(1) | Standard Cost per unit | |||||
Direct material | $40 | (5*8) | ||||
Direct labor | $34 | (2*17) | ||||
Overhead | $24 | (2*12) | ||||
$98 | ||||||
(2) | Total standard cost for 8700 units | $852,600 | (98*8700) | |||
Total actual cost | ||||||
Direct material | $355,590 | |||||
Direct labor | $297,540 | |||||
Overhead | $214,700 | |||||
Actual cost | $867,830 | |||||
Total cost variance | $15,230 | Unfavourable | (867,830-852,600) | |||
Direct material price variance | (SP-AP)*AQ | |||||
(8-8.1)*43,900 | ||||||
-4390 | ||||||
4390 | Unfavourable | |||||
Direct material quantity variance | (SQ-AQ)*SP | |||||
(8700*5-43,900)*8 | ||||||
(43,500-43,900)*8 | ||||||
-3200 | ||||||
3200 | Unfavourable |
Required information [The following information applies to the questions displayed below.) A manufactured product has the...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard 7 lbs. @ $8 per lb. 2 hrs. @ $15 per hr. 2 hrs. @ $11 per hr. Actual 61,300 lbs. @ $8.10 per lb. 17,100 hrs. @ $15.40 per hr. $ 197,500 8,700 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of each variance...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard 6 lbs. @ $8 per lb. 3 hrs. @ $17 per hr. 3 hrs. @ $13 per hr. Actual 43,100 lbs. @ $8.10 per lb. 21,100 hrs. @ $17.40 per hr. $282,800 7,100 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of each variance by...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (7 lbs. @ $8 per lb.) (2 hrs. @ $15 per hr.) (2 hrs. @ $11 per hr.) Actual 55,900 lbs. @ $8.10 per lb. 15,500 hrs. @ $15.40 per hr. $179, 700 7,900 Compute the direct materials price variance and the direct materials quantity variance. Indicate whether each variance is favorable...
Required information (The following information applies to the questions displayed below.) A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. @ $8 per lb.) (2 hrs. $17 per hr.) (2 hrs. $12 per hr.) Actual 52,200 lbs. @ $8.10 per lb. 16,900 hrs. $17.60 per hr. $212,200 8,600 (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute the total cost variance for June. Indicate...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. @ $8 per lb.) (3 hrs. @ $16 per hr.) (3 hrs. @ $12 per hr.) Actual 49,000 lbs. @ $8.10 per lb. 23,900 hrs. @ $16.50 per hr. $297,500 8,100 (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute the total cost variance...
Required information [The following information applies to the questions displayed below] A manufactured product has the following information for June. Direct materials Direct labor Overhead Units manufactured Standard (6 lbs. @ $7 per lb.) (2 hrs. $16 per hr.) (2 hrs. @ $13 per hr.) Actual 44.3e9 lbs. @ $7.10 per lb. 14,300 hrs. $16.50 per hr. $196,700 7,300 (1) Compute the standard cost per unit Direct materials Direct labor Overhead Total (2) Compute the total cost variance for June,...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard (6 1bs. $8 per lb.) (3 hrs. $16 per hr.) (3 hrs. $12 per hr.) Actual 49,000 lbs. $8.10 per lb. 24,000 hrs. $16.40 per hr. Direct materials Direct labor Overhead $297,200 Units manufactured 8,100 Compute the direct materials price variance and the direct materials quantity variance. Indicate whether each variance is favorable or unfavorable. AQ = Actual Quantity...
Required information [The following information applies to the questions displayed below. A manufactured product has the following information for June. Direct materials 1 Actual lbs. @ $7.20 per 9 54,400 lb. Standard (7 lbs. @ $7 per lb.) (3 hrs. @ $15 per hr.) (3 hrs. @ $12 per hr.) Direct labor Overhead Units manufactured 32 saa hrs. @ $15.50 per 22,8001 hr. $283,300 7,700 (1) Compute the standard cost per unit. Direct materials Direct labor Overhead Total (2) Compute...
Required information The following information applies to the questions displayed below) A manufactured product has the following information for June. Standard Actual Direct materials 7 lbs. @ $8 per lb. 51,lbs. $8.10 per 24 hrs. @ $15.40 per Direct labor 3 hrs. @ $15 per hr. 21,400 hr. Overhead 3 hrs. @ $13 per hr. $286,400 Units manufactured 7,200 Compute the direct materials price variance and the direct materials quantity variance Indicate the effect of each variance by selecting for...
Required information [The following information applies to the questions displayed below.] A manufactured product has the following information for June. Standard Actual Direct materials 5 lbs. @ $9 per lb. 40,400 lbs. @ $9.20 per lb. Direct labor 3 hrs. @ $15 per hr. 23,700 hrs. @ $15.60 per hr. Overhead 3 hrs. @ $12 per hr. $ 294,800 Units manufactured 8,000 Compute the direct materials price variance and the direct materials quantity variance. (Indicate the effect of each variance...