1 | ||||
Daisy Products Limited | ||||
Production Budget | ||||
July | August | September | October | |
Budgeted unit sales | 49000 | 56000 | 70000 | 42000 |
Add: Desired ending inventory | 12600 | 14700 | 10500 | 8400 |
Total needs | 61600 | 70700 | 80500 | 50400 |
Less: Beginning inventory | 14000 | 12600 | 14700 | 10500 |
Required production in units | 47600 | 58100 | 65800 | 39900 |
3 | ||||
Daisy Products Limited | ||||
Raw material Purchases Budget | ||||
July | August | September | Third Quarter | |
Production needs (cc) | 142800 | 174300 | 197400 | 514500 |
Add: Desired units of ending raw materials inventory | 87150 | 98700 | 59850 | 59850 |
Total solvent Q80 needs | 229950 | 273000 | 257250 | 574350 |
Less: Units of beginning raw materials inventory | 75600 | 87150 | 98700 | 75600 |
Solvent Q80 purchases (cc) | 154350 | 185850 | 158550 | 498750 |
Daisy Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia. Three cubic centimetres...
Daisy Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia Three cubic centimetres (CC) of solvent Q80 are required to manufacture each unit of Fineclay, one of the company's products. The company is now planning raw materials needs for the third quarter, the quarter in which peak sales of Fineclay occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of each...
Daisy Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia Three cubic centimetres (CC) of solvent Q80 are required to manufacture each unit of Fineclay, one of the company's products. The company is now planning raw materials needs for the third quarter, the quarter in which peak sales of Fineclay occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of each...
Daisy Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia Three cubic centimetres (cc) of solvent Q80 are required to manufacture each unit of Fineclay, one of the company's products. The company is now planning raw materials needs for the third quarter, the quarter in which peak sales of Fineclay occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of each...
Daisy Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia Three cubic centimetres (cc) of solvent Q80 are required to manufacture each unit of Fineclay, one of the company's products. The company is now planning raw materials needs for the third quarter, the quarter in which peak sales of Fineclay occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of each...
Daisy Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia. Three cubic centimetres (cc) of solvent Q80 are required to manufacture each unit of Fineclay, one of the company’s products. The company is now planning raw materials needs for the third quarter, the quarter in which peak sales of Fineclay occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of each...
Daisy Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia. Three cubic centimetres (cc) of solvent Q80 are required to manufacture each unit of Fineclay, one of the company’s products. The company is now planning raw materials needs for the third quarter, the quarter in which peak sales of Fineclay occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of each...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia. Three cubic centimeters (CC) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of each...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company’s products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: The finished goods inventory on hand at the end of each month...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia. Three cubic centimeters (CC) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of each...
Pearl Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia. Three cubic centimeters (cc) of solvent H300 are required to manufacture each unit of Supermix, one of the company's products. The company now is planning raw materials needs for the third quarter, the quarter in which peak sales of Supermix occur. To keep production and sales moving smoothly, the company has the following inventory requirements: a. The finished goods inventory on hand at the end of each...