Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks! |
Nam Construction | ||||
Ans to 1 | Calculation of Percentage complete | |||
Particulars | 2018 | 2019 | 2020 | |
Contract Price | 10,000,000 | 10,000,000 | 10,000,000 | A |
Cost Incurred during the year | 4,800,000 | 2,200,000 | 1,800,000 | B |
Estimated cost to complete | 4,200,000 | 2,050,000 | - | C |
Cost Incurred to date | 4,800,000 | 7,000,000 | 8,800,000 | D |
(Sum total of the cost incurred during the year) | ||||
Estimated total cost | 9,000,000 | 9,050,000 | 8,800,000 | E=C+D |
Percentage complete | 53.33% | 77.35% | 100.00% | F=D/E |
(Cost Incurred to date/Estimated total cost) | ||||
Answer 2 | ||||
Revenue to be recognized | 5,333,333 | 2,401,473 | 2,265,193 | G |
(Contract Price*Percentage complete)- revenue previously recognized | ||||
Year 2018: 53.33% completed. Revenue recognized = 53.33% x $ 10,000,000 = $ 5,333,333. | ||||
Year 2019: 77.35% completed. Revenue recognized = 77.35% x $ 10,000,000 – $ 5,333,333 (previously recognized) = $ 2,401,473. | ||||
Year 2020: 100% completed. Revenue recognized = 100% x $ 10,000,000 – $ 5,333,333- $ 2,401,473 (previously recognized) = $ 2,265,193. | ||||
Answer 3 | ||||
Gross Profit/(Loss) | 533,333 | 201,473 | 465,193 | H=G-B |
Billings during the year | 3,300,000.00 | 3,200,000.00 | 3,500,000.00 | |
Collection during the year | 2,800,000.00 | 3,000,000.00 | 3,700,000.00 |
2018 | 2019 | 2020 | |||||||
Ans to 4 | Journal Entries | Debit $ | Credit $ | Debit $ | Credit $ | Debit $ | Credit $ | ||
Costs Incurred | CIP (Work-in-progress) | 4,800,000 | 2,200,000 | 1,800,000 | |||||
Cash | 4,800,000 | 2,200,000 | 1,800,000 | ||||||
Billing | Accounts Receivable | 3,300,000 | 3,200,000 | 3,500,000 | |||||
Billing on CIP | 3,300,000 | 3,200,000 | 3,500,000 | ||||||
Receiving Payments | Cash | 2,800,000 | 3,000,000 | 3,700,000 | |||||
Accounts Receivable | 2,800,000 | 3,000,000 | 3,700,000 | ||||||
Period end adjustments for Revenue | Construction Expense | 4,800,000 | 2,200,000 | 1,800,000 | |||||
(Gross Profit entry) | CIP (Work-in-progress) | 533,333 | 201,473 | 465,193 | |||||
Construction Revenue | 5,333,333 | 2,401,473 | 2,265,193 | ||||||
Closing Entry | Billing on CIP | 10,000,000 | |||||||
CIP (Work-in-progress) | 10,000,000 |
Answer 5 | |||
Income Statement | 2018 | 2019 | 2020 |
Revenue recognized | 5,333,333 | 2,401,473 | 2,265,193 |
Costs Incurred | 4,800,000 | 2,200,000 | 1,800,000 |
Gross Profit/(Loss) | 533,333 | 201,473 | 465,193 |
Workings for Balance Sheet | |
CIP (Work-in-progress) | |
Account | Amount ($) |
Cash | 4,800,000 |
Construction Revenue | 533,333 |
Balance at the end of 2018 | 5,333,333 |
Cash | 2,200,000 |
Construction Revenue | 201,473 |
Balance at the end of 2019 | 7,734,807 |
Cash | 1,800,000 |
Construction Revenue | 465,193 |
Billing on CIP | (10,000,000) |
Balance at the end of 2020 | - |
Accounts Receivable | |
Account | Amount ($) |
Billing on CIP | 3,300,000 |
Cash | (2,800,000) |
Balance at the end of 2018 | 500,000 |
Billing on CIP | 3,200,000 |
Cash | (3,000,000) |
Balance at the end of 2019 | 700,000 |
Billing on CIP | 3,500,000 |
Cash | (3,700,000) |
Balance at the end of 2020 | 500,000 |
Billing on CIP | |
Account | Amount ($) |
Accounts Receivable | 3,300,000 |
Balance at the end of 2018 | 3,300,000 |
Accounts Receivable | 3,200,000 |
Balance at the end of 2019 | 6,500,000 |
Accounts Receivable | 3,500,000 |
CIP (Work-in-progress) | (10,000,000) |
Balance at the end of 2020 | - |
Answer 6 | |||
Balance Sheet (Partial) | 2018 | 2019 | 2020 |
Contract Assets: | |||
CIP (Work-in-progress) | 5,333,333 | 7,734,807 | - |
Accounts Receivable | 500,000 | 700,000 | 500,000.00 |
Total | 5,833,333 | 8,434,807 | 500,000 |
Contract Liabilities: | |||
Billing on CIP | 3,300,000.00 | 6,500,000.00 | - |
Total | 3,300,000.00 | 6,500,000.00 | - |
Nam Construction, a sub-contractor, entered into a contract with the main contractor, Ming Company, on March...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,008,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,490,000 5,810,000 2,030,000 1,815,000 2019 $3,984,000 1,826,000 4,444,000 3,900,000 3,526,000 4,285,000 Westgate recognizes revenue over time according to percentage of completion. 3....
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,490,000 $ 3,984,000 $ 2,008,600 Estimated costs to complete as of year-end 5,810,000 1,826,000 0 Billings during the year 2,030,000 4,444,000 3,526,000 Cash collections during the year 1,815,000 3,900,000 4,285,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,059,000 $ 2,627,000 $ 2,655,400 Estimated costs to complete as of year-end 5,041,000 2,414,000 0 Billings during the year 2,190,000 2,496,000 5,314,000 Cash collections during the year 1,895,000 2,400,000 5,705,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,542,000 $ 3,772,000 $ 2,074,600 Estimated costs to complete as of year-end 5,658,000 1,886,000 0 Billings during the year 2,020,000 4,294,000 3,686,000 Cash collections during the year 1,810,000 3,800,000 4,390,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,581,000 $ 2,347,000 $ 3,049,200 Estimated costs to complete as of year-end 6,319,000 2,772,000 0 Billings during the year 2,090,000 2,838,000 5,072,000 Cash collections during the year 1,845,000 2,900,000 5,255,000 Westgate recognizes revenue over time according to...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: during the year $2,100,000 $2,450,000 $2,695,000 Estimated costs to complete as of year-end Billings during the year Cash collections during the year 4,900,000 2,450,000 2,200,000 2,350,000 5,450,000 1,900,000 2,300,000 5, 800,000 3 28 Westgate recognizes revenue over time according to percentage of completion Required: ances 1....
in 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,100,000 $ 2,450,000 $ 2,695,000 Estimated costs to complete as of year-end 4,900,000 2,450,000 0 Billings during the year 2,200,000 2,350,000 5,450,000 Cash collections during the year 1,900,000 2,300,000 5,800,000 Westgate recognizes revenue over time according to...
On February 1, 2018, Arrow Construction Company entered into a
three-year construction contract to build a bridge for a price of
$8,125,000. During 2018, costs of $2,050,000 were incurred, with
estimated costs of $4,050,000 yet to be incurred. Billings of
$2,560,000 were sent, and cash collected was $2,300,000. In 2019,
costs incurred were $2,560,000 with remaining costs estimated to be
$3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was
collected. The project was completed in 2020 after additional costs
of...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $2,074,600 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $ 2,542,000 5,658,000 2,020,000 1,810,000 2019 $3,772,000 1,886,000 4,294,000 3,800,000 3,686,000 4,390,000 Westgate recognizes revenue over time according to percentage of completion....
On February 1, 2018, Arrow Construction Company entered into a
three-year construction contract to build a bridge for a price of
$8,125,000. During 2018, costs of $2,050,000 were incurred, with
estimated costs of $4,050,000 yet to be incurred. Billings of
$2,560,000 were sent, and cash collected was $2,300,000. In 2019,
costs incurred were $2,560,000 with remaining costs estimated to be
$3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was
collected. The project was completed in 2020 after additional costs
of...