In 1993, Waterway Company completed the construction of a
building at a cost of $2,380,000 and first occupied it in January
1994. It was estimated that the building will have a useful life of
40 years and a salvage value of $71,200 at the end of that
time.
Early in 2004, an addition to the building was constructed at a
cost of $595,000. At that time, it was estimated that the remaining
life of the building would be, as originally estimated, an
additional 30 years, and that the addition would have a life of 30
years and a salvage value of $23,800.
In 2022, it is determined that the probable life of the building
and addition will extend to the end of 2053, or 20 years beyond the
original estimate.
Using the straight line method annual depreciation from 1994 to 2003 is $57,720 a year.
Annual depreciation from 2004 to 2021 is $76,760 per year.
Compute the annual depreciation to be charged beginning with 2022. Answer is $28,785 I cannot figure out how they arrived at this answer.
Cost | 2380000 | |
Less: Salvage value | 71200 | |
Depreciable cost | 2308800 | |
Useful life | 40 | |
Annual depreciation from 1994 through 2003 | 57720 | |
Cost | 2380000 | |
Add: Additions | 595000 | |
Total cost | 2975000 | |
Less: Accumulated depreciation from 1994 through 2003 | 577200 | =57720*10 |
Book value, Jan 2004 | 2397800 | |
Less: Salvage value | 95000 | =71200+23800 |
Depreciable cost | 2302800 | |
Useful life | 30 | |
Annual depreciation from 2004 through 2021 | 76760 | |
Book value, Jan 2004 | 2397800 | |
Less: Accumulated depreciation from 2004 through 2021 | 1381680 | =76760*18 |
Book value, Jan 2022 | 1016120 | |
Less: Salvage value | 95000 | =71200+23800 |
Depreciable cost | 921120 | |
Divide by Remaining Useful life | 32 | =50-18 |
Annual depreciation expense—building | 28785 |
In 1993, Waterway Company completed the construction of a building at a cost of $2,380,000 and...
In 1993, Waterway Company completed the construction of a building at a cost of $2,380,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $71,200 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $595,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Splish Company completed the construction of a building at a cost of $2,480,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $75,200 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $620,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Bramble Company completed the construction of a building at a cost of $2,280,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $68,800 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $570,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Blossom Company completed the construction of a building at a cost of $2,460,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $74,400 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $615,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Nash Company completed the construction of a building at a cost of $2,040,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $59,200 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $510,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Crane Company completed the construction of a building at a cost of $2,020,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $60,000 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $505,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Nash Company completed the construction of a building at a cost of $2,040,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $59,200 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $510,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Nash Company completed the construction of a building at a cost of $2,040,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $59,200 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $510,000. At that time, it was estimated that the remaining life of the building would be, as originally...
In 1993, Sheffield Company completed the construction of a building at a cost of $2,340,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $69,600 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $585,000. At that time, it was estimated that the remaining life of the building would be, as originally...
E11.12 (LO 1, 2) (Depreciation Computation—Addition, Change in Estimate) In 1993, Herman Moore Company completed the construction of a building at a cost of $2,000,000 and first occupied it in January 1994. It was estimated that the building will have a useful life of 40 years and a salvage value of $60,000 at the end of that time. Early in 2004, an addition to the building was constructed at a cost of $500,000. At that time, it was estimated that...