1) | Predetermined overhead rate per labor hour = ($499200/96000) +$2 | |||||
=$5.2+$2 | ||||||
=$7.2 | per LHs | |||||
Total Job Cost for Job P951 | ||||||
Direct Materials | $ 640 | |||||
Direct Labor | $ 9,600 | |||||
Overhead Cost | $ 720 | |||||
Total | $ 10,960 | |||||
Correct Option: LAST | ||||||
2) | Predetermined overhead rate per machine hour = ($581400/32300 hrs) +$2 | |||||
=$18+ 2 | ||||||
=$20 per machine hour | ||||||
Overhead applied = total machine hours * predetermined overhead rate | ||||||
=40*$20 | ||||||
=$800 | ||||||
Correct Option: FIRST | ||||||
3) | Predetermined overhead rate per labor hour = ($972095/39500) +$6.58 | |||||
=$24.61+ 6.58 | ||||||
=$31.19 per labor hour | ||||||
Correct Option: FIRST | ||||||
4) | Correct Option: FIRST | |||||
Please Upvote.
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per direct labor-hour 70,000 $273,000 $ 6.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 50 100 $ 680 $7,000 The...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per direct labor-hour 72,000 $223,200 $ 3.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 20 100 $ 890 $7,200 The...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 64,000 Total fixed manufacturing overhead cost $358,400 Variable manufacturing overhead per direct labor-hour $ 5.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 20 100 $ 730 $6,400 The...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 64,000 Total fixed manufacturing overhead cost $358,400 Variable manufacturing overhead per direct labor-hour $ 5.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 20 100 $ 730 $6,400 The...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 101,000 Total fixed manufacturing overhead cost $595,900 Variable manufacturing overhead per direct labor-hour $ 3.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 25 100 $ 840 $10,100...
12 Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: 8 01:12:23 Total direct labor-hours 101,000 Total fixed manufacturing overhead cost $595,900 Variable manufacturing overhead per direct labor-hour $ 3.00 Recently, Job P951 was completed with the following characteristics: 25 Number of units in the job Total direct labor-hours Direct materials Direct labor cost 100 $...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 52,000 Total fixed manufacturing overhead cost $291,200 Variable manufacturing overhead per direct labor-hour $ 5.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 20 Total direct labor-hours 100 Direct materials $ 780 Direct labor cost $5,200 The...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per direct labor-hour 94,000 $ 404,200 $ 4.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job Total direct labor-hours Direct materials Direct labor cost 50 100 $ 660 $9,400...
Dehner Corporation uses a job order costing system with a single plantwide predetermined overhead rate based on direct labor hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per direct labor-hour 94, eee $404,200 $ 4.00 Recently. Job P951 was completed with the following characteristics Number of units in the job Total direct labor-hours Direct materials Direct labor cost Se 10e $...
Lupo Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on machine-hours. The company based its predetermined overhead rate for the current year on the following data Total machine-hours Total fixed manufacturing overhead cost Variable manufacturing overhead per machine-hour 31,000 $310, $ Recently, Job T687 was completed with the following characteristics 10 Number of units in the job Total machine-hours Direct materials Direct labor cost $ 730 $1,460 The totaljob cost for Job T687 is...