Problem 2-3 e the multifactor productivity measure for each of the weeks shown for production of chocolate ba and an hourty w
Problem 2-3 Compute the mutifactor productivity measure for each of the weeks shown for production of chocolate bars. Assune
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Formula for Multifactor Productivity = Output/Input

Here, Output will be units

Input will be the total cost.

For Week 1 -

Total Cost = Labor Cost + Material Cost + Overhead Cost

Total Cost = 6*40*16 + 480*9 + 6*40*16*1.5 = 13920

Multi Factor Productivity = 33000/13920 = 2.37 units per $

For Week 2 -

Total Cost = 7*40*16 + 530*9 + 7*40*16*1.5 = 15970

Multi Factor Productivity = 38000/15970 = 2.38 units per $

For Week 3 -

Total Cost = 5*40*16 + 470*9 + 5*40*16*1.5 = 12230

Multi Factor Productivity = 27000/12230 = 2.21 units per $

For Week 4 -

Total Cost = 7*40*16 + 570*9 + 7*40*16*1.5 = 16330

Multi Factor Productivity = 37000/16330 = 2.27 units per $

Add a comment
Know the answer?
Add Answer to:
Problem 2-3 e the multifactor productivity measure for each of the weeks shown for production of...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Problem 2-3 Compute the multifactor productivity measure for each of the weeks shown for production of...

    Problem 2-3 Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor oost Material cost is $9 per pound. (Round your answers to 2 decimal places.) 26,000 31,000 34,000 44,000 540 640 MFP (Output / Total Cost

  • Problem 2-3 Compute the multifactor productivity measure for each of the weeks shown for production of...

    Problem 2-3 Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost Material cost is $9 per pound. (Round your answers to 2 decimal places.) Workers Material (1lbs) t (units) 25,000 30,000 35,000 45,000 400 450 550 650 12 MFP (Output/Total Cost)

  • Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars....

    Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost. Material cost is $9 per pound. (Round your answers to 2 decimal places.) Week Output (units) 26,000 31,000 29,000 33,000 Workers Material (1bs) 400 450 490 510 WeekMFP (output/ Total Cost)

  • Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars....

    Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $14. Overhead is 1.5 times weekly labor cost. Material cost is $8 per pound. (Round your answers to 2 decimal places.)       Week Output (units) Workers Material (lbs) 1 29,000 4 470 2 34,000 7 540 3 30,000 7 490 4 35,000 9 530

  • Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars....

    Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost. Material cost is $9 per pound. (Round your answers to 2 decimal places.) ] Week Output (units) Workers Material (lbs) 1: 28,000 7 430 2: 33,000 8 480 3: 32,000 4 520 4: 42,000 9 620

  • Chapter 2 Homework 27 Problem 2-3 Compute the multifactor productivity measure for each of the weeks...

    Chapter 2 Homework 27 Problem 2-3 Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost Material cost is $9 per pound. (Round your answers to 2 decimal places.) 10 week Output (units)WorkersMaterial (lbs) 32,900 37,800 28,800 38,8e0 470 520 480 580 (Output/ Total Cost)

  • Question 47 5 pts Compute the multifactor productivity measure for each of the weeks shown for...

    Question 47 5 pts Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $12. Overhead is 2 times weekly labor cost. Material cost is $6 per pound. What is the productivity of the most productive week? (Round your answers to 2 decimal places.) Week Output (units) Workers Material (lbs) 30,000 33,000 32,000 36,000 470 550 540 560 2.49 2.23 3.23 2.17 2.99

  • Please answer the following question correctly please: Problem 2-3 Compute the multifactor productivity measure for each...

    Please answer the following question correctly please: Problem 2-3 Compute the multifactor productivity measure for each of the weeks shown for production of chocolate bars. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost. Material cost is $9 per pound. (Round your answers to 2 decimal places.) Output (units) 32,000 37,000 28,000 38,000 Week Workers Material (lbs) 470 520 480 580 3 Week MFP (output /Total Cost)

  • Use Excel to compute multifactor productivity for the following two weeks. Assume 40-hour weeks and an...

    Use Excel to compute multifactor productivity for the following two weeks. Assume 40-hour weeks and an hourly wage of $16. Overhead is 1.5 times weekly labor cost. Material cost is $9 per pound. Week            Output(units)        Workers       Material(lbs) 1                    30,000                     6                 450 2                    35,400                     8                 480 How much percent is the productivity increase or decrease in Week 2 compared to Week 1? An Excel file must be uploaded to indicate your computation to get the points of this question.

  • QUESTION 2 3 p Compute the multifactor productivity measure for an 8 hour day in which...

    QUESTION 2 3 p Compute the multifactor productivity measure for an 8 hour day in which the usable output was 630 units, produced by 5 workers who used 905 pounds of materials. Workers have an hourly wage of 17 and material cost is 2.2 per pound. Overhead is 1.5 times labor cost The multifactor productivity (units/S)- decimal places) (round to 4

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT