In 1993, Nash Company completed the construction of a building at a cost of $2,040,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $59,200 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $510,000. At that time, it was estimated that the remaining life of the building would be, as originally estimated, an additional 30 years, and that the addition would have a life of 30 years and a salvage value of $20,400. In 2022, it is determined that the probable life of the building and addition will extend to the end of 2053, or 20 years beyond the original estimate.
Compute the annual depreciation to be charged, beginning with 2022. (Round answer to 0 decimal places, e.g. 45,892.)
In 1993, Nash Company completed the construction of building, see the below information
Cost of building in 1994 = $2,040,000
Estimated Usage life = 40 years
Salvage Value = $59,200
In 2004 :
Additional cost of building = $510,000
Additional usage life = 30 years
Estimated Salvage value = $20,400
Depreciation = (Cost of building - Salvage Value)/usage life
Depreciation = (2,040,000 - 59,200)/40
Depreciation = 49,520 per year
From 1994 to 2003 total 10 years so,
cost of building in 2004 =2,040,000-(49,520*10)
cost of building in 2004 = $1,544,800
In 2004, with additional cost
cost = 1,544,800+510,000 .
= 2,054,800
Salvage Value = $79,600
Estimated life = (40-10)+30
Estimated Life = 70 years
From 2004,the estimated life would be till 2073th Year
but in 2022, the life of building will be extended to 2053, 20 years beyond estimated life.
If the life upto 2053,from 2004 the estimated life would be 50 years.
Annual depreciation from 2022 = (2,054,800 - 79,600)/50
= $39,504
In 1993, Nash Company completed the construction of a building at a cost of $2,040,000 and...
In 1993, Nash Company completed the construction of a building at a cost of $2,040,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $59,200 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $510,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Nash Company completed the construction of a building at a cost of $2,040,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $59,200 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $510,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Crane Company completed the construction of a building at a cost of $2,020,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $60,000 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $505,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Bramble Company completed the construction of a building at a cost of $2,280,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $68,800 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $570,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Waterway Company completed the construction of a building at a cost of $2,380,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $71,200 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $595,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Splish Company completed the construction of a building at a cost of $2,480,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $75,200 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $620,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Blossom Company completed the construction of a building at a cost of $2,460,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $74,400 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $615,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Waterway Company completed the construction of a building at a cost of $2,380,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $71,200 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $595,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Sheffield Company completed the construction of a building at a cost of $2,340,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $69,600 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $585,000. At that time, it was estimated that the remaining life of the building would be, as originally...
E11.12 (LO 1, 2) (Depreciation Computation—Addition, Change in Estimate) In 1993, Herman Moore Company completed the construction of a building at a cost of $2,000,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $60,000 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $500,000. At that time, it was estimated that...