Part A
Predetermined overhead rate = Estimated total manufacturing overhead cost / direct labor cost = 982800/819000 = 120%
Part B
Job no.: 50 |
|||
Date |
Direct materials |
Direct labor |
Manufacturing overhead |
Beg. |
23400 |
14040 |
18720 |
Jan. |
11700 |
5850 |
7020 |
$35100 |
$19890 |
$25740 |
|
Cost of completed job |
|||
Direct materials |
35100 |
||
Direct labor |
19890 |
||
Manufacturing overhead |
25740 |
||
Total cost |
$80730 |
5850*120% = 7140
Job no.: 51 |
|||
Date |
Direct materials |
Direct labor |
Manufacturing overhead |
Jan. |
45630 |
29250 |
35100 |
$45630 |
$29250 |
$35100 |
|
Cost of completed job |
|||
Direct materials |
45630 |
||
Direct labor |
29250 |
||
Manufacturing overhead |
35100 |
||
Total cost |
$109980 |
29250*120% = 35100
Job no.: 52 |
|||
Date |
Direct materials |
Direct labor |
Manufacturing overhead |
Jan. |
35100 |
23400 |
28080 |
23400*120% = 28080
Concord Company uses a job order cost system and applies overhead to production on the basis...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,400, direct labor $14,040, and manufacturing overhead $18,720. As of January 1, Job 49 had been completed at a cost of $105,300 and was part of finished goods inventory. There was a $17,550...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,400, direct labor $14,040, and manufacturing overhead $18,720. As of January 1, Job 49 had been completed at a cost of $105,300 and was part of finished goods inventory. There was a $17,550...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,400, direct labor $14,040, and manufacturing overhead $18,720. As of January 1, Job 49 had been completed at a cost of $105,300 and was part of finished goods inventory. There was a $17,550...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,400, direct labor $14,040, and manufacturing overhead $18,720. As of January 1, Job 49 had been completed at a cost of $105,300 and was part of finished goods inventory. There was a $17,550...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,400, direct labor $14,040, and manufacturing overhead $18,720. As of January 1, Job 49 had been completed at a cost of $105,300 and was part of finished goods inventory. There was a $17,550...
Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,400, direct labor $14,040, and manufacturing overhead $18,720. As of January 1, Job 49 had been completed at a cost of $105,300 and was part of finished goods inventory. There was a $17,550...
a= 120% Please assist with the red wrong boxes. Thank you. Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,400, direct labor $14,040, and manufacturing overhead $18,720. As of January 1, Job 49 had been completed at a cost of $105,300...
Coronado Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $ 24,000, direct labor $ 14,400, and manufacturing overhead $ 19,200. As of January 1, Job 49 had been completed at a cost of $ 108,000 and was part of finished goods inventory....
Sheridan Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. Un January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $ 23,600 direct labor $ 14.160 and manufacturing overhead $ 18,880. As of January 1, Job 49 had been completed at a cost of $ 106,200 and was part of finished goods inventory....
Sunland Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,800, direct labor $14,280, and manufacturing overhead $19,040. As of January 1, Job 49 had been completed at a cost of $107,100 and was part of finished goods inventory. There was a $17,850...