Answer to Part 1.

DAISY PRODUCTS LIMITED

Production Budget

July August September October
Budgeted Sales 52500 60000 75000 45000
Add: Desired Ending Inventory 13500 15750 11250 9000
Total Needs 66000 75750 86250 54000
Less: Beginning Inventory 15000 13500 15750 11250
Required Production 51000 62250 70500 42750

Ending Inventory = 4,500 + (Following Months sales * 15%)

Answer to Part 3.

DAISY PRODUCTS LIMITED

Raw Materials Purchses Budget

July August September Third Quarter
Required Production 51000 62250 70500 183750
Materials needed per unit 3 3 3 3
Production needs (cc) 153000 186750 211500 551250
Add: Desired Ending Inventory 93375 105750 64125 64125
Total Solvent Q80 needs 246375 292500 275625 615375
Less: Beginning Inventory 81000 93375 105750 81000
Raw Materials to be purchased 165375 199125 169875 534375
Add a comment
Know the answer?
Add Answer to:
Daisy Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia Three cubic centimetres...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT