uses the weighted average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May 64,000 290,000 ? 24,000 Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete Pounds started into production during May Pounds completed and transferred out Pounds in process, May 31; materials 60% complete; conversion 40% complete Cost...
Builder Products, Inc., uses the weighted average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: 81,000 460,000 55,000 Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete Pounds started into production during May Pounds completed and transferred out Pounds in process, May 31; materials 80% complete; conversion 20% complete Cost data:...
Builder Products, Inc., uses the weighted average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: 89,000 540,000 60,000 Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete Pounds started into production during May Pounds completed and transferred out Pounds in process, May 31; materials 80% complete; conversion 20% complete Cost data:...
Builder Products, Inc., uses the weighted average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete Pounds started into production during May Pounds completed and transferred out Pounds in process, May 31; materials 80% complete; conversion 20% complete 81,000 460,000 ? 55,000 Cost...
\
Builder Products, Inc., uses the weighted-average method in its process costing system. It manufactures a caulking compound that goes through three processing stages prior to completion. Information on work in the first department, Cooking, is given below for May: 74,000 390,000 ? 34,000 Production data: Pounds in process, May 1; materials 100% complete; conversion 90% complete Pounds started into production during May Pounds completed and transferred out Pounds in process, May 31; materials 70% complete; conversion 30% complete Cost...