Question

At Happy Air, the standard quantity of labor is 22 hours per refrigeration unit. The standard wage rate is $35. In July, the company produced 77 refrigeration units and incurred 2,100 labor hours at a cost of $71,400.

Calculate the labor rate variance and the labor efficiency variance. Indicate whether the variances are favorable or unfavorable. (Round intermediate calculations to 2 decimal places, e.g. 14.37 and final answers to 0 decimal places, e.g. 125. Enter all variances as a positive number.)

Labor Rate Variance Favorable Labor Efficiency Variance Favorable

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer

  • Labor Rate Variance = $ 2100 Favourable

Labor Rate Variance

(

Standard Rate

-

Actual Rate

)

x

Actual Labor Hours

(

$                              35.00

-

$                    34.00

)

x

2100

2100

Variance

$              2,100.00

Favourable-F

  • Labor Efficiency Variance = $ 14210 Unfavourable

Labour Efficiency Variance

(

Standard Hours

-

Actual Hours

)

x

Standard Rate

(

1694

-

2100

)

x

$                        35.00

-14210

Variance

$            14,210.00

Unfavourable-U

Add a comment
Know the answer?
Add Answer to:
At Happy Air, the standard quantity of labor is 22 hours per refrigeration unit. The standard...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Lawn Band Uniforms uses a standard costing system. The standard material and labor costs for producing...

    Lawn Band Uniforms uses a standard costing system. The standard material and labor costs for producing a marching band hat are as follows: Materials (0.90 yards × $12.20) $10.98 Direct labor (1.20 hours × $13.70) $16.44 During May, the company produced 3,290 band hats; 4,340 yards of material were purchased for $44,702, and 3,300 yards of material were used in production. Also during May, 4,710 direct labor hours were worked at a cost of $61,230. Calculate material price and quantity...

  • Exercise 11-9 Pukalani Band Uniforms uses a standard costing system. The standard material and labor costs...

    Exercise 11-9 Pukalani Band Uniforms uses a standard costing system. The standard material and labor costs for producing a marching band hat are as follows: Materials (0.90 yards x $11.40) Direct labor (1.20 hours x $13.80) $10.26 $16.56 During May, the company produced 3,340 band hats; 3,870 yards of material were purchased for $41,022, and 3,050 yards of material were used in production. Also during May, 4,240 direct labor hours were worked at a cost of $59,360. Calculate material price...

  • Amos, Inc. uses a standard cost system with the following labor standards for one unit of...

    Amos, Inc. uses a standard cost system with the following labor standards for one unit of product: standard hours 0.3 and standard wage rate $8. During January, Amos incurred 5,767 hours of direct labor and paid $45,575 in wages in production of 18,900 units. Calculate the direct labor rate and efficiency variances and indicate whether the variances are favorable or unfavorable. Direct labor rate variance $    favorable Direct labor efficiency variance $ unfavorable

  • Cinrich Band Uniforms uses a standard costing system. The standard material and labor costs for producing a marching ba...

    Cinrich Band Uniforms uses a standard costing system. The standard material and labor costs for producing a marching band hat are as follows: Materials (0.90 yards x $11.50) Direct labor (1.20 hours x $13.20) $10.35 $15.84 During May, the company produced 3,520 band hats; 3,770 yards of material were purchased for $36,946, and 2,900 yards of material were used in production. Also during May, 4,300 direct labor hours were worked at a cost of $60,200. Calculate material price and quantity...

  • Richetti Band Uniforms uses a standard costing system. The standard material and labor costs for producing...

    Richetti Band Uniforms uses a standard costing system. The standard material and labor costs for producing a marching band hat are as follows: Materials (0.90 yards × $11.70) $10.53 Direct labor (1.20 hours × $13.30) $15.96 During May, the company produced 3,770 band hats; 4,400 yards of material were purchased for $42,240, and 3,270 yards of material were used in production. Also during May, 4,790 direct labor hours were worked at a cost of $57,480. Calculate material price and quantity...

  • The standard labor cost in the production of a pair of Beca Brand athletic shoes is...

    The standard labor cost in the production of a pair of Beca Brand athletic shoes is 0.40 hours at $14.00 per hour. During the month of June, 24,630 pairs were produced. Actual labor costs were $96,240 for 8,020 hours. Compute the labor rate and labor efficiency variances for the month of June. (Round actual wage rate to 2 decimal places, e.g. 15.25 and final answers to 0 decimal places, e.g. 125. Enter all variances as a positive number.) Labor Rate...

  • Reed Corp. has set the following standard direct materials and direct labor costs per unit for...

    Reed Corp. has set the following standard direct materials and direct labor costs per unit for the product it manufactures. Direct materials (16 lbs. @ $5 per lb.) $80 Direct labor (4 hrs. @ $15 per hr.) $60 During June the company incurred the following actual costs to produce 9,000 units. Direct materials (146,700 lbs. @ $4.75 per lb.) $696,825 Direct labor (40,300 hrs. @ $15.10 per hr.). $608,530 AH = Actual Hours SH = Standard Hours AR = Actual...

  • Reed Corp. has set the following standard direct materials and direct labor costs per unit for...

    Reed Corp. has set the following standard direct materials and direct labor costs per unit for the product it manufactures. Direct materials (10 lbs. $3 per lb.) Direct labor (2 hrs. $12 per hr.) points During June the company incurred the following actual costs to produce 9,000 units. Bo Direct materials (92,000 lbs. $2.95 per lb.) Direct labor (18.00 hrs. $12.05 per he.) $271.000 226,340 int P References AQ - Actual Quantity SQ - Standard Quantity AP - Actual Price...

  • Hutto Corp. has set the following standard direct materials and direct labor costs per unit for...

    Hutto Corp. has set the following standard direct materials and direct labor costs per unit for the product it manufactures. Direct materials (15 lbs. $4 per lb.) Direct labor ( hrs. $15 per hr.) Sosis 15.) 588 points During May the company incurred the following actual costs to produce 9,000 units. Direct materiale 18.000 lbs. ).75 per 1.) Direct labor 31.000 hrs. 515.10 per hr.). $517.500 468,100 AQ - Actual Quantity SQ - Standard Quantity AP Actual Price SP Standard...

  • Hutto Corp, has set the following standard direct materials and direct labor costs per unit for...

    Hutto Corp, has set the following standard direct materials and direct labor costs per unit for the product it manufactures. Direct materials (15 lbs. $4 per lb.) Direct labor (3 hrs. $15 per hr.) $60 During May the company incurred the following actual costs to produce 8,200 units. Direct materials (126,000 lbs. $3.50 per lb.) Direct labor (28,000 hrs. $15.10 per hr.). $478, 800 422,800 AH = Actual Hours SH - Standard Hours AR - Actual Rate SR Standard Rate...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT