Problem 2-3 Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost Material cost is $9 per pound. (Round your answers to 2 decimal places.) Workers Material (1lbs) t (units) 25,000 30,000 35,000 45,000 400 450 550 650 12 MFP (Output/Total Cost)
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer

Week Output Total Cost MFP [ANSWER]
1                                              25,000 $10,000 2.50
2                                              30,000 $12,050 2.49
3                                              35,000 $16,150 2.17
4                                              45,000 $25,050 1.80

--Working

Week Workers Total Hours Total Labor cost Overhead Material (lbs) Material Cost Total Cost
[A] [B = A x 40 hours] [C = B x $ 16] [D = C x 1.5] [E] [F = E x $ 9] [G = C+D+F]
1 4 160 $2,560 $3,840 400 $3,600 $10,000
2 5 200 $3,200 $4,800 450 $4,050 $12,050
3 7 280 $4,480 $6,720 550 $4,950 $16,150
4 12 480 $7,680 $11,520 650 $5,850 $25,050
Add a comment
Know the answer?
Add Answer to:
Problem 2-3 Compute the multifactor productivity measure for each of the weeks shown for production of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 2-3 Compute the multifactor productivity measure for each of the weeks shown for production of...

    Problem 2-3 Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor oost Material cost is $9 per pound. (Round your answers to 2 decimal places.) 26,000 31,000 34,000 44,000 540 640 MFP (Output / Total Cost

  • Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars....

    Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost. Material cost is $9 per pound. (Round your answers to 2 decimal places.) Week Output (units) 26,000 31,000 29,000 33,000 Workers Material (1bs) 400 450 490 510 WeekMFP (output/ Total Cost)

  • Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars....

    Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $14. Overhead is 1.5 times weekly labor cost. Material cost is $8 per pound. (Round your answers to 2 decimal places.)       Week Output (units) Workers Material (lbs) 1 29,000 4 470 2 34,000 7 540 3 30,000 7 490 4 35,000 9 530

  • Question 47 5 pts Compute the multifactor productivity measure for each of the weeks shown for...

    Question 47 5 pts Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $12. Overhead is 2 times weekly labor cost. Material cost is $6 per pound. What is the productivity of the most productive week? (Round your answers to 2 decimal places.) Week Output (units) Workers Material (lbs) 30,000 33,000 32,000 36,000 470 550 540 560 2.49 2.23 3.23 2.17 2.99

  • Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars....

    Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost. Material cost is $9 per pound. (Round your answers to 2 decimal places.) ] Week Output (units) Workers Material (lbs) 1: 28,000 7 430 2: 33,000 8 480 3: 32,000 4 520 4: 42,000 9 620

  • Please answer the following question correctly please: Problem 2-3 Compute the multifactor productivity measure for each...

    Please answer the following question correctly please: Problem 2-3 Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost. Material cost is $9 per pound. (Round your answers to 2 decimal places.) Output (units) 32,000 37,000 28,000 38,000 Week Workers Material (lbs) 470 520 480 580 3 Week MFP (output /Total Cost)

  • Problem 2-3 e the multifactor productivity measure for each of the weeks shown for production of...

    Problem 2-3 e the multifactor productivity measure for each of the weeks shown for production of chocolate ba and an hourty wage of $16. Overhead is 15 times weekly labor cost Maternial costis s9 per pound. Round your answers to 2 decinel 33,000 38,000 27,000 37,000 4B0 530 470 570 2 k Prevo S Next > Problem 2-3 Compute the mutifactor productivity measure for each of the weeks shown for production of chocolate bars. Assune 40-hour weeks and an hourly...

  • Chapter 2 Homework 27 Problem 2-3 Compute the multifactor productivity measure for each of the weeks...

    Chapter 2 Homework 27 Problem 2-3 Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost Material cost is $9 per pound. (Round your answers to 2 decimal places.) 10 week Output (units)WorkersMaterial (lbs) 32,900 37,800 28,800 38,8e0 470 520 480 580 (Output/ Total Cost)

  • Use Excel to compute multifactor productivity for the following two weeks. Assume 40-hour weeks and an...

    Use Excel to compute multifactor productivity for the following two weeks. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost. Material cost is $9 per pound. Week            Output(units)        Workers       Material(lbs) 1                    30,000                     6                 450 2                    35,400                     8                 480 How much percent is the productivity increase or decrease in Week 2 compared to Week 1? An Excel file must be uploaded to indicate your computation to get the points of this question.

  • QUESTION 2 3 p Compute the multifactor productivity measure for an 8 hour day in which...

    QUESTION 2 3 p Compute the multifactor productivity measure for an 8 hour day in which the usable output was 630 units, produced by 5 workers who used 905 pounds of materials. Workers have an hourly wage of 17 and material cost is 2.2 per pound. Overhead is 1.5 times labor cost The multifactor productivity (units/S)- decimal places) (round to 4

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT