Question

Daisy Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia.      Three cubic centimetres...

Daisy Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia.

     Three cubic centimetres (cc) of solvent Q80 are required to manufacture each unit of Fineclay, one of the company’s products. The company is now planning raw materials needs for the third quarter, the quarter in which peak sales of Fineclay occur. To keep production and sales moving smoothly, the company has the following inventory requirements:

a.

The finished goods inventory on hand at the end of each month must be equal to 4,350 units of Fineclay plus 20% of the next month’s sales. The finished goods inventory on June 30 is budgeted to be 14,500 units.

b.

The raw materials inventory on hand at the end of each month must be equal to one-half of the following month’s production needs for raw materials. The raw materials inventory on June 30 is budgeted to be 78,300 cc of solvent Q80.

c. The company maintains no work-in-process inventories.
A sales budget for Fineclay for the last six months of the year follows:
Budgeted Sales
in Units
  July 50,750
  August 58,000
  September 72,500
  October 43,500
  November 29,000
  December 14,500
Required:
1. Prepare a production budget for Fineclay for the months of July to October.

      

2. Not available in Connect.
3.

Prepare a budget showing the quantity of solvent Q80 to be purchased for July, August, and September, and for the quarter in total.

       

0 0
Add a comment Improve this question Transcribed image text
Answer #1
1
Daisy Products Limited
Production Budget
July August September October
Budgeted unit sales 50750 58000 72500 43500
Add: Desired ending finished goods inventory 15950 18850 13050 10150
Total needs 66700 76850 85550 53650
Deduct: Beginning finished goods inventory 14500 15950 18850 13050
Required production in units 52200 60900 66700 40600
3
Daisy Products Limited
Raw Material Purchases Budget
July August September Third Quarter
Production needs (cc) 156600 182700 200100 539400
Add: Desired ending raw materials inventory 91350 100050 60900 60900
Total solvent Q80 needs 247950 282750 261000 600300
Deduct: Beginning raw materials inventory 78300 91350 100050 78300
Solvent Q80 purchases (cc) 169650 191400 160950 522000
Add a comment
Know the answer?
Add Answer to:
Daisy Products Limited of Shenzhen, China, manufactures and distributes toys throughout Southeast Asia.      Three cubic centimetres...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT