Question

Sheridan Company estimates that annual manufacturing overhead costs will be $902,000. Estimated annual operating activity bas
Coronado Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On Janua
0 0
Add a comment Improve this question Transcribed image text
Answer #1
1Ans: Sheridan Company
Given Estimated annual manufacturing OH cost is 902000
Est. Annual Operating activity bases are as follows
Direct Labor Cost 400000
Direct Labor Hours 40000
Machine Hours 100000
Required
1. Overhead rate per Direct Labor Cost : Direct Labour Cost/ Total OH Cost
400000/902000
44.35%
2. Overhead rate per Direct Labor Hour   Direct Labour Cost/ Direct Labor Hrs
$400000/40000hrs
$10 per Hr
3. Overhead rate per Direct Machine Hour   Direct Machine Cost/ Direct Mch Hrs
$902000-400000/100000 mch hrs
$ 5.02 per Hr

Note: It is assumed that there only Direct Material and Labor cost forms part of Annual Mnf. OH Cost given.

1Ans: Coronado Company
Given that
Job No. Dir. Material Dir. Labor
50 $12,000 $6,000
51 46800 30000
52 36000 24000
Total $94,800 $60,000
Allocation of other Costs
Particulars Amt(in $) Basis of Allocation Job 50 Job 51 Job 52 Total
Opening Balance of RM             18,000 Dir. Material            2,278            8,886            6,835       18,000
Purchases          1,08,000 Dir. Material          13,671          53,316          41,013    1,08,000
Factory Labor Costs             84,000 Dir. Labor            8,400          42,000          33,600       84,000
Mnf OH
Indirect Materials             20,400       20,400
Indirect Labor             24,000       24,000
Depreciation             14,400       14,400
Orhers             19,200       19,200
Total          2,88,000          24,349      1,04,203          81,448    2,88,000
Given that
Est. Total Mnf OH Cost       10,08,000
Direct Labor Cost          8,40,000
Direct Labor Hrs             24,000
Prior Cost for Job 50
Dr. Material             24,000
Dr. Labor             14,400
Other Costs             19,200
Total             57,600
Current cost             24,349
Total cost for Job 50             81,949
Summary
Total Material cost for 3jobs                      2,44,800
Total Labor cost for 3jobs                      1,58,400
Total other mnf OH Costs                          97,200
Grand Total                      5,00,400
Predetermined Rate 50%
Add a comment
Know the answer?
Add Answer to:
Sheridan Company estimates that annual manufacturing overhead costs will be $902,000. Estimated annual operating activity bases...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Coronado Company uses a job order cost system and applies overhead to production on the basis...

    Coronado Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On Janu 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $24.000, direct labor $14,400, and manufacturing overhead $19,200. As of January 1, Job 49 had been completed at a cost of $108,000 and was part of finished goods inventory. There was a $18,000...

  • r cost system and applies overhead to production on the basis of direct labor costs. On...

    r cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $ 24,000, direct labor $ 14,400, and manufacturing overhead $ 19,200. As of January 1, Job 49 had been completed at a cost of $ 108,000 and was part of finished goods inventory. There was a $ 18,000...

  • Coronado Company uses a job order cost system and applies overhead to production on the basis...

    Coronado Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $ 24,000, direct labor $ 14,400, and manufacturing overhead $ 19,200. As of January 1, Job 49 had been completed at a cost of $ 108,000 and was part of finished goods inventory....

  • Coronado Company uses a job order cost system and applies overhead to production on the basis...

    Coronado Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $24,000, direct labor $14,400, and manufacturing overhead $19,200. As of January 1, Job 49 had been completed at a cost of $108,000 and was part of finished goods inventory. There was a $18,000...

  • part C) c-f Coronado Company uses a job order cost system and applies overhead to production...

    part C) c-f Coronado Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $ 24,000, direct labor $ 14,400, and manufacturing overhead $ 19,200. As of January 1, Job 49 had been completed at a cost of $ 108,000 and was part of...

  • C-F Coronado Company uses a job order cost system and applies overhead to production on the...

    C-F Coronado Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $ 24,000, direct labor $ 14,400, and manufacturing overhead $ 19,200. As of January 1, Job 49 had been completed at a cost of $ 108,000 and was part of finished goods...

  • Coronado Company estimates that annual manufacturing overhead costs will be $828,000. Estimated annual operating activity bases...

    Coronado Company estimates that annual manufacturing overhead costs will be $828,000. Estimated annual operating activity bases are direct labor cost $450,000, direct labor hours 45,000, and machine hours 90,000. Compute the predetermined overhead rate for each activity base. Brief Exercise 15-06 Coronado Company estimates that annual manufacturing overhead costs will be $828,000. Estimated annual operating activity bases are direct labor cost $450,000, direct labor hours 45,000, and machine hours 90,000. Compute the predetermined overhead rate for each activity base. (Round...

  • Sheridan Company uses a job order cost system and applies overhead to production on the basis...

    Sheridan Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. Un January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $ 23,600 direct labor $ 14.160 and manufacturing overhead $ 18,880. As of January 1, Job 49 had been completed at a cost of $ 106,200 and was part of finished goods inventory....

  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $23,200, direct labor $13,920, and manufacturing overhead $18,560. As of January 1, Job 49 had been completed at a cost of $104,400 and was part of finished goods inventory. There was a $17,400...

  • Lott Company uses a job order cost system and applies overhead to production on the basis...

    Lott Company uses a job order cost system and applies overhead to production on the basis of direct labor costs. On January 1, 2020, Job 50 was the only job in process. The costs incurred prior to January 1 on this job were as follows: direct materials $21,600, direct labor $12,960, and manufacturing overhead $17,280. As of January 1, Job 49 had been completed at a cost of $97,200 and was part of finished goods inventory. There was a $16,200...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT