Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

Flexible Overhead Budget

Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 11,000 hours of productive capacity in the department:

Variable overhead cost:
   Indirect factory labor $104,500
   Power and light 3,190
   Indirect materials 30,800
      Total variable overhead cost $138,490
Fixed overhead cost:
   Supervisory salaries $48,470
   Depreciation of plant and equipment 30,470
   Insurance and property taxes 19,390
      Total fixed overhead cost 98,330
Total factory overhead cost $236,820

Assuming that the estimated costs for November are the same as for October, prepare a flexible factory overhead cost budget for the Press Department for November for 9,000, 11,000, and 13,000 hours of production. Round your interim computations to the nearest cent, if required. Enter all amounts as positive numbers.

Leno Manufacturing Company
Factory Overhead Cost Budget-Press Department
For the Month Ended November 30
Direct labor hours 9,000 11,000 13,000
Variable overhead cost:
Indirect factory labor $ $ $
Power and light
Indirect materials
Total variable factory overhead $ $ $
Fixed factory overhead cost:
Supervisory salaries $ $ $
Depreciation of plant and equipment
Insurance and property taxes
Total fixed factory overhead $ $ $
Total factory overhead cost $ $ $
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Leno Manufacturing Company Factory Overhead Cost Budget-Press Department For the Month Ended November 30 Direct Labor Hours 9

Add a comment
Know the answer?
Add Answer to:
Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

    Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected Department for October of the current year, during which it expected to require 9,000 hours of productive capacity in the department: Variable overhead cost: Indirect factory labor $88,200 Power and light 2,610 Indirect materials 26,100 Total variable overhead cost $116,910 Fixed overhead cost: Supervisory salaries $40,920 Depreciation of plant and equipment 25,720 Insurance...

  • Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

    Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 9,000 hours of productive capacity in the department: Variable overhead cost:    Indirect factory labor $71,100    Power and light 3,600    Indirect materials 24,300       Total variable overhead cost $99,000 Fixed overhead cost:    Supervisory salaries $34,650    Depreciation of plant and equipment 21,780    Insurance and property taxes 13,860       Total fixed overhead cost 70,290 Total factory...

  • Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

    Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 15,000 hours of productive capacity in the department: Variable overhead cost: Indirect factory labor $121,500 Power and light 6,450 Indirect materials 43,500 Total variable overhead cost $171,450 Fixed overhead cost: Supervisory salaries $60,010 Depreciation of plant and equipment 37,720 Insurance and property taxes 24,000 Total fixed overhead cost 121,730 Total factory...

  • Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

    Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 15,000 hours of productive capacity in the department: Variable overhead cost:    Indirect factory labor $126,000    Power and light 4,350    Indirect materials 42,000       Total variable overhead cost $172,350 Fixed overhead cost:    Supervisory salaries $60,320    Depreciation of plant and equipment 37,920    Insurance and property taxes 24,130       Total fixed overhead cost 122,370 Total factory...

  • Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

    Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 18,000 hours of productive capacity in the department: Variable overhead cost: Indirect factory labor Power and light $144,000 6,480 45,000 $195,480 Indirect materials Total variable overhead cost Fixed overhead cost: Supervisory salaries Depreciation of plant and equipment Insurance and property taxes $68,420 43,010 27,370 Total fixed overhead cost 138,800 Total factory...

  • Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

    Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 18,000 hours of productive capacity in the department: $162,000 5,400 55,800 $223,200 Variable overhead cost: Indirect factory labor Power and light Indirect materials Total variable overhead cost Fixed overhead cost: Supervisory salaries Depreciation of plant and equipment Insurance and property taxes Total fixed overhead cost Total factory overhead cost $78,120 49,100...

  • Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

    Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 14,000 hours of productive capacity in the department: Variable overhead cost:    Indirect factory labor $109,200    Power and light 4,480    Indirect materials 44,800       Total variable overhead cost $158,480 Fixed overhead cost:    Supervisory salaries $55,470    Depreciation of plant and equipment 34,870    Insurance and property taxes 22,190       Total fixed overhead cost 112,530 Total factory...

  • Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

    Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 12,000 hours of productive capacity in the department: Variable overhead cost: Indirect factory labor $99,600 Power and light 5,640 Indirect materials 36,000 Total variable overhead cost $141,240 Fixed overhead cost: Supervisory salaries $49,430 Depreciation of plant and equipment 31,070 Insurance and property taxes 19,770 Total fixed overhead cost 100,270 Total factory...

  • Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

    Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 16,000 hours of productive capacity in the department: Variable overhead cost: Indirect factory labor $115,200 Power and light 6,880 Indirect materials 35,200 Total variable overhead cost $157,280 Fixed overhead cost: Supervisory salaries $55,050 Depreciation of plant and equipment 34,600 Insurance and property taxes 22,020 Total fixed overhead cost 111,670 Total factory...

  • Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press...

    Flexible Overhead Budget Leno Manufacturing Company prepared the following factory overhead cost budget for the Press Department for October of the current year, during which it expected to require 12,000 hours of productive capacity in the department: Variable overhead cost:    Indirect factory labor $88,800    Power and light 5,040    Indirect materials 27,600       Total variable overhead cost $121,440 Fixed overhead cost:    Supervisory salaries $42,500    Depreciation of plant and equipment 26,720    Insurance and property taxes 17,000       Total fixed overhead cost 86,220 Total factory...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT