Question

Nam Construction, a sub-contractor, entered into a contract with the main contractor, Ming Company, on March...


Nam Construction, a sub-contractor, entered into a contract with the main contractor, Ming Company, on March 6, 2018 to provide civil engineering services at the contract fee of $10,000,000. The contract spans three years from 2018 to 2020. Costs incurred, estimated costs to complete at year-end, billings and cash collections for the life of the contract are shown below:
2018 2019 2020
Costs incurred during the year $ 4,800,000 $ 2,200,000 $ 1,800,000
Estimated costs to complete as of year-end 4,200,000 2,050,000 —
Billings during the year 3,300,000 3,200,000 3,500,000
Cash collections during the year 2,800,000 3,000,000 3,700,000
Required:
1. Using costs as a measure of the extent to which performance obligations are satisfied over time, what is the percentage of completion at the end of 2018, 2019, and 2020?
2. How much revenue related to this contract will Nam report in its 2018, 2019, and 2020 income statements?
3. What is the amount of contract profit or loss to be recognized for the Ming contract during 2018, 2019, and 2020 income statements?
4. Prepare all necessary journal entries for each of the years. Assume that construction costs are paid in cash.
5. Prepare a partial income statement to show the revenue and expenses arising from this contract in 2018, 2019, and 2020.
6. Prepare a partial but balanced statement of financial position at the end of 2018, 2019, and 2020 to show the items related to the contract, stating clearly contract asset or contract liability and other relevant accounts. Include cash balances and accumulated retained earnings.
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks!
Nam Construction
Ans to 1 Calculation of Percentage complete
Particulars 2018 2019 2020
Contract Price         10,000,000       10,000,000        10,000,000 A
Cost Incurred during the year           4,800,000          2,200,000          1,800,000 B
Estimated cost to complete           4,200,000          2,050,000                        -   C
Cost Incurred to date           4,800,000          7,000,000          8,800,000 D
(Sum total of the cost incurred during the year)
Estimated total cost           9,000,000          9,050,000          8,800,000 E=C+D
Percentage complete 53.33% 77.35% 100.00% F=D/E
(Cost Incurred to date/Estimated total cost)
Answer 2
Revenue to be recognized           5,333,333          2,401,473          2,265,193 G
(Contract Price*Percentage complete)- revenue previously recognized
Year 2018: 53.33% completed. Revenue recognized = 53.33% x $ 10,000,000 = $ 5,333,333.
Year 2019: 77.35% completed. Revenue recognized = 77.35% x $ 10,000,000 – $ 5,333,333 (previously recognized) = $ 2,401,473.
Year 2020: 100% completed. Revenue recognized = 100% x $ 10,000,000 – $ 5,333,333- $ 2,401,473 (previously recognized) = $ 2,265,193.
Answer 3
Gross Profit/(Loss)              533,333             201,473             465,193 H=G-B
Billings during the year     3,300,000.00    3,200,000.00    3,500,000.00
Collection during the year     2,800,000.00    3,000,000.00    3,700,000.00
2018 2019 2020
Ans to 4 Journal Entries Debit $ Credit $ Debit $ Credit $ Debit $ Credit $
Costs Incurred CIP (Work-in-progress)           4,800,000 2,200,000     1,800,000
Cash 4,800,000 2,200,000     1,800,000
Billing Accounts Receivable           3,300,000 3,200,000     3,500,000
Billing on CIP 3,300,000 3,200,000     3,500,000
Receiving Payments Cash           2,800,000 3,000,000     3,700,000
Accounts Receivable 2,800,000 3,000,000     3,700,000
Period end adjustments for Revenue Construction Expense           4,800,000 2,200,000     1,800,000
(Gross Profit entry) CIP (Work-in-progress)              533,333      201,473        465,193
Construction Revenue 5,333,333 2,401,473     2,265,193
Closing Entry Billing on CIP 10,000,000
CIP (Work-in-progress) 10,000,000
Answer 5
Income Statement 2018 2019 2020
Revenue recognized           5,333,333          2,401,473          2,265,193
Costs Incurred           4,800,000          2,200,000          1,800,000
Gross Profit/(Loss)              533,333             201,473             465,193
Workings for Balance Sheet
CIP (Work-in-progress)
Account Amount ($)
Cash                                 4,800,000
Construction Revenue                                    533,333
Balance at the end of 2018                                 5,333,333
Cash                                 2,200,000
Construction Revenue                                    201,473
Balance at the end of 2019                                 7,734,807
Cash                                 1,800,000
Construction Revenue                                    465,193
Billing on CIP                             (10,000,000)
Balance at the end of 2020                                               -  
Accounts Receivable
Account Amount ($)
Billing on CIP                                 3,300,000
Cash                                (2,800,000)
Balance at the end of 2018                                    500,000
Billing on CIP                                 3,200,000
Cash                                (3,000,000)
Balance at the end of 2019                                    700,000
Billing on CIP                                 3,500,000
Cash                                (3,700,000)
Balance at the end of 2020                                    500,000
Billing on CIP
Account Amount ($)
Accounts Receivable                                 3,300,000
Balance at the end of 2018                                 3,300,000
Accounts Receivable                                 3,200,000
Balance at the end of 2019                                 6,500,000
Accounts Receivable                                 3,500,000
CIP (Work-in-progress)                             (10,000,000)
Balance at the end of 2020                                               -  
Answer 6
Balance Sheet (Partial) 2018 2019 2020
Contract Assets:
CIP (Work-in-progress)           5,333,333          7,734,807                        -  
Accounts Receivable              500,000             700,000       500,000.00
Total          5,833,333         8,434,807             500,000
Contract Liabilities:
Billing on CIP     3,300,000.00    6,500,000.00                        -  
Total     3,300,000.00 6,500,000.00                        -  
Add a comment
Know the answer?
Add Answer to:
Nam Construction, a sub-contractor, entered into a contract with the main contractor, Ming Company, on March...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,490,000 5,810,000 2,030,000 1,815,000 2019 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. 3....

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000 3,900,000 4,285,000 Westgate recognizes revenue over time according to...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,059,000 $ 2,627,000 $ 2,655,400 Estimated costs to complete as of year-end 5,041,000 2,414,000 0 Billings during the year 2,190,000 2,496,000 5,314,000 Cash collections during the year 1,895,000 2,400,000 5,705,000 Westgate recognizes revenue over time according to...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa ...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,542,000 $ 3,772,000 $ 2,074,600 Estimated costs to complete as of year-end 5,658,000 1,886,000 0 Billings during the year 2,020,000 4,294,000 3,686,000 Cash collections during the year 1,810,000 3,800,000 4,390,000 Westgate recognizes revenue over time according to...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: during the year $2,100,000 $2,450,000 $2,695,000 Estimated costs to complete as of year-end Billings during the year Cash collections during the year 4,900,000 2,450,000 2,200,000 2,350,000 5,450,000 1,900,000 2,300,000 5, 800,000 3 28 Westgate recognizes revenue over time according to percentage of completion Required: ances 1....

  • in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...

  • In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...

    In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,074,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $ 2,542,000 5,658,000 2,020,000 1,810,000 2019 $3,772,000 1,886,000 4,294,000 3,800,000 3,686,000 4,390,000 Westgate recognizes revenue over time according to percentage of completion....

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT