Given that Contract Price is $35,000,000. Now for the purpose of solution, following calculations have been made,
Calculation of year-wise Revenue and Gross Profit:
2021 | 2022 | |
Costs Incurred to date | $ 45,00,000.00 | $ 130,00,000.00 |
Estimated costs to complete | $ 180,00,000.00 | $ 120,00,000.00 |
Total Costs | $ 225,00,000.00 | $ 250,00,000.00 |
Percentage of Completion | ||
(Current Costs / Total Costs) | 20% | 52% |
Total Revenue to be recognized | ||
(Percentage x Contract Price) | $ 70,00,000.00 | $ 182,00,000.00 |
Less: Revenue for prior year | $ - | $ -70,00,000.00 |
Revenue for Current Year | $ 70,00,000.00 | $ 112,00,000.00 |
Less: Current Year Costs | $ -45,00,000.00 | $ -85,00,000.00 |
Gross Profit to be recognized | $ 25,00,000.00 | $ 27,00,000.00 |
Note: Cost for 2022 = $13,000,000 - $4,500,000 = $8,500,000
Therefore,
(a) In the year 2021, gross profit to be reported amounting to $2,500,000.
(b) In the year 2022, gross profit to be reported amounting to $2,700,000.
(c) Journal entries shall be passed as follows,
Year | Particulars | Amount (Dr.) | Amount (Cr.) |
2021 | Construction in Progress A/c………Dr. | $ 25,00,000.00 | |
Cost of Construction A/c……..Dr. | $ 45,00,000.00 | ||
To, Revenue from Long-term Contracts A/c | $ 70,00,000.00 | ||
(Being Revenue and gross profit for the year 2021 recognized) | |||
2022 | Construction in Progress A/c………Dr. | $ 27,00,000.00 | |
Cost of Construction A/c……..Dr. | $ 85,00,000.00 | ||
To, Revenue from Long-term Contracts A/c | $ 112,00,000.00 | ||
(Being Revenue and gross profit for the year 2022 recognized) |
PART B (15 Points) Label all work and show I un Penner Builders contracted to build...
Ex. 18-126-Percentage-of-completion method. Penner Builders contracted to build a high-rise for $21,000,000. Construction began in 2012 and is expected to be completed in 2015. Data for 2012 and 2013 are: 2012 2013 Costs incurred to date $2,700,000 $7,800,000 Estimated costs to complete 10,800,000 7,200,000 Penner uses the percentage-of-completion method. Instructions (a) How much gross profit should be reported for 2012? Show your computation (b). How much gross profit should be reported for 2013? (C) Make the journal entry to record...
brady construction company contracted to build an apartment for a
price of $6,000,000.
Brady Construction Company contracted to build an apartment complex for a price of $6,000,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred (As of the End During Year of the Year) Situation 2021 2022...
Brady Construction Company contracted to build an apartment
complex for a price of $5,600,000. Construction began in 2021 and
was completed in 2023. The following is a series of independent
situations, numbered 1 through 6, involving differing costs for the
project. All costs are stated in thousands of dollars.
Estimated Costs to Complete
Costs Incurred During Year
(As of the End of the Year)
Situation
2021
2022
2023
2021
2022
2023
1
1,560
2,310
1,080
3,390
1,080
—
2
1,560...
Brady Construction Company contracted to build an apartment
complex for a price of $5,000,000. Construction began in 2021 and
was completed in 2023. The following is a series of independent
situations, numbered 1 through 6, involving differing costs for the
project. All costs are stated in thousands of dollars.
Estimated Costs to Complete
Costs Incurred During Year
(As of the End of the Year)
Situation
2021
2022
2023
2021
2022
2023
1
1,500
2,100
900
3,000
900
—
2
1,500...
Citation Builders, Inc., builds office buildings and
single-family homes. The office buildings are constructed under
contract with reputable buyers. The homes are constructed in
developments ranging from 10−20 homes and are typically sold during
construction or soon after. To secure the home upon completion,
buyers must pay a deposit of 10% of the price of the home with the
remaining balance due upon completion of the house and transfer of
title. Failure to pay the full amount results in forfeiture...
Previous questions have wrong answers on here.
Brady Construction Company contracted to build an apartment complex for a price of $5,200,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Costs Incurred During Year Situation 2021 2022 2023 1 1,520 2,190 960 2 1,520 960 2,480 3 1,520 2,190 1,760 4 520 3,020 1,040...
Brady Construction Company contracted to build an apartment complex for a price of $5,400,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Situation Costs Incurred During Year 2021 2022 2023 1,540 2,250 1,020 1,540 1,020 2,560 1,540 2,250 1,920 540 3,040 1,080 540 3,040 1,580 540 3,040 2,200 Estimated costs to Complete (As...
On June 15, 2021, Sanderson Construction entered into a
long-term construction contract to build a baseball stadium in
Washington, D.C., for $370 million. The expected completion date is
April 1, 2023, just in time for the 2023 baseball season. Costs
incurred and estimated costs to complete at year-end for the life
of the contract are as follows ($ in millions):
2021
2022
2023
Costs incurred during the year
$
70
$
110
$
80
Estimated costs
to complete as of...
On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $310 million. The expected completion date is April 1, 2023, just in time for the 2023 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows $ in millions): 2021 $ 70 2022 $60 30 2023 $30 Costs incurred during the year Estimated costs to complete as of December...
2. Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Situation о» от дома Costs Incurred During Year 2021 2022 2023 1,500 2,100 900 1,500 900 2,400 1,500 2,100 1,600 500 3,000 1,000 500 3,000 1,300 500 3,000 1,800 Estimated...